According to the environmental impact assessment report (EIA), the project implementation location is across the administrative boundaries of Nam Dong and Phu Loc districts, Thua Thien Hue province and Hoa Vang district, Da Nang City.
The project length is about 65km (of which the route length through Thua Thien Hue province is about 35.4km; through Da Nang city is about 29.6km).
The total land area of the project is about 460,138 hectares, of which 458,838 hectares of existing traffic land (the project is currently cleared with 4 lanes); Land for growing perennial trees (acacia): 1.3 hectares. The entire additional recovered land area is located in Thua Thien Hue province.
According to the EIA, the project will expand the road surface and works on the route to ensure a complete 4-lane scale; The intersection remains in its current state, maintaining the invested bridges with a scale of 4 lanes. Expand 50 bridges on the route to 4 lanes.
The goal of the project is to gradually complete transportation infrastructure according to planning, ensuring synchronization and modernity; improve exploitation capacity and reduce traffic accidents to promote the role of the Eastern North-South Expressway in connecting localities, ensuring national defense and security in the region and the whole country; Improving the capacity to exploit the La Son - Hoa Lien expressway in particular, along with the Cam Lo - La Son and Da Nang - Quang Ngai expressways will contribute to improving the ability to exploit the North - South expressway in particular. shared.
The total investment of the project is 3,010.73 billion VND.