On March 16, the People's Committee of Kon Tum province said that it had requested competent authorities to focus on promoting the progress of projects to build transport infrastructure, embankments, and resettlement projects...
The project to build a bridge and a road at both ends of the bridge from Ia Chim Tourist Area to Ya Ly Commune, the provincial Department of Construction must speed up the construction progress, ensuring completion on time. At the same time, the Department must be responsible to the Provincial People's Committee for the progress of this project.
For the Kon Tum city's main road project in the West, the Provincial Management Board of Investment and Construction of Traffic, Civil and Industrial Works has directed the construction unit to arrange enough human resources and materials, "wherever the site is cleared, construction will be done" to speed up the progress.
The Board is responsible for completing construction packages 1 and 2 (section from Km7, National Highway 24 to Provincial Road 671) before December 31, 2025.
As for the project of Embankment to prevent floods and landslides in ethnic minority villages along the Dak Bla River, the Management Board has accelerated the construction progress according to plan. The construction needs to ensure quality, urban aesthetics, serving the development of the city's night-time economy and tourism.
The province requested the Kon Tum City People's Committee to develop a resettlement plan for affected households, ensuring completion in June 2025. At the same time, implement a project to expand the population in ethnic minority villages in Kon Tum's inner city.
People's expansion is associated with resettlement and settlement to ensure people have land for production and stabilize social life.