Information from the People's Committee of Lang Son province said that the unit has just issued a document on reviewing the collective and individual responsibilities related to the Project to invest in building and renovating the Commune Health Station in Loc Binh district.
Accordingly, the provincial leaders requested the People's Committee of Loc Binh district to review the responsibility of the collective and individuals involved in the slow implementation of the investment project and propose to adjust the project implementation time.
In addition, the Department of Construction is required to review the responsibilities of relevant groups and individuals during the review process, and advise the People's Committee to adjust the project completion time.
According to the reporter's investigation, the investment project to build and renovate the commune-level health stations in Loc Binh district was decided by the Chairman of Lang Son Provincial People's Committee with the purpose of building health stations to ensure facilities to meet the needs of medical examination and treatment for people in the communes of Ai Quoc, Tam Gia, Huu Lan, Khanh Xuan, Minh Hiep, Dong Buc, Mau Son, Nam Quan, Tu Mich and Loc Binh town, Loc Binh district.
The project was assigned to the People's Committee of Loc Binh district as the investor with a total amount of nearly 15 billion VND, from the central budget under the Socio-Economic Recovery and Development Program. The expected implementation period is from 2022-2023.
However, the Department of Construction of this province proposed that the People's Committee agree to adjust the project implementation time to the end of February 2025.
Mr. Duong Xuan Huyen - Vice Chairman of the Provincial People's Committee said that according to the Resolution of the National Assembly, for the capital source of the Socio-Economic Recovery and Development Program, it is only allowed to extend the implementation period and disbursement of investment capital until December 31, 2024.
At the same time, in the directive documents of the Provincial People's Committee, for transitional projects, it is required to disburse 100% of the capital plan by the end of the above-mentioned period.