The shape of the nearly 9 km section of Ho Chi Minh City Ring Road 3 through Binh Duong area

ĐÌNH TRỌNG |

HCMC - The Ho Chi Minh City Ring Road 3 project, the section passing through Binh Duong province, was previously being accelerated, the nearly 9 km section of road is gradually taking shape.

Recorded on December 15, contractors are speeding up the construction progress of construction package No. 3, from Binh Chuan to Saigon River. This is a construction package of the component project 5 of Ho Chi Minh City Ring Road 3, the section passing through Binh Duong province before.

The current construction package No. 3 passing through Thuan Giao ward, Phu Loi ward, Thu Dau Mot ward and Thuan An ward has compensated and reclaimed 73.11 hectares, enough clean land for the project to construct.

The Binh Duong Traffic Construction Investment Project Management Board said that this package was started on June 29, 2023, and is expected to be completed according to the contract on January 10, 2026.

The construction of the expressway from Binh Chuan intersection to Saigon River is nearly 9 km long, the total value of construction package No. 3 is 1,852 billion VND. The project aims to strive to open to technical traffic by the end of 2025.

Diem dau cua goi xay lap so 3 doan nut giao Binh Chuan. Anh: Dinh Trong
The starting point of construction package No. 3 at Binh Chuan intersection. Photo: Dinh Trong

The nearly 9 km section, phase 1 of the construction of a 4-lane expressway designed for express vehicles at 100 km/h and parallel roads on both sides are connected to the existing traffic network. Organize traffic at intersections and highway entrance and exit points.

Of which, the expressway section is nearly 8 km long, has been filled with sand, the shape of the road is gradually taking shape. Units are building technical fences and paving the road surface with stone.

The remaining section of nearly 1 km will also be built with an elevated overpass. The columns and abutments of the pillars have now been completed. The construction unit is completing the installation of girders and pouring concrete on the overpass surface.

Doan cau vuot gan 1km dang duoc khan truong xay dung. Anh: Dinh Trong
The nearly 1 km overpass is under urgent construction. Photo: Dinh Trong
Sau 2 nam thi cong, cong trinh Vanh dai 3 doan qua phuong Thuan Giao va phuong Thu Dau Mot dan thanh hinh. Anh: Dinh Trong
After 2 years of construction, the Ring Road 3 project through Thuan Giao ward and Thu Dau Mot ward is gradually taking shape. Photo: Dinh Trong
Phan duong dai khoang 8km doan qua phuong Thuan dang duoc do dat dap nen duong. Anh: Dinh Trong
The about 8 km long road section through Thuan An ward is being filled with soil to fill the roadbed. Photo: Dinh Trong
Hinh hai duong cao toc va duong song hanh hai ben dang dan thanh hinh. Anh: Dinh Trong
The shape of the expressway and the parallel roads on both sides is gradually taking shape. Photo: Dinh Trong
Doan giao voi duong An Son 02 dang bat dau dap nen
The intersection with An Son 02 Street, under construction at the intersection, is spreading stone on the parallel roadbed. Photo: Dinh Trong
Doan
The section near Binh Goi Bridge is under construction of abutment piers and access roads to the bridge. Photo: Dinh Trong
Cong trinh dat muc tieu thong xe ky thuat vao cuoi nam 2025. Anh: Dinh Trong
The project aims to be technically open to traffic by the end of 2025. Photo: Dinh Trong

It is known that Ho Chi Minh City Ring Road 3 passing through Binh Duong area (formerly) is about 26.6 km long, with a total investment of VND 19,280 billion. The project is divided into 2 component projects. In which, component project 5 is construction divided into 4 construction packages of more than 11 km of roads and connecting bridges.

For component project 6, site clearance and resettlement have a total investment of VND 13,528 billion. Currently, the entire site has been handed over for units to speed up construction.

Meanwhile, 15.3 km overlapping with My Phuoc Tan Van road is still studying a complete investment plan.

ĐÌNH TRỌNG
RELATED NEWS

Dialogue with households compensated for building Ho Chi Minh City Ring Road 3

|

HCMC - Dong Hoa Ward continues to dialogue with households subject to compensation for site clearance for the construction of Ho Chi Minh City Ring Road 3.

The major intersection on Ho Chi Minh City Ring Road 3 enters the peak of construction day and night

|

HCMC - Tan Van intersection on Ho Chi Minh City Ring Road 3 is being accelerated, construction forces are working day and night to meet the target of opening traffic on schedule.

The most complicated intersection of Ho Chi Minh City Ring Road 3 speeds up, ready for technical traffic

|

Ho Chi Minh City - Tan Van intersection, the most complicated connection point on Ring Road 3, is accelerating construction, ready for technical traffic opening at the end of 2025.

Advising Vietnamese citizens on the Cambodia - Thailand conflict

|

The Ministry of Foreign Affairs recommends that Vietnamese citizens living in border provinces between Cambodia and Thailand.

China completes testing new stealth UAV

|

The flight marks an important step forward in China's stealth UAV program.

Proposal to install 20,000 electric motorbike battery swaps on the sidewalks of Ho Chi Minh City

|

HCMC - Two enterprises proposed to invest in 20,000 electric motorbike battery cabinets on the sidewalks of HCMC, expected to be completed in the first quarter of 2026.

Hanoi urgently clears the construction of Ring Road 1, will build 2 direct overpasses

|

Hanoi - After receiving the clean site, the investor will deploy the construction of road items and 2 overpasses to directly open the Ring Road 1 project, Hoang Cau - Voi Phuc section.

SEA Games 33 Medal Schedule on December 15

|

Updated total medal table of the 33rd SEA Games on December 15.

Dialogue with households compensated for building Ho Chi Minh City Ring Road 3

ĐÌNH TRỌNG |

HCMC - Dong Hoa Ward continues to dialogue with households subject to compensation for site clearance for the construction of Ho Chi Minh City Ring Road 3.

The major intersection on Ho Chi Minh City Ring Road 3 enters the peak of construction day and night

TÚ QUỲNH |

HCMC - Tan Van intersection on Ho Chi Minh City Ring Road 3 is being accelerated, construction forces are working day and night to meet the target of opening traffic on schedule.

The most complicated intersection of Ho Chi Minh City Ring Road 3 speeds up, ready for technical traffic

Anh Tú |

Ho Chi Minh City - Tan Van intersection, the most complicated connection point on Ring Road 3, is accelerating construction, ready for technical traffic opening at the end of 2025.