Bustling at the Dong Dang - Tra Linh highway construction site

Khánh Linh |

In the last days of the year, the construction site of Dong Dang - Tra Linh highway seems to be busier.

These days, at the construction site of the Dong Dang - Tra Linh expressway, more than 1,000 workers and engineers have been mobilized to the construction site, "3 shifts, 4 teams" are deployed to urgently construct the project.

Amidst the mountains, groups of workers take turns, the sound of machinery rumbles, and drills seem to tear apart the mountain.

At That Khe tunnel, after determining the location and drilling the first drill to open the tunnel in mid-October, the construction unit is deploying 4 construction drills continuously in 3 shifts/day. Reinforcement is carried out as the tunnel is dug, ensuring construction safety, labor safety and the critical path according to the plan.

In addition, construction sites such as Km56+200, Na Pa hamlet, Duc Xuan commune; mountain tunnel No. 2 - Dong Khe tunnel, Ban Neng hamlet, Thuy Hung commune (Thach An); Km79+600 Na Da hamlet, Hoa Thuan town and Km85+700 Ban Tin hamlet, Lung Tao, Hanh Phuc commune (Quang Hoa)... are also being synchronously deployed.

Mr. Nguyen Duc Tuan - Deputy General Director of Dong Dang - Tra Linh Expressway Joint Stock Company said: "Currently, on the handed over site, the contractor is organizing 18 construction teams with 467 personnel and nearly 200 locomotives and equipment. Human resources and machinery are working day and night."

On December 5, directly inspecting the construction site of the No. 1 mountain tunnel - That Khe Tunnel, located in Chi Minh Commune, Trang Dinh District (Lang Son), Chairman of Cao Bang Provincial People's Committee Hoang Xuan Anh also requested the construction units to promptly overcome difficulties and problems related to earth fill mines, construction material mines, relocation of technical infrastructure, site clearance, and resettlement to serve the project.

The Chairman of the Cao Bang Provincial People's Committee also requested the Party Committees and authorities of the two districts of Thach An and Quang Hoa to soon stabilize housing for people in the resettlement area, ensuring that the new housing is better and more spacious than the old housing, with the determination to open the route by the end of 2025, and complete the entire project in 2026.

The Dong Dang - Tra Linh Expressway project is 121 km long, passing through Lang Son and Cao Bang. This project is divided into two investment phases, with phase 1 currently being implemented, including the construction of a highway over 93 km long.

The total investment of the project is more than 14,100 billion VND in the form of PPP, of which the state budget accounts for 69%.

The sections over bridges and tunnels have 4 complete lanes, the main road has 2 lanes. The investor also cleared the land according to the scale of 4 complete lanes.

Up to now, the project's site clearance has reached 93.6%, of which the section through Cao Bang province has reached 99% and the section through Lang Son province has reached 90%.

The two provinces are unanimous in striving to hand over 100% of the project site by the end of December.

Some images recorded at the project site:

Khánh Linh
TIN LIÊN QUAN

The first tunnel on Dong Dang - Tra Linh highway takes shape

|

Cao Bang - The government and a consortium of investors have just held a ceremony to open the Dong Khe tunnel on the Dong Dang - Tra Linh expressway project.

With increased capital, how is the Dong Dang - Tra Linh expressway being built

|

The two localities through which the expressway passes are speeding up the process of site clearance and related procedures to serve the project's construction.

Provincial leaders proactively "knock on the door" of corporations to invite investment

|

Long An - On the occasion of the beginning of Spring, Mr. Huynh Van Son - Vice Chairman of the Provincial People's Committee - shared with Lao Dong Newspaper about how to become a bright spot to attract investment.

Trump unveils shocking plan to deport immigrants

|

US President Donald Trump announced a shocking plan to send 30,000 deported immigrants to Guantanamo.

Digging through trash to find a 1 billion VND diamond ring for a resident in Da Nang

|

Diamond jewelry worth more than 1 billion VND that was mistakenly thrown into the trash in Da Nang on New Year's Eve was found by environmental workers and returned to the owner.

The snake and the symbol of medicine

|

The medical profession has long used the image of a snake wrapped around a staff as a symbol, appearing on medical badges, hospitals and healthcare organizations around the world. But few people know that behind this seemingly simple symbol is a long story, tied to ancient mythology and a deep meaning of healing, regeneration and even a warning about the power of medicine.

What did Thanh Son say about receiving a salary of 150-200 thousand/show?

|

The year 2025 started with a big turning point for Thanh Son when he participated in his first Tet movie.

65 years from the cave to the prosperous village of the Ruc people

|

Quang Binh - In the middle of Phong Nha - Ke Bang mountains and forests, the Ruc people, from a tribe living in caves, are now gradually changing, integrating and developing strongly.

The first tunnel on Dong Dang - Tra Linh highway takes shape

Tân Văn |

Cao Bang - The government and a consortium of investors have just held a ceremony to open the Dong Khe tunnel on the Dong Dang - Tra Linh expressway project.

With increased capital, how is the Dong Dang - Tra Linh expressway being built

Tân Văn |

The two localities through which the expressway passes are speeding up the process of site clearance and related procedures to serve the project's construction.

Những mũi khoan đầu tiên phá núi đá, đào hầm sâu trên tuyến cao tốc Đồng Đăng - Trà Lĩnh

Tân Văn |

Liên danh nhà đầu tư đã tiến hành thi công mở cửa hầm phía Tây - đây cũng là đường hầm đầu tiên được khai mở trên tuyến cao tốc Đồng Đăng - Trà Lĩnh.