Lao Cai stops construction of 3 administrative headquarters worth hundreds of billions of VND

Đinh Đại |

Lao Cai - In the process of arranging and organizing the apparatus, a series of hundred-billion-dong headquarters projects in the districts will be temporarily suspended.

Sa Pa Town Administrative Headquarters

The Sa Pa town administrative agency headquarters project has a total investment of VND197.8 billion, invested by the Department of Transport - Construction.

The project belongs to group B project, designed in a modern architectural style, including 6 upper floors, 1 basement, construction area of 5,108 m2, floor area of 14,600 m2.

In which, the basement is arranged for parking and technical equipment of the building, the floors from the 1st to the 5th floor are arranged with offices for agencies, meeting rooms, and conference rooms; the 6th floor is designed as a storage warehouse for agencies and units.

In mid-March 2025, according to records, the new administrative center is located on the top of a hill, in the Northwest Sub-region of the town. Around the area are a series of townhouses under construction.

Tru so hanh chinh moi cua thi xa Sa Pa (Lao Cai). Anh: Dinh Dai
New administrative headquarters of Sa Pa town (Lao Cai). Photo: Dinh Dai

Through observation, up to now, the rough construction of the project has almost been completed, the shape of the headquarters is gradually emerging.

According to Sa Pa Town Party Secretary Phan Dang Toan: The project to build a new administrative center of the town has now completed the construction. Within the first 6 months of 2025, the project will be completed and put into use.

Bao Thang District Administrative Headquarters

The new headquarters of Bao Thang District Administrative Center was built in Pho Lu town, on the old headquarters.

In mid-March, according to records, the hundred-billion-dong headquarters of Bao Thang district has gradually emerged after a period of construction.

The architectural scale of the office is 15 stories high, with 3 floors of the base and 12 floors of the tower, the construction area is 3,370m2, the total floor area is 13,591m2. The investment cost of the project is 200 billion VND, with the Bao Thang District Investment and Construction Project Management Board as the investor's representative.

Trung tam hanh chinh huyen Bao Thang. Anh: Dinh Dai
Bao Thang District Administrative Center. Photo: Dinh Dai

The project started in December 2023 and is expected to be completed in 2025.

On March 13, speaking with a reporter from Lao Dong Newspaper, Deputy Director of the Bao Thang District Construction Investment Project Management Board Vu Hong Ha said: Lao Cai province has issued a document requesting a temporary suspension of the implementation of works and projects in the process of implementing the arrangement and organization of the political apparatus. Therefore, we are synthesizing to report to the Provincial People's Committee before March 15".

Bac Ha District Administrative Headquarters

The project to build the administrative headquarters of Bac Ha district with an investment capital of 200 billion VND is funded by the central budget and the budget of Bac Ha district.

The project has a scale of: 5-storey apartment building, including 3 clusters of space arranged in 3 levels of the terrain connected by a roofed corridor system, creating a seamless and convenient working space.

Phoi canh 3D sau khi tru so hanh chinh huyen Bac Ha hoan thanh xay dung.
3D perspective after the construction of the Bac Ha district administrative headquarters is completed.

The project has a duration of 360 days, started in June 2024 and is expected to be completed by May 24, 2025.

According to the reporter of Lao Dong Newspaper, many items of the new headquarters have been completed.

A representative of the Bac Ha District Construction Investment Project Management Board said: "The new headquarters was built on the old headquarters, so the site clearance work is more or less favorable. Only a few households have to carry out site clearance and hand over for the project".

On March 10, Provincial Party Secretary and Chairman of Lao Cai Provincial People's Committee Trinh Xuan Truong issued a document on reviewing and temporarily suspending the implementation of works and projects in the process of arranging and organizing the apparatus. At the same time, the People's Committees of districts are assigned to urgently review, synthesize and propose handling measures for each specific case, and report to the Provincial People's Committee before March 15.

Đinh Đại
RELATED NEWS

Lao Cai merges provincial newspapers and radio and television stations

|

Lao Cai - Lao Cai Newspaper was established on the basis of merging two agencies, which are the provincial newspaper and radio and television.

Announcing the leaders of the Customs Branch of Region VII in Lao Cai

|

Lao Cai - The Customs Department has just held a conference to announce the apparatus and leaders of regional VII branches.

Revealing the investor of 86 billion VND commercial housing in Lao Cai

|

Lao Cai - The commercial housing project in the residential area of Coc Leu ward with an investment capital of VND 86.5 billion has just been approved for investment by the Provincial Economic Zone Management Board.

The 8th National Book Award honors 50 works

|

On March 3, the Vietnam Publishing Association held a press conference to inform about the 8th National Book Award.

Mr. Nguyen Thanh Binh is introduced to be elected as Chairman of Ninh Binh Provincial People's Committee

|

Ninh Binh - Mr. Nguyen Thanh Binh - Deputy Secretary of Thai Nguyen Provincial Party Committee - was transferred and appointed to hold the position of Deputy Secretary of Ninh Binh Provincial Party Committee, term 2025 - 2030.

Da Nang voters hope National Assembly deputies will pay attention to stable education policies

|

Da Nang - Voters expect National Assembly deputies of the 16th term to pay more close attention to education policies, ensuring stability and practical suitability.

President Trump criticizes Britain for delay in Iran offensive campaign

|

President Trump expressed disappointment with Prime Minister Keir Starmer when Britain hesitated to allow the use of air bases to attack Iran.

People anxiously waiting for the trillion-dong coastal road to be constructed

|

Thanh Hoa - After many years of implementation, many sections of the coastal road project have not yet been implemented, affecting people's lives.

Lao Cai merges provincial newspapers and radio and television stations

Đinh Đại |

Lao Cai - Lao Cai Newspaper was established on the basis of merging two agencies, which are the provincial newspaper and radio and television.

Announcing the leaders of the Customs Branch of Region VII in Lao Cai

Đinh Đại |

Lao Cai - The Customs Department has just held a conference to announce the apparatus and leaders of regional VII branches.

Revealing the investor of 86 billion VND commercial housing in Lao Cai

Đinh Đại |

Lao Cai - The commercial housing project in the residential area of Coc Leu ward with an investment capital of VND 86.5 billion has just been approved for investment by the Provincial Economic Zone Management Board.