Completed many items at Kho Vang resettlement area

Đinh Đại |

Lao Cai - Many housing projects in the resettlement area of ​​Kho Vang village (Coc Lau commune, Bac Ha district) are being urgently completed.

On December 3, information from the Project Management Board and Construction Investment of Bac Ha district, after more than 2 months of construction, items of the Kho Vang village reconstruction project are being implemented by units to ensure the set plan.

Regarding infrastructure, electricity and water have been supplied to the construction site. Up to now, the roadbed has been completed and the crushed stone foundation, precast components, drainage and embankment are being constructed; more than 100m of road surface concrete has been poured.

For residential housing, each house will have an area of ​​about 60 m2, including 2 or 3 bedrooms, 1 living room, 1 kitchen and outbuildings. Currently, 12 houses have been roofed, 12 houses have been topped out and the model house in the resettlement area has been completed; 6 houses are being fabricated with trusses, steel purlins, etc.

Accordingly, a new, spacious resettlement area is gradually appearing, with the goal that by the end of December 2024, all 35 households will be able to move into their new homes.

Đinh Đại
RELATED NEWS

Nam Tong residents draw lots for resettlement housing locations

|

Lao Cai - 15 households in Nam Tong village, Nam Luc commune (Bac Ha) have drawn lots for house locations in the resettlement area.

Installing doors for houses in Lang Nu resettlement area

|

Lao Cai - After many days of construction, the stilt houses in the resettlement area of ​​Lang Nu people, Phuc Khanh commune (Bao Yen) have had doors installed.

Thousands of cubic meters of soil dumped into resettlement area in Yen Bai

|

Yen Bai - A large amount of landslide soil after storms and floods was brazenly transported to level the resettlement area along the river in Yen Bai.

The first overnight surgery at Bach Mai Hospital, Ninh Binh facility

|

The first surgery at Bach Mai Hospital, Ninh Binh facility, saved a man with severe spinal injury from the risk of paralysis of both legs.

Overcoming encroachment on Suoi Vang lake, signs of legitimizing the status quo appear

|

Lam Dong - The remedy of violations at Suoi Vang lake is still very unusual. Functional agencies need to inspect and handle, avoiding the situation of legitimizing violations.

Saturday afternoon coffee: From live sessions to finalize billion-VND bills to responsibilities in cyberspace

|

Billion-VND livestream sessions are opening up great opportunities, but also posing increasingly high requirements for responsibility.

List of collectives and individuals expected to be honored in the 2026 Glory of Vietnam Program

|

On the afternoon of June 25, 2026, the Selection Council for the 2026 Glory of Vietnam Program met to consider nominees from Central Committees, Ministries, sectors and Provincial and City Labor Federations, Central Industry Trade Unions and equivalents. Below are the expected selection of collectives and individuals to be considered and honored in the 2026 Glory of Vietnam Program.

Nam Tong residents draw lots for resettlement housing locations

Đinh Đại |

Lao Cai - 15 households in Nam Tong village, Nam Luc commune (Bac Ha) have drawn lots for house locations in the resettlement area.

Installing doors for houses in Lang Nu resettlement area

Đinh Đại |

Lao Cai - After many days of construction, the stilt houses in the resettlement area of ​​Lang Nu people, Phuc Khanh commune (Bao Yen) have had doors installed.

Thousands of cubic meters of soil dumped into resettlement area in Yen Bai

Trần Bùi |

Yen Bai - A large amount of landslide soil after storms and floods was brazenly transported to level the resettlement area along the river in Yen Bai.