Current status of the area where an overpass will be built on the "most expensive road project on the planet" in Hanoi

Hữu Vũ |

Hanoi - The two direct overpasses on Ring Road 1 are expected to relieve congestion that has lasted for many years in this area.

On Ring Road 1 (Hoang Cau - Voi Phuc section) in Hanoi, two large direct overpasses will be built at the Lang Ha - De La Thanh and Nguyen Chi Thanh - De La Thanh intersections.

These are two areas that often have traffic congestion, especially during rush hour.

Each bridge is about 250m long, 18m wide with 4 lanes, expected to solve the congestion that has lasted for many years at these traffic hotspots.

This is an important item in the Ring Road 1 project, more than 2.2 km long, playing a role in enhancing connectivity and shortening travel time between central areas of the capital.

According to the reporter's records on August 11, at the Nguyen Chi Thanh - De La Thanh overpass, the site clearance work is sluggish, and only a part has been cleared.

Nut giao Nguyen Chi Thanh - De La Thanh nhin tu tren cao. Anh: Song Huu
Nguyen Chi Thanh - De La Thanh intersection seen from above. Photo: Song Huu

Inside the land surrounded by corrugated iron, garbage and construction waste are piled up, causing dust every time vehicles pass by.

Phe thai xay dung ngon ngang tai cac diem giai phong mat bang o nut giao Nguyen Chi Thanh - De La Thanh. Anh: Huu Vu
Construction waste is scattered at site clearance points at the Nguyen Chi Thanh - De La Thanh intersection. Photo: Huu Vu

Ms. Vu Thi Hong (residing on Nguyen Chi Thanh Street) expressed her indignation: "Sometimes I see a few groups of workers coming to work, but I don't quite implement it, the area has become shabby all the time".

Meanwhile, at the Lang Ha - De La Thanh overpass location, some items have been started. Excavators and excavators have been gathered and workers are constructing project items.

Vi tri xay dung cau vuot nut giao Lang Ha - De La Thanh. Anh: Huu  Vu
Location of the Lang Ha - De La Thanh intersection overpass. Photo: Huu Vu
Cong nhan tien hanh thi cong mot so hang muc tai nut giao Lang Ha - De La Thanh. Anh: Huu Vu
Workers are constructing some items at the Lang Ha - De La Thanh intersection. Photo: Huu Vu

It is known that up to now, the contractor has constructed 1 T1 pillar of Lang Ha overpass; cast 766/1,197 technicalane components; implemented the construction of technicalane in the O Cho Dua ward (new).

The Ring Road 1 project has a total investment of nearly VND 7,200 billion, of which the construction cost is about VND 627 billion, but the site clearance cost is up to more than VND 5,818 billion.

Hang muc cau vuot tai day bat dau duoc trien khai tu thang 5.2025. Anh: Huu Vu
The overpass project will start deployment from May 2025. Photo: Huu Vu

This is the number that makes the route known as "the most expensive road on the planet".

Previously, at the question-and-answer session of the 25th session of the Hanoi People's Council held on July 9, Director of the Department of Construction Nguyen Phi Thuong admitted that this is a key, complicated and prolonged project, especially in the site clearance stage.

Mr. Nguyen Phi Thuong said that after stabilizing the apparatus from the process of rearranging administrative units according to the 2-level urban government model, the Project Steering Committee and the new wards will make a detailed plan, striving to complete site clearance in the fourth quarter of 2025.

When completed, the Hoang Cau - Voi Phuc section will not only help reduce pressure on the De La Thanh route, which was jammed during rush hour, but also significantly improve connectivity and traffic capacity for key traffic routes in Hanoi.

Hữu Vũ
RELATED NEWS

Stuck with more than 1.6km of site clearance, Thuan An seawall overpass project faces difficulties

|

The Thuan An estuary overpass project is behind schedule due to problems with the southern access road, causing the contractor to only be able to construct slowly in each section.

Informal labor is of interest

|

Hanoi - Informal labor is one of the contents discussed at the scientific conference evaluating 5 years of implementing the 2019 Labor Code.

US announces demilitarization of Gaza begins

|

The US launched a new phase in Gaza, aimed at transitional management and disarmament of all illegal armed subjects.

Live broadcast of the ASEAN Cup 2026 draw: Vietnam national team determines opponent

|

Live broadcast of the Vietnam national team draw at ASEAN Cup 2026, taking place at 4:00 PM today (January 15).

Groundbreaking ceremony for Metro Line 2, people along the route expect the new urban appearance

|

Ho Chi Minh City - On January 15, Ho Chi Minh City started construction of Metro Line 2 project (Ben Thanh - Tham Luong), people along the route expect the new urban appearance.

Ho Chi Minh City starts construction of Metro Line 2 worth more than 55,000 billion VND, passing through 14 wards

|

Ho Chi Minh City - On the morning of January 15, the Ho Chi Minh City People's Committee held a groundbreaking ceremony for Metro Line 2 project (Ben Thanh - Tham Luong), connecting the central area with the Northwest gateway of the City.

Stuck with more than 1.6km of site clearance, Thuan An seawall overpass project faces difficulties

PHÚC ĐẠT - NGUYỄN LUÂN |

The Thuan An estuary overpass project is behind schedule due to problems with the southern access road, causing the contractor to only be able to construct slowly in each section.

Chi tiết 4 địa điểm dự kiến xây dựng trạm sạc xe điện dọc Vành đai 1

Minh Hạnh |

Hà Nội - Công ty TNHH MTV Khai thác điểm đỗ xe Hà Nội đề xuất bố trí 4 bãi đỗ xe kết hợp trạm sạc, chuẩn bị cho lộ trình cấm xe máy xăng.

Chi tiết những địa điểm Hà Nội dự kiến lắp đặt trạm sạc xe điện tại Vành đai 1

Nhóm PV |

Hà Nội dự kiến xây dựng trạm sạc xe điện tại các vị trí trọng điểm trong Vành đai 1, chuẩn bị cho lệnh cấm xe máy xăng từ 1.7.2026