According to the Binh Duong Province Traffic Construction Investment Project Management Board, the construction package 2 for the construction of Binh Chuan intersection belongs to the Ho Chi Minh City Ring Road 3 project.
The Binh Chuan intersection project started construction in June 2023. This intersection is 1.3 km long, including the highway, bridge, underpass...
After more than 2 years of construction, the value of the volume reached 220,5 billion VND/490.9 billion VND, reaching a rate of more than 45% compared to the contract implementation volume.

According to the records at the project, 114 bored piles have been constructed 100%). Construction of piles, retaining walls, and closed tunnel of branch C and branch D reached 100%. Construction of abutment and body piers has completed 13/14 piers. Construction of the empty box girder reaches 6/12 girders.
The expressway traffic route is under construction with crushed stone layering on the main route. The contractor is constructing drainage and digging soil, filling the foundations of SH1, SH2, SH3, SH4 routes.

According to the plan, in August 2025, an overpass will be constructed across My Phuoc Tan Van road. To prepare for this, the units are currently constructing the branch lines on both sides. It is expected that from August 15, a lane will be closed on My Phuoc Tan Van road to construct an overpass. Vehicles will be adjusted to move to the branch.


Traffic congestion at intersections
My Phuoc Tan Van road, the Ring Road 3 project section, currently has 6 lanes. In the Binh Chuan intersection construction area, motorbikes are regulated to move onto the sidewalk, cars move on both sides of the road with 2 lanes.

Due to the large volume of vehicles passing through the construction site, traffic congestion often occurs at this section.
Recorded in the morning of August 2, traffic on My Phuoc Tan Van road was congested in the afternoon from An Phu to Thu Dau Mot. Two dense lanes of cars and vehicles moved slowly through Binh Chuan intersection.