Unfinished resettlement infrastructure for Tuyen Quang Expressway

Việt Bắc |

Tuyen Quang - Although they have moved to resettlement areas for a long time, giving up land for expressway projects, many households have not really stabilized their lives.

Unfinished resettlement infrastructure

As one of the few households that have moved to the Dong Thang resettlement area, Nhu Khe commune, Yen Son district (Tuyen Quang) for nearly a year now, Ms. Doan Thi Dinh is not sure when the construction in this resettlement area will be completed.

Previously, because the resettlement area had not yet completed the site while the old residence had been handed over for the Tuyen Quang - Phu Tho expressway project, Ms. Dinh had to rent a place to live for more than a year.

Dong Thang resettlement area serving the evacuation of Tuyen Quang - Phu Tho expressway is still unfinished after nearly 3 years of construction.

"I moved here in early April 2024, and until now, I still see the infrastructure unfinished like that, they have been working for a few days and then they are leaving it. There is still no clean water, we have to use well water to drill the limestone, life is very inconvenient," Ms. Dinh lamented.

Dong Thang resettlement area has an area of over 5 hectares, providing accommodation for nearly 40 households subject to land acquisition for the Tuyen Quang - Phu Tho expressway project. Up to now, the expressway has been in operation for more than a year but the infrastructure of the resettlement area is still unfinished, and the completion date is unknown.

Recorded at the end of March 2025, Dong Thang resettlement area has only had nearly 10 households moving in, some other households are constructing houses. Unfinished traffic roads, clean water pipes, drainage culverts, and construction materials are scattered.

Vat lieu xay dung de ngon ngang, cac hang muc xay dung do dang va khong co hoat dong thi cong tai khu TDC Dong Thang. Anh: Viet Bac.
Materials are left lying around, construction items are unfinished and there are no construction activities in Dong Thang resettlement area. Photo: Viet Bac.

According to the investigation, Dong Thang Resettlement Area is invested by the Yen Son District Construction Management Board, the construction unit is Hoang Long Company Limited. Although still in the construction phase, at the time of recording this resettlement area, no construction activities were taking place.

Similar situation in the resettlement areas of Tuyen Quang - Ha Giang expressway in Ham Yen district, infrastructure is messy and only a few households have moved to live while construction work is sluggish.

Ms. Luong Thi Uong (Bua Nghiao resettlement area, Phu Luu commune, Ham Yen) said that her family has moved to the resettlement area for more than a year but lacks everything. The entire area was planned for 48 households, but so far only 2 households have lived there.

Nhung duong day dien tam bo nguoi dan khu TDC xa Phu Luu tu keo. Anh: Viet Bac.
The temporary power lines were pulled by the people of the resettlement area of Phu Luu commune. Photo: Viet Bac.

"There is no clean water, people have to drill wells themselves, electricity is temporarily dragged by themselves, the two houses sharing a meter are very inconvenient, the road is unfinished, it is not known when it will be completed," Ms. Ung worried.

Slow progress

Go Danh resettlement area, Nhu Khe commune (Yen Son district) is considered one of the projects behind schedule. The project is represented by the Yen Son District Construction Investment Project Management Board. The construction unit of the Joint Venture of Duc Anh Company - Hoang Ha Company - Tho Son Company.

Go Danh resettlement area started on January 5, 2024, and was completed in 390 days. However, according to the reporter's records at the end of March 2025, the construction was very sluggish, with many unfinished items. At some points, no construction activities were carried out.

Khu TDC Go Danh, xa Nhu Khe, Yen Son (Tuyen Quang) phuc vu di dan du an cao toc Tuyen Quang - Ha Giang nhung dang cham tien do. Anh: Viet Bac.
The resettlement area of Nhu Khe and Yen Son communes (Tuyen Quang) serves the evacuation of people for the Tuyen Quang - Ha Giang expressway project but is behind schedule. Photo: Viet Bac.

Although there is no basic infrastructure such as roads, electricity, and water, due to the urgent need for housing, at least 3 households subject to relocation have started building houses in Go Danh resettlement area despite risks and inconveniences.

