Start of demolition of Phong Chau bridge

Tô Công |

Phu Tho - At Phong Chau bridge area in Phung Nguyen commune, Lam Thao district, many workers and machines have arrived at the scene.

According to Lao Dong Newspaper reporters on the afternoon of December 9 at Phung Nguyen commune (Lam Thao district), authorities mobilized many human resources and vehicles to the scene to demolish the remaining Phong Chau bridge.

4 may xuc duoc huy dong den doan cau Phong Chau con lai phia xa Phung Nguyen. Anh: To Cong.
Four excavators were mobilized to the remaining Phong Chau bridge section on the Phung Nguyen commune side. Photo: To Cong.

It can be seen that 3 large excavators have been brought and assembled on the bridge, another one is supporting workers in constructing the barrier (building the steel frame); other equipment and materials have also been assembled at the bridgehead; no-entry signs have also been installed... Under the bridge, the ground has been prepared in advance.

Don vi thi cong dang tien hanh lap dat hang rao. Anh: To Cong.
Construction unit is installing fence. Photo: To Cong.

Here, the remaining Phong Chau bridge has a total length of about 210 m, including spans 1 to 5. From top to bottom, there are still full items such as: lighting, railings, bridge deck, steel beams, reinforced concrete beam structures, bridge piers, bridge abutments.

Con nhieu cau kien can pha do. Anh: To Cong.
Many structures are ready to be demolished. Photo: To Cong.

According to the previous assessment of the authorities, span 5 was tilted outwards towards the Red River (with signs of subsidence of pier T6), spans 2, 3 and 4 showed signs of being twisted and tilted in the direction of the Red River flow; the expansion joints (connecting the bridge spans) were stretched much further than the original design.

In the coming time, the authorities will dismantle the steel truss and reinforced concrete approach spans; clear the lower structure of the old bridge to ensure waterway traffic safety, clear the flow... prepare the necessary conditions to start construction of the new Phong Chau bridge (assigned to start construction in December 2024).

Phan cau Phong Chau con lai co khoi luong sat thep rat lon. Anh: To Cong.
The remaining Phong Chau bridge has a huge amount of steel. Photo: To Cong.

On December 6, the Ministry of Transport approved the plan to build the new Phong Chau bridge, with a total investment of more than 635 billion VND from the central budget reserve in 2024. Of which, it is expected to allocate about 100 billion VND in 2024 and about 535 billion VND in 2025.

According to the design, the entire project route has a total length of nearly 653 m, the newly built bridge is more than 383 m long (to the end of the abutment), the road section at both ends of the bridge connecting to the existing road on the Lam Thao district side is more than 113 m long, on the Tam Nong side is nearly 156 m. The bridge width is 20.5 m, suitable for the width of the roadbed, arranged for 4 lanes for motor vehicles and 2 lanes for rudimentary vehicles.

Pha do cau Phong Chau cu de chuan bi mat bang xay cau moi. Anh: To Cong.
The demolition of the old Phong Chau bridge is also to prepare the ground for the construction of a new bridge. Photo: To Cong.

The bridge is permanently built with reinforced concrete and prestressed reinforced concrete, can withstand earthquakes of level 8, and has a clearance of 40m x 7m.

Regarding the demolition and salvage of the collapsed Phong Chau bridge located under the river, up to now, the authorities have completed the salvage of the entire N7 span along with many components and vehicles; currently, the work of bringing N6 span from the river to the shore (in the middle of the river, about 50m downstream from the bridge) is underway.

Tô Công
TIN LIÊN QUAN

Verifying the identity of the skull downstream of Phong Chau bridge

|

Phu Tho - A skull was discovered on the Red River alluvial plain in Vinh Lai commune, Lam Thao district, about 10km downstream from Phong Chau bridge.

Sand dredgers arrive at Phong Chau bridge to assist in salvage

|

Phu Tho - Sand dredgers have been mobilized to serve the demolition and salvage of span N6 of Phong Chau bridge, which is submerged deep under layers of sand and alluvium.

The water level of the Red River through Phong Chau Bridge changes continuously

|

Phu Tho - The water level of the Red River passing through Phu Tho province changes continuously, the sand dunes in the Phong Chau bridge area gradually disappear after the water rises.

Amending the decree on gold bar monopoly before June 2025

|

The National Assembly requires that before June 2025, the decree regulating gold trading, including regulations on gold bar monopoly, must be amended.

Deadline for submitting plan to merge Ministry of Construction and Ministry of Transport

|

Before December 20, the Ministry of Construction and the Ministry of Transport will work with the Ministry of Home Affairs to complete the plan for restructuring the apparatus after the merger.

Tu Lien Bridge - Hanoi expected to be completed after 2 years

|

A joint venture between Vingroup Corporation and Pacific Construction Corporation on the construction of Tu Lien Bridge (Hanoi) has been established to ensure progress.

RHYDER: Life changed when I was runner-up on Say Hi Brother

|

Runner-up of Say Hi Brother RHYDER shared with Lao Dong reporter about his 10-year journey pursuing music.

Confusion about sidewalk rental in Hanoi

|

Many Hanoians, although agreeing with the draft sidewalk rental plan in Hanoi, are still concerned about the rental price, management method and exploitation of this activity.

Verifying the identity of the skull downstream of Phong Chau bridge

Tô Công |

Phu Tho - A skull was discovered on the Red River alluvial plain in Vinh Lai commune, Lam Thao district, about 10km downstream from Phong Chau bridge.

Sand dredgers arrive at Phong Chau bridge to assist in salvage

Tô Công |

Phu Tho - Sand dredgers have been mobilized to serve the demolition and salvage of span N6 of Phong Chau bridge, which is submerged deep under layers of sand and alluvium.

The water level of the Red River through Phong Chau Bridge changes continuously

Tô Công - Nguyễn Chuyên |

Phu Tho - The water level of the Red River passing through Phu Tho province changes continuously, the sand dunes in the Phong Chau bridge area gradually disappear after the water rises.