Building temporary roads to serve the construction of bridges that have been shelved for many years in Hanoi's inner city

SÓNG HỮU |

Hanoi - The contractor is making a temporary road to re-construct the L3 bridge across the Lu River, part of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, after many years of being shelved.

On October 22, many workers and machinery were mobilized to construct a temporary road to serve the construction of the L3 bridge across the Lu River under the Ring Road 2.5 project, Dam Hong - National Highway 1A section.

Speaking to Lao Dong Newspaper reporters at the construction site, Mr. Le Thanh Tung, Deputy Director of Hoang Mai - Hanoi Construction Investment Company Limited (project enterprise) said that up to now, the work of moving underground and above-ground works (electricity, water, telecommunications) in the area at both ends of the bridge has been completed, and the site has been handed over to the contractor for the construction of bridge L3.

s
The construction area of the L3 bridge across the Lu River belongs to the Ring Road 2.5 project, Dam Hong - National Highway 1A section (Hanoi). Photo: Song Huu
s
The L3 bridge over the Lu river has been suspended since 2020. Photo: Song Huu
s
s
Currently, the temporary road on Trinh Dinh Cuu Street for the construction of L3 Bridge has been completed. Photo: Song Huu

On Trinh Dinh Cuu Street, the contractor has completed the temporary road section. On Ha Ke Tan Street, the construction of a temporary road serving the construction of L3 Bridge is also being implemented, expected to be completed in the next few days.

"We will ask for permission from the Hanoi Department of Construction to divert traffic to serve the bridge construction. During the construction process, the contractor will organize traffic flow in accordance with regulations and issued licenses, ensuring safe and smooth travel for people in the area on this route" - Mr. Tung said.

Regarding the construction part, Mr. Tung said that the L3 bridge over the Lu river has completed the middle span. The contractor will continue to drill and fill piles, construct two bridge abutments and the remaining items.

s
Mr. Tung (2nd from left) directly inspects the project construction work. Photo: Song Huu
s
Machinery and construction materials are gathered in the Ha Ke Tan street area. Photo: Song Huu
s
The construction of a temporary road on Ha Ke Tan Street is being implemented by the contractor. Photo: Song Huu
s
s
Workers working at the project site. Photo: Song Huu

According to Mr. Tung, the total volume of the route has reached about 70%. For the remaining volume, the investor is directing the contractor to mobilize maximum machinery and personnel to organize the construction in 3 shifts, 4 teams, committed to ensuring safety and quality, and completing the project in the first quarter of 2026.

In addition, the investor also requires the contractor to strictly implement safety measures in construction, regularly watering and washing the road surface to limit dust. Deep holes in the construction site are also required to be fenced off and warning signs are placed to ensure safety for people.

s
s
barriers and warning signs have been installed to ensure the safety of the people. Photo: Song Huu
s
The contractor sprays water onto the road surface 4 times/day to limit dust during the project construction process. Photo: Song Huu

Mr. Le Thanh Tung assessed that the Dam Hong - National Highway 1A section of Ring Road 2.5 is an important link in the Hanoi urban transport network. When completed, the route will connect the southern area of the city with major traffic axes, thereby reducing the burden on Ring Road 2 and Ring Road 3, which are increasingly overloaded.

"When the route is opened to traffic in sync with the Kim Dong - Giai Phong underpass, it will also open up opportunities for new urban development in the southern area of the city" - Deputy Director of Hoang Mai - Hanoi Construction Investment Company Limited added.

Talking to reporters, many people in the area expressed their hope that the road will be completed soon, technically opened to traffic, making traffic and travel more convenient and directly promoting socio-economic development.

The project to build the Ring Road 2.5, Dam Hong - National Highway 1A section (Hanoi) is invested in the form of a BT (build - transfer) contract with a length of about 1.3 km, with a total investment of more than 1,300 billion VND.

The project started in 2014 and was expected to be completed in 2017 but was behind schedule.

In 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason is due to difficulties in site clearance and extension of BT contract appendices.

In May 2025, the basic difficulties and obstacles were resolved, and the project was officially restarted.

SÓNG HỮU
RELATED NEWS

Ready to re-construct the bridge on the billion-dong road that has been unfinished for many years in Hanoi

|

Hanoi - L3 bridge over Lu river - an important item of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, will resume construction from October 2025.

The billion-dollar road in Hanoi is being constructed day and night, the investor is committed to completing it on schedule

|

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being urgently constructed by the contractor, the investor is committed to bringing the project to the finish line in the first quarter of 2026.

The progress of the billion-dollar road in Hanoi is being accelerated, to be completed in 2026

|

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being accelerated by the contractor, the entire route is expected to be completed in 2026.

Workshop "Promoting self-respect and full tax contributions - Building a strong era"

|

Improving tax compliance is not only a technical task, but a step forward in cultural development and trust between the State and citizens.

A good doctor is to consider patients as teachers

|

The Deputy Minister of Health said that good doctors must examine patients, study them, consider patients as teachers, the greatest book of his life.

Quang Tri has heavy rain before the wedding of Miss Do Thi Ha and the young master of Son Hai Group

|

The wedding of Miss Do Thi Ha and the young master of Son Hai Group is taking place in Quang Tri. Heavy rain with winds as storm No. 12 is approaching.

Minister Nguyen Kim Son talks about the roadmap to build a shared textbook set

|

Minister Nguyen Kim Son said that it is expected that in November the Ministry will complete the plan to build a shared textbook set and submit it to the Government for approval.

Thailand investigates new link suspected of involving Cambodian scam leader Chen Zhi

|

Thailand has officially opened an investigation into Prince International - a business suspected of being involved in the network of Cambodian scammer Chen Zhi.

Ready to re-construct the bridge on the billion-dong road that has been unfinished for many years in Hanoi

SÓNG HỮU |

Hanoi - L3 bridge over Lu river - an important item of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, will resume construction from October 2025.

The billion-dollar road in Hanoi is being constructed day and night, the investor is committed to completing it on schedule

SÓNG HỮU |

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being urgently constructed by the contractor, the investor is committed to bringing the project to the finish line in the first quarter of 2026.

The progress of the billion-dollar road in Hanoi is being accelerated, to be completed in 2026

SÓNG HỮU |

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being accelerated by the contractor, the entire route is expected to be completed in 2026.