Unfinished resettlement, bottleneck in the progress of Tuyen Quang expressway

Việt Bắc |

The delay in relocating people to resettlement areas and site clearance is a bottleneck that needs to be removed to ensure the progress of the Tuyen Quang - Ha Giang expressway.

As Lao Dong has reported, many resettlement areas (TDC) of the expressway in Tuyen Quang are still behind schedule, some areas have people living but lack basic infrastructure such as electricity, clean water or unstable geology.

Meanwhile, the work of issuing land use right certificates (LURCs) in the resettlement area is still slow, causing many households to refuse to move from their old residences. This has greatly affected site clearance and progress of projects, especially the Tuyen Quang - Ha Giang expressway.

According to PV's records in Ham Yen district (Tuyen Quang), the locality has nearly 50km of Tuyen Quang - Ha Giang expressway running through 19 resettlement areas built for 288 households subject to relocation.

However, by the end of March 2025, only 170 households had been allocated resettlement land, the rest had not been allocated land and had not been relocated for resettlement, many resettlement areas had under construction and infrastructure. This makes it difficult to hand over the site to the contractors, affecting the project progress.

Mat bang cao toc Tuyen Quang - Ha Giang ban giao theo kieu “xoi do” dan toi viec thi cong gap nhieu kho khan. Anh: Viet Bac.
The site of the Tuyen Quang - Ha Giang expressway handed over in the " sticky rice and bean" style has led to many difficulties in construction. Photo: Viet Bac.

Talking with reporters, Mr. Le Van Thai - Director of the Ham Yen District Construction Investment Project Management Board said that difficulties in moving people to resettlement areas are being actively resolved.

According to Mr. Thai, the resettlement areas in the area have not yet been connected to the national grid even though the infrastructure of the poles and lines has been completed. The reason is that the construction of transformer stations and power lines to resettlement areas has not been completed, in addition to problems with site clearance and implementation costs.

"Regarding clean water, areas with clean water systems will be connected to households. In remote areas, households are supported to find suitable sources of domestic water for themselves.

In general, living conditions and infrastructure in resettlement areas have met the needs of people and are better than old housing. However, during the implementation process, there were some difficulties that required adjustments, leading to progress being affected," said Mr. Thai.

According to the Tuyen Quang Province Traffic Construction Investment Project Management Board, as of March 20, the entire Tuyen Quang - Ha Giang expressway project still has 5.3km of site that has not been handed over (equivalent to nearly 10%).

As of the entire 77km route, there are still 184 households subject to resettlement that have not yet handed over the construction site (in Tuyen Quang city, Yen Son district, Ham Yen district). The reason is that the resettlement areas have not been completed and cannot be handed over to the people.

In addition, the authorities of the districts have not yet carried out procedures for granting land use right certificates and allocating land to households subject to resettlement relocation. All of the above problems have created 65 construction bottlenecks.

Tien do thi cong du an cao toc Tuyen Quang - Ha Giang bi anh huong do cong tac giai phong mat bang, tai dinh cu cham. Anh: Viet Bac.
The construction progress of the Tuyen Quang - Ha Giang expressway project is affected by slow site clearance and resettlement. Photo: Viet Bac.

According to the Tuyen Quang Provincial Traffic Project Management Board, if there is no timely and final solution, it will be impossible to complete 100% of the site clearance and hand over to the contractor for construction in the first quarter of 2025 and there is a risk that the project will be behind schedule.

To resolve the above problems, on March 21, Mr. Nguyen Van Son - Chairman of Tuyen Quang Provincial People's Committee requested Ham Yen district to speed up the construction progress of resettlement areas. Urgently carry out procedures to issue land use right certificates to households, ensuring the items and conditions of the resettlement area so that people can build houses.

The Chairman of Tuyen Quang Provincial People's Committee also suggested that the Department of Agriculture and Environment should proactively guide districts to solve difficulties in site clearance, build resettlement areas, and issue land use right certificates to people. The Department also needs to prepare propaganda documents for people who have not complied with the relocation...

The whole province of Tuyen Quang has 24 resettlement areas to provide accommodation for 479 households subject to land acquisition for the Tuyen Quang - Ha Giang expressway. Of which, Tuyen Quang city has 1 point, Yen Son district has 4 points and Ham Yen district has 19 points.

By the end of March 2025, resettlement land had been allocated to 357/479 households. Most of the resettlement areas have not yet completed the infrastructure construction, the progress is only 85 -95%.

Việt Bắc
TIN LIÊN QUAN

Unfinished resettlement, bottleneck in the progress of Tuyen Quang expressway

|

The delay in relocating people to resettlement areas and site clearance is a bottleneck that needs to be removed to ensure the progress of the Tuyen Quang - Ha Giang expressway.

Unfinished resettlement infrastructure for Tuyen Quang Expressway

|

Tuyen Quang - Although they have moved to resettlement areas for a long time, giving up land for expressway projects, many households have not really stabilized their lives.

slow construction of the only road leading to the capital Tuyen Quang

|

Tuyen Quang - The sluggish construction situation has caused the road from Tan Thanh commune to Phu Luu commune to be bumpy and littered with construction materials.

Unfinished infrastructure, resettled people suffer from lack of electricity and water

|

Thai Nguyen - Phuc Thuan resettlement area of the connecting road project lacks infrastructure, electricity and water for daily use, causing people's lives to struggle.

Struggling on the side of the billion-dollar road resettlement area in Thai Nguyen

|

The fact that the resettlement area has not completed enough infrastructure and lacks electricity and water has caused many households in Phuc Thuan commune (Pho Yen city) to struggle to live.

Many households in Buon Ma Thuot are upset because of continuous water outages

|

Dak Lak - Many areas in Buon Ma Thuot city are constantly cut off from water, causing people to lack clean water for daily activities during the dry season.

The army mobilizes and appoints 12 officers of Military Region 1

|

On the afternoon of March 31, the Standing Committee of the Party Committee of Military Region 1 held a conference to hand over decisions on the transfer and appointment of cadres from agencies and units in the Military Region.

Ms. Cao Thi Hoa An holds the position of Secretary of Phu Yen Provincial Party Committee

|

Phu Yen - On the afternoon of March 31, Phu Yen Provincial Party Committee held a Conference to implement the Politburo's Decision on personnel work.

Unfinished resettlement, bottleneck in the progress of Tuyen Quang expressway

Việt Bắc |

The delay in relocating people to resettlement areas and site clearance is a bottleneck that needs to be removed to ensure the progress of the Tuyen Quang - Ha Giang expressway.

Unfinished resettlement infrastructure for Tuyen Quang Expressway

Việt Bắc |

Tuyen Quang - Although they have moved to resettlement areas for a long time, giving up land for expressway projects, many households have not really stabilized their lives.

slow construction of the only road leading to the capital Tuyen Quang

Lam Thanh |

Tuyen Quang - The sluggish construction situation has caused the road from Tan Thanh commune to Phu Luu commune to be bumpy and littered with construction materials.

Unfinished infrastructure, resettled people suffer from lack of electricity and water

Lam Thanh |

Thai Nguyen - Phuc Thuan resettlement area of the connecting road project lacks infrastructure, electricity and water for daily use, causing people's lives to struggle.

Struggling on the side of the billion-dollar road resettlement area in Thai Nguyen

Lam Thanh |

The fact that the resettlement area has not completed enough infrastructure and lacks electricity and water has caused many households in Phuc Thuan commune (Pho Yen city) to struggle to live.