Lao Cai names a series of projects with slow disbursement of public investment capital

Đinh Đại |

A series of sluggish construction investment projects have caused the disbursement rate of public investment capital in Lao Cai province to only reach about 60%, even though it is now the end of December.

On December 28, according to the reporter of Lao Dong Newspaper at the border bridge project across the Red River in Ban Vuoc commune, at the project construction site, heavy machinery and workers were deployed.

Through research, the total investment of the project is 1,490 billion VND, the Central budget supports 950 billion VND, the local budget matches 540 billion VND. Up to now, this project still has more than 192 billion VND that cannot be disbursed.

Du an dau tu xay dung cong trinh Cau bien gioi qua song Hong tai xa Ban Vuoc va ha tang ket noi con gan 200 ti chua giai ngan. Hien du an cung dang vuong mat bang va dat dap khien tien do thi cong bi anh huong. Anh: Dinh Dai
The investment project to build the Border Bridge across the Red River in Ban Vuoc commune and connecting infrastructure still has nearly 200 billion VND that has not been disbursed. Photo: Dinh Dai

As for the project to build Bat Xat District General Hospital, 200 billion VND was invested to build a new one. After more than a year of construction, the project has completed over 80% of the work volume.

The project currently has about 19.5 billion VND left to be disbursed. The most difficult problem is that the district is urgently clearing the land.

Benh vien Da khoa huyen Bat Xat la mot trong nhung du an duoc tinh Lao Cai dau tu nham hien dai hoa ha tang y te. Anh: Dinh Dai
Bat Xat District General Hospital is one of the projects invested by Lao Cai province to modernize medical infrastructure. Photo: Dinh Dai

Van Ban District General Hospital, with an investment capital of 200 billion VND, is also in the process of completion. According to research, the project still has 20 billion VND that has not been disbursed in 2024.

In addition, at the project to upgrade and renovate the Ban Xeo - Y Ty route with an investment capital of 200 billion VND in Bat Xat district, at the construction site, workers are still working to complete the road. According to the report, there are still 25 billion VND that have not been disbursed by the end of 2024.

Not only that, a series of other transportation projects are also slow to disburse, such as upgrading the road from Lang Giang bridge to National Highway 70, which is still 72.5 billion VND, and the road connecting Noi Bai - Lao Cai expressway to Sa Pa, which is still 26.5 billion VND...

Benh vien Da khoa huyen Van Ban dang gap rut hoan thanh. Anh: Dinh Dai
Van Ban District General Hospital is being rushed to completion. Photo: Dinh Dai

According to a report from the Department of Planning and Investment of Lao Cai province, as of mid-December 2024, the total disbursement value of the province reached 3,954/6,588 billion VND, equal to 60% of the plan, the total undisbursed public investment capital in 2024 to date is 2,633 billion VND. Compared to the requirement of reaching over 95% of the public investment disbursement plan in 2024 assigned by the Central Government, the current progress of only 60% is very slow.

In addition to the objective reasons pointed out, the disbursement progress of the 2024 public investment capital plan is slow due to a series of subjective reasons under the responsibility of the Departments, branches, People's Committees of districts, towns, cities, and investors.

Nhieu du an giao thong tai Lao Cai dang bi cham giai ngan. Anh: Dinh Dai
Many transport projects in Lao Cai are facing slow disbursement. Photo: Dinh Dai

Faced with the above situation, most recently, in urgent notice No. 7454, Chairman of Lao Cai Provincial People's Committee Trinh Xuan Truong requested that departments, branches, sectors, and localities tighten discipline and order associated with the sense of responsibility of leaders in the process of handling documents; acceptance - payment; in coordinating opinions; and extending contract implementation time.

It should be noted that the delay in coordinating the handling of documents and giving opinions from departments and branches is one of the main subjective reasons limiting the progress of disbursement of public investment capital.

Viec cac du an cham giai ngan da lam anh huong chung den muc tieu thuc hien tren 95% ke giai ngan von dau tu cong cua tinh. Anh: Dinh Dai
Slow disbursement of projects has affected the overall target of implementing over 95% of the province's public investment disbursement plan. Photo: Dinh Dai

Units need to proactively review and evaluate the disbursement capacity of each project, carry out acceptance procedures - payment for completed volume weekly; synthesize the additional capital needs of the projects, propose a plan to report to the Department of Planning and Investment for synthesis and submission to the Provincial People's Committee for approval.

Mr. Trinh Xuan Truong affirmed that the province will handle the responsibility of the head of the investor if the projects have their capital withdrawn by the Central Government.

Đinh Đại
TIN LIÊN QUAN

Reclaiming more than 25 hectares of land from a gold mining company in Lao Cai

|

Lao Cai province decided to reclaim more than 25 hectares of land from Nhan Joint Stock Company.

Prime Minister attends groundbreaking ceremony of social housing project worth over 2,000 billion in Lao Cai

|

On the afternoon of December 22, Prime Minister Pham Minh Chinh attended the groundbreaking ceremony of the Golden Square Lao Cai Social Housing project with an investment capital of more than 2,000 billion VND.

Checking a student vehicle, Hanoi Traffic Police discovered a modified vehicle

|

Hanoi - Checking the parking lot around the school, the Traffic Police discovered a modified student vehicle.

Russia accuses Ukraine of violating ceasefire agreement

|

Russia has accused Ukraine of violating the deal while President Zelensky has seen a temporary ceasefire in the energy sector as a diplomatic victory.

Fire in Ho Chi Minh City, mother dies while returning to save her child

|

HCMC - At the time of the fire, the mother rushed to take her young child out and returned home to save the old son. Unfortunately, the house collapsed, both mother and child and the brother died.

Miss Do My Linh's husband becomes Chairman of Vietravel Airlines

|

Businessman Do Vinh Quang - husband of Miss Vietnam Do My Linh has just been elected as Chairman of Vietravel Airlines at the age of just 30.

Myanmar earthquake and measures to reduce aftershocks in Vietnam

|

The earthquake in Myanmar affected some places in Vietnam, so measures should be taken to reduce the risk of aftershocks from neighboring areas.

Hoi An searches for the person who destroyed the ancient town stele near Chua Cau

|

Taking advantage of the dark, the bad guys seriously sabotage an ancient stele near Chua Cau, Hoi An.

Lào Cai bắt nhóm cho vay lãi nặng với lãi suất 365%/năm

Đinh Đại |

Công an Lào Cai đã triệt phá, bắt nhiều đối tượng cho vay lãi nặng với lãi suất lên đến 365%/năm.

Reclaiming more than 25 hectares of land from a gold mining company in Lao Cai

Đinh Đại |

Lao Cai province decided to reclaim more than 25 hectares of land from Nhan Joint Stock Company.

Prime Minister attends groundbreaking ceremony of social housing project worth over 2,000 billion in Lao Cai

Đinh Đại |

On the afternoon of December 22, Prime Minister Pham Minh Chinh attended the groundbreaking ceremony of the Golden Square Lao Cai Social Housing project with an investment capital of more than 2,000 billion VND.