In the afternoon of July 15, Mr. Nguyen Le Huy - Standing Vice Chairman of the Provincial People's Committee chaired a meeting of the Provincial People's Committee to listen to the Department of Finance report on the disbursement situation and the roadmap for disbursement of the 2026 public investment capital plan for central capital, provincial capital and commune-level budget.
According to the report of the Department of Finance, the total public investment capital plan for 2026 of the province has been implemented at 48,203.264 billion VND, of which the capital plan for 2026 assigned by the Prime Minister is 43,311.7 billion VND. By the end of June 2026, the whole province had disbursed 16,589.664 billion VND, reaching 40.3% of the plan assigned by the Prime Minister.
The disbursement results in the first 6 months of the year are assessed to have many positive changes, closely following the Government's requirements on accelerating the disbursement of public investment capital.
In the context of many difficulties in site clearance, investment procedures, bidding and fluctuations in raw material prices, the province's disbursement rate is still higher than the national average.

Many investors and localities have proactively completed investment procedures, bidding, and organized construction right from the beginning of the year; a number of key projects and works have been focused on directing and accelerating progress.
However, the disbursement progress of some projects has not yet met the requirements. The main reasons are that site clearance work still has many obstacles; the preparation of investment, design, appraisal, approval and contractor selection for some large projects is still prolonged; the supply of construction materials is scarce, raw material prices are high; some projects still have outstanding advance capital from previous years, affecting disbursement progress.
Concluding the meeting, Mr. Nguyen Le Huy acknowledged the disbursement results of public investment capital in the first 6 months of the year, and at the same time requested departments, branches, localities and investors to closely follow the roadmap, striving to complete the target of disbursing 100% of the 2026 capital plan.
The Standing Vice Chairman of the Provincial People's Committee identified site clearance as a key stage, requesting investors to closely coordinate with localities and contractors to remove difficulties and accelerate progress; promptly report to the Provincial People's Committee on contents beyond their authority; assign specialized agencies to advise on solutions for the supply of construction materials.
At the same time, it is required that the adjustment of capital plans and total investment levels must be strict, prioritizing projects with good disbursement capacity, urgent, and promoting investment efficiency.
