Dak Nong resolutely disburses behind-the-scenes traffic projects

PHAN TUẤN |

Dak Nong - Vice Chairman of Dak Nong Provincial People's Committee requested relevant units to focus on removing obstacles, speeding up construction progress, and disbursing public investment capital.

Many projects are behind schedule

In Krong No district, the road project to develop the new urban area of Dak Am town has a total investment of 80 billion VND.

The project will be implemented in the period of 2022 - 2025, the investor is the Project Management and Land Fund Development Board of Krong No district.

In 2025, the project was allocated more than 31.6 billion VND. However, by March 7, the project had only disbursed 200 million VND, reaching 0.6%.

Similarly, the road project from the center of Dak Song district to Thuan Ha commune and Dak N'Drung commune is invested by the Dak Song District Project Management and Land Fund Development Board with a total cost of 82 billion VND.

The project was invested in the period of 2021 - 2024 but has not been completed yet. In 2025, the project was assigned a capital plan of nearly 28.5 billion VND. By March 7, the project had disbursed 0%.

Requesting contractors to speed up progress

Recently, after inspecting the two projects, Vice Chairman of the Provincial People's Committee Le Trong Yen emphasized that traffic routes are very important, contributing to promoting local socio-economic development.

Moreover, 2025 is a pivotal year with many important events. Focusing on completing projects and works on schedule will contribute to the celebration of the Provincial Party Congress and major national holidays.

Therefore, Mr. Le Trong Yen requested investors to focus on urging contractors to increase human and material resources, speeding up the construction progress of projects. The completion of the projects will bring great socio-economic efficiency to the locality.

The project investor proactively reviews and promotes site clearance and strengthens inspection and supervision of construction progress.

Relevant units need to coordinate closely to ensure timely and effective disbursement, contributing to promoting local socio-economic growth.

In the face of slow disbursement of public investment capital, the Vice Chairman of the Dak Nong Provincial People's Committee has directed departments, branches, sectors and localities to urgently implement solutions to remove obstacles and speed up the progress of projects.

PHAN TUẤN
TIN LIÊN QUAN

Dak Nong disburses national target capital of VND 2,280 billion

|

Lam Dong - By the end of February 2025, the whole province will disburse nearly VND 2,280 billion (71% of the plan), with more than VND 1,520 billion remaining in the national target program capital.

Quang Nam pays 153 billion VND in central government capital due to slow disbursement

|

Quang Nam - The province plans to repay nearly 154 billion VND of central budget capital, due to failure to disburse on time.

Nghe An resolutely urges disbursement of public investment capital

|

Nghe An Provincial People's Committee has taken drastic actions to speed up the disbursement progress of public investment projects.

Speed up capital allocation, avoid pressure to disburse at the end of the year

|

Although it has entered February, many ministries, central and local agencies have not yet completed the allocation of public investment capital plans. This puts great pressure on disbursement progress and capital efficiency in the last months of the year.

A wall collapsed in Can Tho when demolished, a worker injured

|

Can Tho - On the afternoon of March 15, a house wall collapse suddenly occurred near the Mau Than - 3 Thang 2 - Tran Hung Dao intersection, in Ninh Kieu district.

Despite the danger, people freely fish in prohibited waters

|

Hoa Binh - Although warning signs have been erected along the Hoa Binh Hydropower Plant area, many people are still calmly fishing right at the foot of the dam.

Transferring the Ministry of Public Security to consider investigating 2 projects in Vinh Long

|

The Government Inspectorate forwarded information and documents to the Ministry of Public Security for consideration and investigation of the two projects in Vinh Long.

Vietnam travels to the United Nations to map the Gulf of Tonkin base road

|

Vietnam has used the United Nations' basic golf and Tonkin route map and coordinates.

Dak Nong disburses national target capital of VND 2,280 billion

PHAN TUẤN |

Lam Dong - By the end of February 2025, the whole province will disburse nearly VND 2,280 billion (71% of the plan), with more than VND 1,520 billion remaining in the national target program capital.

Quang Nam pays 153 billion VND in central government capital due to slow disbursement

Hoàng Bin |

Quang Nam - The province plans to repay nearly 154 billion VND of central budget capital, due to failure to disburse on time.

Nghe An resolutely urges disbursement of public investment capital

QUANG ĐẠI |

Nghe An Provincial People's Committee has taken drastic actions to speed up the disbursement progress of public investment projects.

Speed up capital allocation, avoid pressure to disburse at the end of the year

Thạch Lam |

Although it has entered February, many ministries, central and local agencies have not yet completed the allocation of public investment capital plans. This puts great pressure on disbursement progress and capital efficiency in the last months of the year.