50 billion VND dyke against landslides in Lao Cai runs out of water before Lunar New Year

Đinh Đại |

Lao Cai - The 50 billion VND anti-erosion embankment in Cam Duong ward is being accelerated by the contractor to construct the final items.

The landslide protection embankment in the area of groups 13, 14, 15 of the old Pom Han ward (now belonging to Cam Duong ward) has a total investment of 50 billion VND.

The project is implemented to protect the safety of dozens of households living in areas at high risk of landslides, especially during the rainy and flood season.

Tuyen ke hien hoan thien phan lon cac hang muc chinh. Anh: Dinh Dai
The dyke is currently completing most of the main items. Photo: Dinh Dai

The project started in April 2025, and according to the initial plan, it will be completed in August 2025. However, by mid-January 2026, the project could not be handed over due to many objective factors.

Records of Lao Dong Newspaper reporters on January 15 show that in the construction area, many main items of the embankment line have gradually been revealed. Machinery and equipment are still being mobilized at the construction site, workers are urgently constructing during favorable weather days.

Nha thau dang hoan tra mat duong va ranh thoat nuoc. Anh: Dinh Dai
The contractor is restoring the road surface and drainage ditch. Photo: Dinh Dai

However, due to the impact of prolonged rain for many months, the project progress was interrupted and could not be completed on schedule.

While waiting for the embankment line to be completed, the lives of people in the landslide area are still facing many difficulties. Dozens of households have to temporarily relocate, some renting rooms, some staying at the residential cultural house. Life conditions are cramped and lacking, especially the worry of prolonged heavy rain is still constant.

Don vi thi cong ho tro nguoi dan trong khu do nha da nut hong sau bao lu. Anh: Dinh Dai
The construction unit supports people in the area to dismantle broken and damaged houses after storms and floods. Photo: Dinh Dai

In order to complete the embankment line soon, the investor and contractor are mobilizing manpower and machinery to accelerate progress and ensure safety for households around the area.

On January 15, in an exchange with reporters, Mr. Nguyen The Trong - Deputy Director of Minh Duc General Construction Co., Ltd., the project construction unit - said that as soon as the weather was favorable, the contractor mobilized maximum manpower and machinery to compensate for progress. Up to now, the project has completed about 90% of the volume.

Currently, the unit is focusing on restoring the road surface and constructing the drainage system on the 23.9. route. We organize overtime, taking advantage of each sunny day to complete the project soon. The contractor is committed to bringing the project to completion before the Lunar New Year," Mr. Trong affirmed.

Toan canh tuyen ke o duong 23.9, phuong Cam Duong, tinh Lao Cai ghi nhan trong chieu 15.1. Anh: Dinh Dai
Overview of the embankment on 23.9 street, Cam Duong ward, Lao Cai province recorded in the afternoon of January 15. Photo: Dinh Dai

According to the Investment and Construction Project Management Board of Cam Duong - Hop Thanh area, this is a project that the provincial leaders are particularly interested in, regularly directing and urging progress.

Regarding the reasons for the slow completion, the leader of the Project Management Board said that the project did not encounter site clearance problems because it was completed early. However, prolonged rain in the past time has prevented many items from being implemented continuously, directly affecting the overall progress.

Currently, the investor is closely coordinating with the contractor, requesting to maximize favorable weather conditions to accelerate construction, soon complete the project, and stabilize people's lives.

Đinh Đại
RELATED NEWS

The shape of 3 anti-landslide embankments about to reach the finish line in Lao Cai

|

Lao Cai - With a turnover of tens of billions of VND, the 3 embankments in Cam Duong ward are expected to ensure safety for areas at risk of landslides and stabilize people's lives.

Engineers day and night build embankments to prevent landslides, race for the 31.12 mark in Khe Sanh

|

Quang Tri - Hundreds of officers and soldiers were mobilized and constructed day and night to prevent landslides in Khe Sanh commune. This is a key item in the "Quang Trung Campaign".

On the construction site of a hundred-billion-dong anti-erosion embankment on the banks of the Red River in Lao Cai

|

Lao Cai - The investor is coordinating with Corporation 319 (Ministry of National Defense) to increase human resources to construct an anti-landslide embankment in Bao Thang commune.

Foreign affairs contribute to creating a solid momentum to bring the country into a new era of development

|

Lao Dong respectfully introduces an article about Vietnam's Foreign Affairs by Standing Deputy Minister of Foreign Affairs Nguyen Minh Vu.

Traffic Tao Chi Trung talks about retirement life with a few billion VND

|

Traffic Tao Chi Trung said that he has a few billion VND deposited in the bank and has a "long-term" plan for retirement life.

Revealing the total amount of money spent on the 2025 Golden Kite Awards

|

Despite many difficulties, Canh Dieu 2025 is still organized and awarded to the winning units.

Propaganda and Mass Mobilization Application officially launched on mobile phones

|

The Central Propaganda and Mass Mobilization Committee launched the application of the Propaganda and Mass Mobilization sector (TGDV App) on mobile phones.

Interest rates and cash flow pose new challenges for real estate businesses

|

Real estate businesses are facing new challenges in terms of interest rates and cash flow, especially in the context of rising interest rates.

The shape of 3 anti-landslide embankments about to reach the finish line in Lao Cai

Đinh Đại |

Lao Cai - With a turnover of tens of billions of VND, the 3 embankments in Cam Duong ward are expected to ensure safety for areas at risk of landslides and stabilize people's lives.

Engineers day and night build embankments to prevent landslides, race for the 31.12 mark in Khe Sanh

HƯNG THƠ |

Quang Tri - Hundreds of officers and soldiers were mobilized and constructed day and night to prevent landslides in Khe Sanh commune. This is a key item in the "Quang Trung Campaign".

On the construction site of a hundred-billion-dong anti-erosion embankment on the banks of the Red River in Lao Cai

Đinh Đại |

Lao Cai - The investor is coordinating with Corporation 319 (Ministry of National Defense) to increase human resources to construct an anti-landslide embankment in Bao Thang commune.