"The old house has been handed over to the state for road construction, and there is no shelter and they are currently having to stay. Knowing that the resettlement area is not yet completed but the houses have been built, it is inconvenient to do many things but there is no other choice," said a household in Go Danh resettlement area.

According to report No. 116 dated March 18, 2025 of the investor on the construction progress of Go Danh resettlement area, the volume of items such as leveling and new traffic infrastructure has reached 90%, construction of power lines and new transformer stations has reached 20%.

Cac hang muc xay dung khu TDC Go Danh deu dang do, cham tien do. Anh: Viet Bac.
The construction items of Go Danh resettlement area are all unfinished and behind schedule. Photo: Viet Bac.

"After committing the progress in the minutes dated February 5, 2025, the contractors have organized the construction of unfinished items, however, the construction progress is very slow compared to the commitment and the progress of the signed contract," the investor's report stated.

Faced with this situation, the investor has reported and proposed that the People's Committee of Yen Son district give instructions on strictly handling the construction contractor behind schedule.

On March 20, at a meeting with reporters, Mr. Pham Quang Duc - Deputy Director of the Management Board of the Construction Investment Project Management Board of Yen Son district admitted that there was a delay in the progress of some construction works of the expressway resettlement area in the area.

"In addition to the unfavorable weather conditions such as heavy rain in 2024, there are also problems with legal regulations on exploitation and handling of excavated soil volume for embankment in resettlement areas. However, there are also some cases where contractors have not proactively accelerated the construction progress," said Mr. Duc.

According to the reporter's research, to implement the Tuyen Quang - Ha Giang expressway project, Tuyen Quang province has approved the construction of 24 resettlement areas for 479 households subject to housing relocation. Of which, the most is in Ham Yen district with 19 areas.

Up to now, in most of the resettlement areas, the number of households moving to live is very small, including the reason that the resettlement areas have not completed infrastructure, land and the work of granting land use right certificates to people is still slow.

Việt Bắc
TIN LIÊN QUAN

Binding of key transport projects in Tuyen Quang

|

Many key transport projects in Tuyen Quang province are facing difficulties in site clearance, which risks affecting the completion progress.

Risk of breaking the progress of site clearance for Tuyen Quang Expressway

|

The Tuyen Quang - Ha Giang Expressway is still nearly 5.3km uncleared, while the deadline for this must be completed before March 31.

Struggling on the side of the billion-dollar road resettlement area in Thai Nguyen

|

The fact that the resettlement area has not completed enough infrastructure and lacks electricity and water has caused many households in Phuc Thuan commune (Pho Yen city) to struggle to live.

Vietnamese tourists are required to declare online when traveling to Thailand

|

From May 1, all international tourists traveling to Thailand must fill in their digital entry cards before entering the country. This is something Vietnamese tourists need to pay attention to.

The Ministry of Construction has many violations when adjusting the planning of the capital area

|

The Government Inspectorate has just pointed out many violations in adjusting the Construction Planning of the Capital Region.

The Inspection Committee proposes to discipline the former Vice Chairman of the Dong Nai Provincial People's Committee

|

The Provincial Party Committee's Inspection Committee proposed to discipline former Vice Chairman of Dong Nai Provincial People's Committee Vo Van Chanh for related land violations.

Ho Chi Minh City sidewalks "transformed", people are excited about clean and beautiful walking paths

|

HCMC - After the renovation process, many sidewalks in the city center have taken on a new look, people are excited because they have a clean and beautiful walking space.

Hanoi Police lost the first leg of the Southeast Asian Cup C1 semi-final

|

Hanoi Police lost 0-1 to PSM Makassar in the first leg of the 2024-2025 Southeast Asian Cup C1 semi-final on the evening of April 2.

Binding of key transport projects in Tuyen Quang

Việt Bắc |

Many key transport projects in Tuyen Quang province are facing difficulties in site clearance, which risks affecting the completion progress.

Risk of breaking the progress of site clearance for Tuyen Quang Expressway

Việt Bắc |

The Tuyen Quang - Ha Giang Expressway is still nearly 5.3km uncleared, while the deadline for this must be completed before March 31.