Leaders of Ho Chi Minh City People's Committee divide the work of handling a series of large backlog projects

MINH QUÂN |

Chairman of the Ho Chi Minh City People's Committee Phan Van Mai and five vice chairmen directly directed the removal of a series of stalled projects, speeding up the completion progress to avoid waste and loss.

The People's Committee of Ho Chi Minh City has just issued a notice assigning the Standing Committee of the People's Committee to monitor and direct the settlement of pending projects, stop construction, urgently deploy, complete, and put into use to prevent waste and loss.

Chairman of Ho Chi Minh City People's Committee Phan Van Mai monitors and directs the settlement of:

- BT project of Thu Thiem 2 bridge (Ba Son bridge).

- BT project to invest in building 4 roads in Thu Thiem New Urban Area.

- BT project to build a parallel road from Mai Chi Tho Street through Nam Rach Chiec Residential Area to Ring Road 2.

- Project to solve tidal flooding in Ho Chi Minh City area considering climate change factors (phase 1).

- Phan Dinh Phung Stadium Project.

- Observation Tower Complex Project belongs to the Functional Area in Thu Thiem New Urban Area.

- Saigon Safari Park Project - Cu Chi.

- Land plot number 1 Ly Thai To.

- Investment project to build National Cultural Historical Park.

- Binh Quoi - Thanh Da Urban Area Project, Binh Thanh District.

Du an ngan trieu TPHCM “dap chieu“, hien lai vay phat sinh 1,7 ti dong moi ngay. Anh: Minh Quan
The Ho Chi Minh City tide control project is "shelved", currently generating 1.7 billion VND in interest every day. Photo: Minh Quan

Mr. Duong Ngoc Hai - Permanent Vice Chairman of Ho Chi Minh City People's Committee:

- Monitor and direct the implementation of inspection and examination conclusions, cases and judgments.

- Focus on directing the implementation of the conclusions of Inspection Team 857.

- Land lot number 8 - 12 Le Duan, Ben Nghe ward, District 1.

- Land lot number 2 - 4 - 6 Hai Ba Trung, Ben Nghe ward, District 1.

- Sing - Viet project, Binh Chanh district.

Mr. Vo Van Hoan - Vice Chairman of Ho Chi Minh City People's Committee, monitors and directs the resolution:

- Industrial Parks Pham Van Hai 1 + 2, Le Minh Xuan 2, Le Minh Xuan expansion, Lang Le - Bau Co.

- City Aquaculture Center Project in Can Gio District (area 99.99 ha).

- Investment project to build a high-tech agricultural zone for the aquaculture industry in Can Gio district (area 89.74 ha).

- Project to build the City Aquaculture Center in Phu Xuan commune, Nha Be district (area 71 ha).

Mr. Bui Xuan Cuong - Vice Chairman of Ho Chi Minh City People's Committee:

- Project to build the section connecting Pham Van Dong Street to Go Dua intersection, National Highway 1 (Van Phu - Bac Ai).

- Binh An Water Plant Project.

- Auction of resettlement apartment project: 3,790 Thu Thiem apartments, 953 apartments in Vinh Loc B residential area, Binh Chanh district.

- Determine financial obligations of Lotte's Eco-smart city project, 230 Nguyen Trai project.

- One Central HCM Project - Investor: Saigon Glory Company Limited.

- Public investment projects under the management of the sector have not been completed to date and have exceeded the capital allocation period as prescribed by the Law on Public Investment.

- Directing the review of projects and residential areas that are not fully invested according to the planning.

Mr. Nguyen Van Dung - Vice Chairman of Ho Chi Minh City People's Committee:

- Monitor and direct the implementation of audit conclusions.

- Norfolk Hotel Project.

- General monitoring of public investment projects that have not been completed to date and have exceeded the capital allocation period as prescribed by the Law on Public Investment.

- Caravelle Hotel expansion land.

- Land plot number 2 - 4 - 6 Nguyen Hue - expansion of Majestic hotel.

- Tax Commercial Center land (old).

- Land plot number 62 Tan Thanh.

- Urge the progress of reviewing cases of houses and lands that are currently vacant, propose plans to rearrange and handle houses and lands according to Decree No. 167/2017/ND-CP dated December 31, 2017; propose plans to auction houses and lands; plans to recover them for use.

Ms. Tran Thi Dieu Thuy - Vice Chairman of Ho Chi Minh City People's Committee:

- Projects for 50 years of Southern Liberation.

- Public investment projects under the management of the sector have not been completed to date and have exceeded the capital allocation period as prescribed by the Law on Public Investment.

- Urge investment and upgrading of 10/12 theaters that are not qualified to organize performances, causing waste of facilities: Workers Theater (No. 30 Tran Hung Dao, District 1), theater at 243 Ly Tu Trong, District 1 (used to be the headquarters of the Hat Boi Art Theater)...

MINH QUÂN
RELATED NEWS

5 steps to completely handle pending projects in Ho Chi Minh City

|

Faced with a series of stalled or ineffective projects, the Ho Chi Minh City People's Committee has issued a detailed plan to thoroughly handle and prevent waste.

Ho Chi Minh City directs handling of backlog projects, not letting them go to waste

|

Ho Chi Minh City directed to thoroughly handle backlog projects, stop construction and urgently complete them for use, to avoid waste and loss.

Viet Duc Friendship Hospital Ninh Binh facility completes appraisal before opening day

|

After completing the appraisal of the Ministry of Health, Viet Duc Friendship Hospital Ninh Binh facility has met the conditions for issuing an Operating License, officially operating from July 9, 2026.

Vietnamese rescue team removes 57 bodies from rubble in Venezuela

|

The Vietnamese rescue and relief team, after days of supporting the search for victims after the earthquake, has removed 57 bodies from the rubble in Venezuela.

Gold price update morning 7.7: Sideways, momentum not strong enough

|

Gold price update morning 7.7: Entering a sideways phase. The market has not found strong enough momentum to overcome the 4,200 USD/ounce resistance zone.

5 steps to completely handle pending projects in Ho Chi Minh City

MINH QUÂN |

Faced with a series of stalled or ineffective projects, the Ho Chi Minh City People's Committee has issued a detailed plan to thoroughly handle and prevent waste.

Ho Chi Minh City directs handling of backlog projects, not letting them go to waste

MINH QUÂN |

Ho Chi Minh City directed to thoroughly handle backlog projects, stop construction and urgently complete them for use, to avoid waste and loss.

Dự án ngăn triều nằm im, lãi vay phát sinh 1,7 tỉ đồng mỗi ngày

MINH QUÂN |

Là một trong những dự án bị Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính điểm tên, dự án chống ngập do triều cường gần 10.000 tỉ đồng tại TPHCM dù đạt 93% khối lượng, nhưng lại "đắp chiếu" nhiều năm, khiến lãi vay phát sinh hằng ngày hơn 1,7 tỉ đồng.