Checking and finding solutions for the border project project is slow

Tân Văn |

Considered the new development motivation of Cao Bang city, but due to difficulties in site clearance and natural disasters, the construction of Cao Bang bypass road is behind schedule.

The hundred billion projects are behind schedule

Investment project to build Cao Bang bypass route by the Department of Transport of the province as an investor, with the Management Board of Construction Investment Project is the investor representative. The objective of the project is to be completed in the period 2021-2025, with a total investment of 371,843 billion dong. However, up to now, the implementation volume is only about 130 billion dong, reaching 68.4% compared to the signed contract value, 30% later than the original plan. By the end of 2024, disbursed capital reached VND 126.17 billion out of VND 202.84 billion, equivalent to 62% of the assigned plan.

The site clearance for the project is implemented separately into a separate subproject. In order to implement the project, Cao Bang province needs to change the purpose of using 5.65 hectares of land, including rice land, protective forest land, special -use forest and production forest land. Up to now, the site clearance has been completed 87%, mainly in phase 1.

As noted on 9.2 of PV, this route will go through four wards: Duyet Trung, Tan Giang, Hoa Chung and Song Hien, with a total length of about 7.56km, starting from Duyet Trung ward and ending with Quoc Lo 3 in Song Hien ward. However, there are still many areas that cannot be cleared, affecting the construction progress.

According to the people, Mr. Le Van Chinh (Group 18, Song Hien Ward) said that the prolonged construction made the lives of people difficult. "We have to move on the unfinished construction road, dusty and mud covered with mud, not to mention the landslide occurred in some households due to the impact of construction and heavy rain." - Mr. Chinh said.

"Many parcels of land have errors when papers are perennially planted, but people have built houses to live on it for a long time, so it makes it more or less difficult for the clearance process" - Representative of Cao Bang City People's Committee information to PV.

Recently, Vice Chairman of Cao Bang Provincial People's Committee, Mr. Hoang Van Thach, chaired the actual inspection of the project progress, surveyed landslides and areas that were facing difficulties in the clearance. equal.

People are troublesome

After the inspection, Mr. Thach chaired a meeting with departments, agencies and People's Committee of Cao Bang City to listen to the report and propose the settlement plan. According to the report at the meeting, the project progress was 30% delayed compared to the plan due to the impact of storms and storms, leading to landslides in many positions, having to reinforce taluy roofs and transportation of rocky soil. Along with that, the ground clearance is also delayed.

During the meeting, Vice Chairman of the People's Committee Cao Bang asked the Department of Transport to direct the construction units right after the Tet holiday, speeding up the progress. In particular, at landslides, it is necessary to urge contractors to overcome, clean and reinforce the roof, ensuring long -term geological stability. Cao Bang City People's Committee must also preside over and coordinate with departments and branches to solve issues related to site clearance and change of land use purpose to implement the project. At the same time, the application procedures should be completed to submit to the provincial People's Council in the upcoming thematic meeting.

The City People's Committee is also required to develop a settlement plan for households who have received compensation but has not handed over the ground, and also implemented coercive procedures in accordance with the law.

Mr. Dam Hai Trieu - Deputy Chief of Office of Cao Bang Provincial People's Committee - added: "At the meeting on 5.2, Vice Chairman Hoang Van Thach assigned tasks to units from now until 30.6 to be completed. , pine and bring the road to use ".

Tân Văn
TIN LIÊN QUAN

Ea Tam irrigation reservoir worth nearly 1,500 billion VND is behind schedule and has many problems

|

The Ea Tam irrigation reservoir project, with a total investment of nearly 1,500 billion VND in the center of Buon Ma Thuot city, is facing many difficulties, the progress of site clearance and construction has not met expectations...

The Ring Road 4 Project must not be delayed

|

Chairman of the Hanoi People's Council Nguyen Ngoc Tuan requested the project investor and the construction contractor not to let the Ring Road 4 project slow down.

Hour 9: I am the third person - Part 2

|

Hour 9 - The husband in the story has developed feelings for his wife's best friend. Where will this marriage go?

Mobilizing resources to treat accident victims on National Highway 6

|

The accident on National Highway 6, Sup Vat commune, Yen Chau district, Son La province caused many casualties and heavy casualties were transferred to the upper level.

Ho Chi Minh City University of Education has many violations in the 17.42 billion VND project

|

The Inspectorate of the Ministry of Education and Training concluded that Ho Chi Minh City University of Education has limitations, shortcomings, and violations related to the project with an investment of 17.42 billion VND.

making a living on landfills

|

Soc Trang - The landfill is a home, the only source of life for dozens of households.

Intersection in Hanoi before proposal to build underpass worth over VND1,400 billion

|

Hanoi - The Hoang Quoc Viet extended underpass - Ring Road 3 is proposed to be built 600m long, with an investment capital of more than VND1,400 billion to help reduce congestion and increase connectivity.

Ea Tam irrigation reservoir worth nearly 1,500 billion VND is behind schedule and has many problems

BẢO TRUNG |

The Ea Tam irrigation reservoir project, with a total investment of nearly 1,500 billion VND in the center of Buon Ma Thuot city, is facing many difficulties, the progress of site clearance and construction has not met expectations...

The Ring Road 4 Project must not be delayed

KHÁNH AN |

Chairman of the Hanoi People's Council Nguyen Ngoc Tuan requested the project investor and the construction contractor not to let the Ring Road 4 project slow down.

Loạt dự án chậm tiến độ ở Bắc Ninh: Khu du lịch 20 năm vẫn dang dở

Vân Trường |

Bắc Ninh - Dự án Khu du lịch Thiên Thai (huyện Gia Bình) sau gần 20 năm triển khai, xây dựng đến nay vẫn là công trình dang dở.