More than 9 km of road connecting Long Thanh airport with Ho Chi Minh City has been constructed 44%

HÀ ANH CHIẾN |

Dong Nai - Project to upgrade road 25B from the center of Nhon Trach commune to National Highway 51 connecting Long Thanh airport with Ho Chi Minh City.

On February 28, according to information from the Dong Nai Provincial Construction Investment Project Management Board, for the 25B road upgrade project from the center of Nhon Trach commune to National Highway 51, currently the handed-over land area has reached about 70% of the total area. The project implementation value currently reaches about 44% of the signed contract value.

The project to upgrade road 25B from the center of Nhon Trach commune to National Highway 51 is more than 9 km long, with a total investment of 1,493 billion VND, started in December 2024.

The above project, along with the provincial road 25C construction project (from Huong Lo 19 to National Highway 51), are projects implemented by Dong Nai with the aim of connecting traffic from Long Thanh airport to Ho Chi Minh City.

According to the plan, provincial roads 25B and 25C will connect Long Thanh airport through National Highway 51 to the Ben Luc - Long Thanh expressway, Ring Road 3 HCMC, reducing the load on the HCMC - Long Thanh - Dau Giay expressway.

Previously, the Dong Nai Provincial Construction Investment Project Management Board also proposed to accelerate the site clearance progress of the 25B road upgrade project from the center of Nhon Trach commune to National Highway 51 to be put into operation in 2026, connecting Long Thanh airport and Ho Chi Minh City.

According to the progress, compensation and site clearance for the project to upgrade road 25B from the center of Nhon Trach commune to National Highway 51 will be completed in March 2026.

HÀ ANH CHIẾN
RELATED NEWS

Prime Minister requests completion of Long Thanh airport project in the first half of 2026

|

The Prime Minister requested to urgently develop a plan and organize construction to ensure the completion of the Long Thanh airport project (phase 1) in the first half of 2026.

Thu Thiem - Long Thanh railway line 42km long connects Long Thanh airport

|

Dong Nai - The Thu Thiem - Long Thanh railway project has a total estimated investment of about 84,753 billion VND, completed in 2031.

Long Thanh airport connecting road will be difficult to open to traffic in March 2026

|

Dong Nai - Road 25C section from National Highway 51 to Huong Lo 19 lacks construction site, difficult to technically open to traffic in March 2026 to connect Long Thanh airport.

Groundbreaking ceremony for 2 bridges connecting Long Thanh airport and Ho Chi Minh City on January 15th

|

Dong Nai - It is expected that the groundbreaking ceremony for the Cat Lai bridge and Long Hung 2 bridge projects will be held on January 15 to celebrate the 14th National Party Congress.

Moment Iranian missile attacks US military base

|

The Iranian Islamic Revolutionary Guard Corps on February 28 confirmed that it had targeted many US facilities.

Live football Cong An Ha Noi vs Hoang Anh Gia Lai in round 14 of V.League

|

Live match between Hanoi Police and Hoang Anh Gia Lai in round 14 of V.League 2025-2026, taking place at 7:15 PM today (February 28).

Fire in Bo De ward, column of smoke rises tens of meters high

|

Hanoi - A fire suddenly broke out in alley 405 Bac Cau street, Bo De ward.

Officially opening the Tam Chuc Pagoda Spring Festival in 2026

|

Ninh Binh - February 28th, officially opens Tam Chuc Pagoda Spring Festival Binh Ngo 2026 with the theme "Dawn of the Buddhist realm - Tam Chuc Spring Opening".

Prime Minister requests completion of Long Thanh airport project in the first half of 2026

PHẠM ĐÔNG |

The Prime Minister requested to urgently develop a plan and organize construction to ensure the completion of the Long Thanh airport project (phase 1) in the first half of 2026.

Thu Thiem - Long Thanh railway line 42km long connects Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The Thu Thiem - Long Thanh railway project has a total estimated investment of about 84,753 billion VND, completed in 2031.

Long Thanh airport connecting road will be difficult to open to traffic in March 2026

HÀ ANH CHIẾN |

Dong Nai - Road 25C section from National Highway 51 to Huong Lo 19 lacks construction site, difficult to technically open to traffic in March 2026 to connect Long Thanh airport.

Groundbreaking ceremony for 2 bridges connecting Long Thanh airport and Ho Chi Minh City on January 15th

HÀ ANH CHIẾN |

Dong Nai - It is expected that the groundbreaking ceremony for the Cat Lai bridge and Long Hung 2 bridge projects will be held on January 15 to celebrate the 14th National Party Congress.