Completed many items at Kho Vang resettlement area

Đinh Đại |

Lao Cai - Many housing projects in the resettlement area of ​​Kho Vang village (Coc Lau commune, Bac Ha district) are being urgently completed.

On December 3, information from the Project Management Board and Construction Investment of Bac Ha district, after more than 2 months of construction, items of the Kho Vang village reconstruction project are being implemented by units to ensure the set plan.

Regarding infrastructure, electricity and water have been supplied to the construction site. Up to now, the roadbed has been completed and the crushed stone foundation, precast components, drainage and embankment are being constructed; more than 100m of road surface concrete has been poured.

For residential housing, each house will have an area of ​​about 60 m2, including 2 or 3 bedrooms, 1 living room, 1 kitchen and outbuildings. Currently, 12 houses have been roofed, 12 houses have been topped out and the model house in the resettlement area has been completed; 6 houses are being fabricated with trusses, steel purlins, etc.

Accordingly, a new, spacious resettlement area is gradually appearing, with the goal that by the end of December 2024, all 35 households will be able to move into their new homes.

Đinh Đại
RELATED NEWS

Nam Tong residents draw lots for resettlement housing locations

|

Lao Cai - 15 households in Nam Tong village, Nam Luc commune (Bac Ha) have drawn lots for house locations in the resettlement area.

Installing doors for houses in Lang Nu resettlement area

|

Lao Cai - After many days of construction, the stilt houses in the resettlement area of ​​Lang Nu people, Phuc Khanh commune (Bao Yen) have had doors installed.

Thousands of cubic meters of soil dumped into resettlement area in Yen Bai

|

Yen Bai - A large amount of landslide soil after storms and floods was brazenly transported to level the resettlement area along the river in Yen Bai.

Ho Chi Minh City to build a road along the Saigon River, 78km long, 30 - 40m wide

|

Ho Chi Minh City - The Saigon riverside road is about 78km long, 30 - 40m wide, with a preliminary total capital of 21,200 billion VND, implemented in the form of public-private partnership (PPP).

Mr. Vu Anh Duc is the Director of the Institute of Occupational Safety and Health Science

|

In the afternoon of August 28, the Vietnam General Confederation of Labor organized a conference to announce and award decisions on personnel work at the Institute of Occupational Safety and Health Sciences.

Many violations revealed after inspection of unfinished residential area project in Thai Nguyen

|

Thai Nguyen - The inspection conclusion has pointed out violations and backlogs at the Quang Trung - Quang Vinh Residential Area project with nearly 10 years of unfinished implementation.

Nam Tong residents draw lots for resettlement housing locations

Đinh Đại |

Lao Cai - 15 households in Nam Tong village, Nam Luc commune (Bac Ha) have drawn lots for house locations in the resettlement area.

Installing doors for houses in Lang Nu resettlement area

Đinh Đại |

Lao Cai - After many days of construction, the stilt houses in the resettlement area of ​​Lang Nu people, Phuc Khanh commune (Bao Yen) have had doors installed.

Thousands of cubic meters of soil dumped into resettlement area in Yen Bai

Trần Bùi |

Yen Bai - A large amount of landslide soil after storms and floods was brazenly transported to level the resettlement area along the river in Yen Bai.