Completed many items at Kho Vang resettlement area

Đinh Đại |

Lao Cai - Many housing projects in the resettlement area of ​​Kho Vang village (Coc Lau commune, Bac Ha district) are being urgently completed.

On December 3, information from the Project Management Board and Construction Investment of Bac Ha district, after more than 2 months of construction, items of the Kho Vang village reconstruction project are being implemented by units to ensure the set plan.

Regarding infrastructure, electricity and water have been supplied to the construction site. Up to now, the roadbed has been completed and the crushed stone foundation, precast components, drainage and embankment are being constructed; more than 100m of road surface concrete has been poured.

For residential housing, each house will have an area of ​​about 60 m2, including 2 or 3 bedrooms, 1 living room, 1 kitchen and outbuildings. Currently, 12 houses have been roofed, 12 houses have been topped out and the model house in the resettlement area has been completed; 6 houses are being fabricated with trusses, steel purlins, etc.

Accordingly, a new, spacious resettlement area is gradually appearing, with the goal that by the end of December 2024, all 35 households will be able to move into their new homes.

Đinh Đại
RELATED NEWS

Nam Tong residents draw lots for resettlement housing locations

|

Lao Cai - 15 households in Nam Tong village, Nam Luc commune (Bac Ha) have drawn lots for house locations in the resettlement area.

Installing doors for houses in Lang Nu resettlement area

|

Lao Cai - After many days of construction, the stilt houses in the resettlement area of ​​Lang Nu people, Phuc Khanh commune (Bao Yen) have had doors installed.

Thousands of cubic meters of soil dumped into resettlement area in Yen Bai

|

Yen Bai - A large amount of landslide soil after storms and floods was brazenly transported to level the resettlement area along the river in Yen Bai.

Nearly 200 workers in Son La are waiting to be paid salaries near Tet

|

Son La - Nearly 200 workers in Chieng Khoong commune are waiting for the construction unit of the Primary - Secondary Inter-level Boarding School Project to pay wages on the eve of Tet.

Holding 1 million VND, still can't buy 1kg of Ca Mau crab on the eve of Tet

|

Some Ca Mau crabs have exceeded the 1 million VND/kg mark in the days leading up to the Binh Ngo Lunar New Year 2026.

Workers wake up at 4 am, excitedly returning to their hometowns on a trade union bus

|

Hai Phong - On the morning of February 14, hundreds of workers boarded a bus to return to their hometowns to celebrate Tet organized by the Trade Union of Yazaki Hai Phong Vietnam Co., Ltd.

Fishing boats dock at the end of the year, ready for the first spring sea trip

|

Can Tho - After many long days of sticking to the fishing grounds, fishermen's fishing boats have returned to shore to celebrate Tet and prepare for the first sea trip of the new year.

Rainy and cold weather in Hanoi due to cold air during the Binh Ngo Tet 2026

|

Forecast from the 27th to the 29th of Tet, Hanoi's weather during the day is quite warm. However, from the night of the 29th of Tet, the weather is likely to turn rainy and cold due to cold air.

Nam Tong residents draw lots for resettlement housing locations

Đinh Đại |

Lao Cai - 15 households in Nam Tong village, Nam Luc commune (Bac Ha) have drawn lots for house locations in the resettlement area.

Installing doors for houses in Lang Nu resettlement area

Đinh Đại |

Lao Cai - After many days of construction, the stilt houses in the resettlement area of ​​Lang Nu people, Phuc Khanh commune (Bao Yen) have had doors installed.

Thousands of cubic meters of soil dumped into resettlement area in Yen Bai

Trần Bùi |

Yen Bai - A large amount of landslide soil after storms and floods was brazenly transported to level the resettlement area along the river in Yen Bai.