Over 800 billion VND to clear 60 km of highway through 4 districts in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - The Dau Giay - Tan Phu Expressway Project Phase 1 has a total investment of nearly VND 8,500 billion, with a scale of 4 lanes being accelerated.

On May 18, according to information from the People's Committee of Dong Nai province, by June 20, four localities in the province must complete the preparation of compensation and support plans for the Dau Giay - Tan Phu expressway project.

The Dau Giay - Tan Phu Expressway project is over 60km long, passing through 4 districts including Thong Nhat, Xuan Loc, Dinh Quan and Tan Phu.

The project starts at Km0+000 , the intersection with National Highway 1, connecting with the Ho Chi Minh City - Long Thanh - Dau Giay Expressway, in Dau Giay town, Thong Nhat district; the end point is at Km60+243.83 (end of the intersection with National Highway 20), connecting with the Tan Phu - Bao Loc Expressway project, in Phu Son commune, Tan Phu district.

In phase 1, the project has a total investment of nearly VND 8,500 billion, invested in construction according to the standards of a 100% highway, with a scale of 4 lanes, and a roadbed width of 17m. The weak ground sections, bridges and emergency stops will be constructed on a complete scale, with a roadbed width of nearly 25m.

According to reports from localities, the total number of households affected by the project is more than 1,500 households. Of which, the number of households needing to be resettled is about 279 cases including: 20 cases in Thong Nhat district, 7-8 cases in Xuan Loc district, 120 cases in Dinh Quan district and 131 cases in Tan Phu district.

To arrange resettlement for people, localities have also reviewed the number of resettlement plots in resettlement areas that have been invested in and built as well as are implementing procedures to invest in building new resettlement areas.

On the investor's side, the Thang Long Project Management Board (Ministry of Construction) said that in 2025, the Dau Giay - Tan Phu Expressway Project will be allocated a capital of 814 billion VND to serve site clearance. Up to now, this capital has been transferred to the account of the district land fund development centers to carry out the work of measurement, counting, and compensation.

Accordingly, site clearance work is carried out on a complete scale with a total land area of about 378 hectares.

The Dau Giay - Tan Phu Expressway was invested in construction with the goal of meeting transportation needs, reducing traffic congestion and ensuring traffic safety on National Highway 20. Complete and put into synchronous operation expressways with high capacity, traffic safety and high speed on the Ho Chi Minh City - Dau Giay - Lien Khuong transport corridor to promote the socio-economic development of Dong Nai in particular and the Southeast region in general.

At the same time, it creates a driving force for linkage, promoting cooperation and development of the Southeast region with the Mekong Delta, the Central Highlands and the South Central region.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Dong Nai assigns 4 districts to compensate for 9,000 billion VND expressway project

|

Dong Nai Provincial People's Committee has assigned 4 districts to compensate and clear the land for the Dau Giay - Tan Phu expressway project (about 378 hectares).

US admits it cannot provide more strategic weapons to Ukraine

|

The US Secretary of State affirmed that Washington is not capable of providing additional patriot air defense systems to Ukraine because the production speed is not kept up.

Checking DJ Ngan 98's weight loss product in Ho Chi Minh City, the company closed

|

HCMC - The Department of Food Safety of HCMC inspects the weight loss product of DJ Ngan 98. However, at the time of inspection, the company's office was closed and no samples had been taken.

Permanent Deputy Prime Minister talks about personnel work when working in Lam Dong

|

Permanent Deputy Prime Minister Nguyen Hoa Binh expressed his delight that the policy of merging the three provinces of Lam Dong, Binh Thuan, and Dak Nong received high consensus.

Taking advantage of Nguyen Thuc Thuy Tien's trust and the price to pay

|

Miss Thuy Tien was prosecuted after Quang Linh Vlogs, Hang Du Cach. Her career collapsed after a billion-dollar deal.

Ho Chi Minh City Women's Club stops in the semi-finals of the Asian Cup C1

|

Ho Chi Minh City Women's Club lost 0-2 to Wuhan Jiangda, thereby stopping at the semi-finals of the 2024-2025 AFC Champions League for women (Asian Cup C1).

Regulations on trade unions at all levels after amending the 2024 Trade Union Law

|

The 2024 Trade Union Law (amended) adds regulations on trade union levels to ensure Cor correspondence with the organization of administrative units and local governments at both levels.

Dong Nai assigns 4 districts to compensate for 9,000 billion VND expressway project

HÀ ANH CHIẾN |

Dong Nai Provincial People's Committee has assigned 4 districts to compensate and clear the land for the Dau Giay - Tan Phu expressway project (about 378 hectares).

Bộ GTVT thông tin về tiến độ cao tốc Dầu Giây - Liên Khương

Xuyên Đông |

Ngày 19.8, Bộ Giao thông Vận tải trả lời cử tri thông tin về cao tốc Dầu Giây - Liên Khương.

Cần chuẩn xác số liệu, sớm hoàn thiện hồ sơ cao tốc Dầu Giây - Tân Phú

Đức Mạnh |

Đường cao tốc Dầu Giây – Tân Phú là đoạn đầu của cao tốc Dầu Giây – Liên Khương với tổng chiều dài hơn 60km, đi qua địa bàn các huyện Thống Nhất, Xuân Lộc, Định Quán, Tân Phú của tỉnh Đồng Nai. Giai đoạn 1 cao tốc được xây dựng với quy mô 4 làn xe, bề rộng nền đường 17m, có tổng mức đầu tư 8.776 tỉ đồng.