Current shape of overpass pillars at two intersections of Ring Road 1 project

SÓNG HỮU |

Hanoi - The overpass item at the Nguyen Chi Thanh and Lang Ha intersection of the Ring Road 1 project is under construction, and some bridge piers have taken shape.

The project to invest in the construction of Ring Road 1, Hoang Cau - Voi Phuc section has a total length of about 2,274km, with a cross-section scale of 50m.

The first point intersects with Cat Linh - La Thanh - Yen Lang road at Hoang Cau; The end point is at Voi Phuc intersection.

The project has a total investment of more than 7,210 billion VND, invested by the Hanoi Civil Engineering Construction Investment Project Management Board.

The total recovered area is about 153. 341m2, related to 1,983 households and organizations in Dong Da and Ba Dinh districts before (now O Cho Dua, Giang Vo and Lang wards).

The project implementation period is from 2018-2020, but it will not be until the end of 2025 that the wards will complete site clearance to hand over to the investor to implement the project.

According to the Hanoi People's Committee, for the construction package of the road and 2 overpasses at Lang Ha - Giang Vo intersection started on January 9, 2026, the contractor has completed demolition, cleared the ground, transported all waste, and moved 357 green trees on the entire route.

Currently, the construction progress of the road has reached about 50% of the volume. Drainage, technical trenches, roadbed, infrastructure movement, electricity, water, and information items are being implemented in a rolling manner, including holidays; asphalt concrete has been paved for the section from Km2+500 to Km2+816, technically cleared before January 15, 2026.

On the route, there are two overpasses at the Lang Ha and Nguyen Chi Thanh intersections that are also being accelerated.

To date, Lang Ha overpass has completed 6/6 piers, reaching 50% of the volume.

The Nguyen Chi Thanh overpass has reached about 20%, main pillars are under construction and are preparing to enter the main span construction phase from June 2026.

According to the expected plan, the road will be completed and put into operation in the fourth quarter of 2026.

However, the project still has some difficulties and obstacles in the implementation process.

Accordingly, the urban railway construction investment project No. 5, Van Cao - Ngoc Khanh - Lang - Hoa Lac section, experienced conflicts and overlaps in many construction items (according to the approved design drawing) when intersecting with the Ring Road 1 project, Hoang Cau - Voi Phuc section, at the Nguyen Chi Thanh intersection.

The intersection conflict between the two projects will affect the progress of Ring Road 1 project at Nguyen Chi Thanh intersection. Accordingly, the scope and volume of Ring Road 1 project are changed because the completion of this intersection is reduced; the implementation time of Ring Road 1 project may be prolonged; the design of Ring Road 1 project may have to be adjusted.

To ensure the project completion progress in accordance with the direction of the City Party Committee, the Standing Committee of the City People's Committee Party Committee assigned the City People's Committee to continue to direct the city's departments, agencies, and branches to promptly resolve some difficulties and obstacles related to the project at the request of the investor.

Some images recorded at Ring Road 1 project

d
Construction site of Ring Road 1 project, Hoang Cau - Voi Phuc section on the afternoon of April 21. Photo: Song Huu
d
The contractor poured 171m3 of concrete foundation for the retaining wall, constructed the retaining wall with a completed volume of 135/730md (meters long). Photo: Song Huu
d
Construction machinery for project items. Photo: Song Huu
d
The Lang Ha intersection overpass has completed 6/6 piers, reaching 50% of the volume. Photo: Song Huu
d
d
It is expected that the contractor will construct the main span structure from June 1 to July 20. Photo: Song Huu
d
Workers working at the Lang Ha intersection overpass construction site. Photo: Song Huu
d
Nguyen Chi Thanh intersection is also built with a direct overpass. Photo: Song Huu
d
Nguyen Chi Thanh overpass has now reached about 20% of the volume, and drilled piles of 5/7 pillars have been completed. Photo: Song Huu
SÓNG HỮU
RELATED NEWS

Ring Road 1 project accelerates progress amidst material and site pressure

|

Despite facing many difficulties in terms of land, increased material costs and traffic organization, contractors are still making efforts to accelerate the progress of the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Removing a series of challenges in the construction process to accelerate the progress of Ring Road 1

|

Hanoi - Construction units of Ring Road 1 project have to both construct and handle arising difficulties, determined to overcome obstacles and ensure project progress.

4 continuous construction teams, Ring Road 1 construction site races for progress

|

Hanoi - Ring Road 1 construction site, Hoang Cau - Voi Phuc section, accelerates construction, striving to technically open part of the route in June and complete it in 2026.

Minister of Justice clarifies concerns that unemployed public lawyers still receive salaries

|

The Minister of Justice said that there is no rigid regulation on the ratio of time to perform tasks: Public lawyers and the work of civil servants.

Live football U17 Vietnam vs U17 Australia in the semi-finals of U17 Southeast Asia

|

Live match between U17 Vietnam and U17 Australia in the U17 Southeast Asian semi-finals, taking place at 7:30 PM today (April 22).

Fight against false and hostile information with scientific and persuasive arguments

|

Regulation No. 19-QD/TW has stated the proactive struggle against false and hostile information and arguments with scientific and persuasive arguments.

Thousands of tons of eels are in stock, farmers in Can Tho and Ca Mau face the risk of losses

|

Can Tho - Eel prices in Can Tho and Ca Mau have dropped sharply, causing farmers to face the risk of losses.

Veteran and the journey of more than 30 years of "keeping the fire" of national history

|

Instead of choosing a comfortable retirement age, the veteran entered a new "job" - educating national historical traditions.

Cầu qua sông Hồng, sông Đuống ở Hà Nội sau gần 1 năm thi công

SÓNG HỮU |

Hà Nội - Cầu Tứ Liên qua sông Hồng, sông Đuống đang được các nhà thầu đẩy nhanh tiến độ thi công ở những đoạn đã có mặt bằng sạch.

Ring Road 1 project accelerates progress amidst material and site pressure

Tùng Giang |

Despite facing many difficulties in terms of land, increased material costs and traffic organization, contractors are still making efforts to accelerate the progress of the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Removing a series of challenges in the construction process to accelerate the progress of Ring Road 1

Hữu Vũ |

Hanoi - Construction units of Ring Road 1 project have to both construct and handle arising difficulties, determined to overcome obstacles and ensure project progress.

4 continuous construction teams, Ring Road 1 construction site races for progress

Hữu Vũ - Thiện Nhân |

Hanoi - Ring Road 1 construction site, Hoang Cau - Voi Phuc section, accelerates construction, striving to technically open part of the route in June and complete it in 2026.