More than 15,000 engineers and workers work during the APEC 2027 major construction site

NGUYÊN ANH |

An Giang - About 15,500 engineers and workers are diligently working shifts throughout the holiday to bring the projects serving APEC 2027 closer to completion.

On the holidays of National Day September 2nd, the sound of machinery or the sound of work exchanges at the construction sites serving APEC 2027 in Phu Quoc are still lively and bustling.

Mr. Nguyen Dac Thao, technical supervisor at the APEC Conference Center, has been attached to the construction profession for more than 40 years. Looking at the items that are changing every day, the veteran engineer could not hide his emotion.

This is the largest and most complex project in my career. Witnessing the project changing day by day, I am very proud to see that Vietnamese people have been able to build world-class projects," said Mr. Nguyen Dac Thao.

Ông Nguyễn Đắc Thảo miệt mài làm việc tại dự án Trung tâm Hội nghị APEC. Nguồn Sun Group
Mr. Nguyen Dac Thao diligently works at the APEC Conference Center project. Photo: Sun Group

And Mr. Le Hoang Minh, safety supervisor at the Multi-purpose Theater, said that he regularly moves through construction areas to check working conditions, observe and remind teams to comply with procedures. When the number of construction teams and workload increase, safety assurance requirements become stricter.

This holiday I chose to work at the construction site. I think it's a responsibility but also a heart, a way for young people to contribute and contribute to the country with their abilities," Mr. Minh shared.

Ms. Luong Thi Bich, a female worker working at the construction site of Terminal T2 of Phu Quoc International Airport, is also one of the workers who registered to stay at the construction site.

I miss my children but I have to work hard to save money for the future. Before, I was a livestock breeder, with unstable income. Later, my husband and I went to work in construction here, and the current job has a higher and more stable income," Ms. Bich confided.

Or Ms. Tran Thi Ruong, a sanitation worker at Bai Dat Do hotel complex, said that she collected excess materials, cleared the ground to hand over to the next construction teams. Her husband also works at the project and registered to work during the holiday.

Mr. Nguyen Van Tuan, Head of the Project Management Board of Bai Dat Do Hotel Complex, said that workers register to work during the September 2nd holiday on a voluntary basis, in accordance with the requirements of each location and construction plan.

Hai cần cẩu siêu trường, siêu trọng có sức nâng khoảng 650 tấn và 800 tấn đang phục vụ thi công phần mái Nhà hát Đa năng. Nguồn Sun Group
Two super-heavy cranes with lift capacity of about 650 tons and 800 tons are serving the construction of the roof of the Multi-purpose Theater. Photo: Sun Group

Engineers and workers working on holidays are not only paid extra wages according to regulations but also arranged for compensatory leave to ensure health. Shifting is arranged in accordance with the nature of work, actual conditions and safety requirements at the construction site.

The project regularly arranges accommodation with about 3,000 accommodations, along with a health system and essential amenities for workers to stabilize their lives and feel secure working at the construction site," Mr. Nguyen Van Tuan added.

According to Mr. Nguyen Tien Hop, Managing Director of PPP projects in Phu Quoc of Sun Group, 6 projects serving APEC 2027 are simultaneously entering the peak construction phase. During this year's National Day, about 15,500 engineers and workers have registered to work during the holiday to maintain progress.

In addition to the regimes on salaries and leave time, the work of caring for spiritual life is also emphasized. On holidays, representatives of the project management board and leaders of units are assigned to go to each camp area, each construction site to visit workers. Those friendly meetings have added spirit to those who celebrate holidays away from home, helping them have more motivation to work "overcoming sun and winning rain".

NGUYÊN ANH
RELATED NEWS

APEC 2027 construction site is bustling with workers and machinery working throughout the holiday

|

An Giang - At the large construction site of APEC 2027 projects, engineers and workers are still working day and night.

600 workers and engineers work overtime at the light tram line construction site to catch up with APEC 2027

|

An Giang - Currently, the large construction site still maintains a 3-shift working cycle continuously day and night with nearly 600 engineers and workers sticking to it.

Ensuring project quality, construction safety of projects serving APEC 2027

|

An Giang - Projects serving APEC 2027 contribute to perfecting the modern and synchronous urban appearance, meeting the requirements of organizing large-scale international events.

Hai Long nominated for ASEAN Cup 2026 Most Energy Player title

|

Nguyen Hai Long was nominated for the title of ASEAN Cup 2026 Most Energy Player after an impressive performance against Indonesia.

Voters propose to merge National Unity Day with Vietnam Culture Day

|

The Ministry of Culture, Sports and Tourism has a document responding to the recommendations of voters in some localities sent after the first session of the 16th National Assembly.

Forecast of the time to end widespread intense heat

|

Forecast from September 3rd, Northern Vietnam will only have localized hot weather with the highest temperature in some places above 35 degrees Celsius. In Central Vietnam, hot weather will continue until around September 4th.

Victim of passenger car overturning in Gia Lai paralyzed in both legs, emergency surgery

|

On September 1st, Cho Ray Hospital in Ho Chi Minh City reported to the Ministry of Health and the Department of Medical Examination and Treatment Management on emergency surgery for a two-legged paralyzed patient in the passenger car overturning incident in Gia Lai.

APEC 2027 construction site is bustling with workers and machinery working throughout the holiday

NGUYÊN ANH |

An Giang - At the large construction site of APEC 2027 projects, engineers and workers are still working day and night.

600 workers and engineers work overtime at the light tram line construction site to catch up with APEC 2027

NGUYÊN ANH |

An Giang - Currently, the large construction site still maintains a 3-shift working cycle continuously day and night with nearly 600 engineers and workers sticking to it.

Ensuring project quality, construction safety of projects serving APEC 2027

NGUYÊN ANH - TIẾN DŨNG |

An Giang - Projects serving APEC 2027 contribute to perfecting the modern and synchronous urban appearance, meeting the requirements of organizing large-scale international events.