People anxiously waiting for the trillion-dong coastal road to be constructed

QUÁCH DU |

Thanh Hoa - After many years of implementation, many sections of the coastal road project have not yet been implemented, affecting people's lives.

The coastal road through Thanh Hoa province has a length of 96.2 km, passing through districts, towns, and (old) cities such as: Nga Son, Hau Loc, Hoang Hoa, Sam Son, Quang Xuong and Nghi Son. The route is divided into 5 sections with different lengths.

Tuyến đường ven biển đoạn từ TP Sầm Sơn (cũ) đến huyện Quảng Xương (cũ) đã hoàn thành đưa vào sử dụng nhiều năm qua. Ảnh: Quách Du
The coastal road section from Sam Son City (old) to Quang Xuong district (old) has been completed and put into use for many years. Photo: Quach Du

To date, Thanh Hoa province has only completed 2 sections with a total length of more than 32 km, with an investment cost of about 3,500 billion VND.

In the remaining sections, the section from Hoang Thanh commune to Sam Son ward, nearly 12 km long, with a total investment of more than 1,800 billion VND, is facing many difficulties in the implementation process.

Specifically, this route section has not been allocated capital plan according to sources and capital structure, so it does not meet the conditions for approving the contractor selection plan for component projects.

Đường ven biển (đoạn qua phường Sầm Sơn, tỉnh Thanh Hóa) “án binh bất động“, trở thành bãi cỏ hoang, người dân tận dụng để trồng rau màu. Ảnh: Quách Du
The coastal road (section passing through Sam Son ward, Thanh Hoa province) is "motionless", becoming a wasteland, people take advantage of it to grow vegetables. Photo: Quach Du

On March 3, in an exchange with a reporter from Lao Dong Newspaper, many households in Sam Son ward said that the coastal road project was implemented many years ago, but then "lay idle", causing people's lives to be affected.

Mr. Do Duc Linh (resident of Yen Trach residential group, Sam Son ward) said that the process of deploying the coastal road, the section from Hoang Thanh commune to Sam Son ward has been "stuck" for many years. Meanwhile, site clearance has been completed for a long time but construction has not been seen.

Typically, the route passes through Chau Binh, Xuan Phuong, An Chinh, Yen Trach residential groups of Sam Son ward, after site clearance and relocation of households to other places, this area is abandoned, affecting the travel of many households" - Mr. Linh said.

Ông
Mr. Do Nhu Thanh (resident in Yen Trach residential group, Sam Son ward) shared about the coastal road project that has been sluggish for many years. Photo: Quach Du

Like Mr. Linh, Mr. Do Nhu Thanh (63 years old, residing in Yen Trach residential group, Sam Son ward) angrily said that after many years of project implementation and site clearance, up to now, the planned road area of tens of meters has become a wild grass field, swampy, and flooded every time it rains.

The most difficult thing is that after site clearance, some residential areas no longer have convenient roads. Households have to pile soil and make temporary paths to enter their houses, which is very inconvenient in daily life" - Mr. Thanh shared.

Dự án
Many households in Sam Son ward have to pile soil and build temporary roads due to the slow implementation of the coastal road project. Photo: Quach Du

According to many households in Sam Son ward, if the coastal road project is implemented synchronously and completed on schedule, it will bring many benefits in connecting inter-communes, inter-regions and inter-provinces, thereby promoting economic development. However, the slow implementation of some sections not only affects travel but also causes many inconveniences and great impacts on the lives of people in the project area.

Regarding the construction of the coastal road project through Thanh Hoa province, in an exchange with a reporter from Lao Dong Newspaper, a representative of the Thanh Hoa Traffic Construction Investment Project Management Board said that the coastal road of Vietnam was approved for planning by the Prime Minister in Decision No. 129/QD-TTg dated January 18, 2010 and approved for adjustment in document No. 2409/TTg-KTN dated December 31, 2015.

The road through Thanh Hoa province has a length of 96.2 km. Up to now, Thanh Hoa province has only completed 2 sections with a length of more than 32 km.

The project still has 64km in progress. In which, the Hoang Hoa - Sam Son and Quang Xuong - Nghi Son sections, with a length of 29.9km, face many difficulties in arranging capital and construction.

QUÁCH DU
RELATED NEWS

Trillion-VND coastal road through Thanh Hoa: Completed section, unfinished section

|

Thanh Hoa - After many years of implementing the coastal road project, many sections have been completed, but many sections are still "motionless".

Toll collection for coastal roads in Hung Yen province from 03.01.2026

|

From 0:00 on January 3, 2026, cars traveling on the coastal road of Hung Yen province officially pay BOT tolls in the form of electronic non-stop toll collection ETC.

Lao Dong Newspaper warns of capital increase for coastal road project before inspection conclusion

|

Quang Tri - Before the Government Inspectorate pointed out violations, Lao Dong Newspaper reported abnormalities in the proposal to adjust and increase capital in the coastal road project.

Mr. Nguyen Thanh Binh is introduced to be elected as Chairman of Ninh Binh Provincial People's Committee

|

Ninh Binh - Mr. Nguyen Thanh Binh - Deputy Secretary of Thai Nguyen Provincial Party Committee - was transferred and appointed to hold the position of Deputy Secretary of Ninh Binh Provincial Party Committee, term 2025 - 2030.

Da Nang voters hope National Assembly deputies will pay attention to stable education policies

|

Da Nang - Voters expect National Assembly deputies of the 16th term to pay more close attention to education policies, ensuring stability and practical suitability.

President Trump criticizes Britain for delay in Iran offensive campaign

|

President Trump expressed disappointment with Prime Minister Keir Starmer when Britain hesitated to allow the use of air bases to attack Iran.

Parents line up to compete for a 10th grade spot for their children, principal proposes handling plan

|

According to the Principal of Phan Boi Chau High School (Hanoi), parents queuing to register for 10th grade is a spontaneous occurrence. From this afternoon, the school stopped receiving applications directly.

Car owners and drivers talk about new regulations to check diesel engine emissions

|

According to drivers, if the vehicle is maintained periodically and in accordance with the manufacturer's recommendations, the emission inspection process will generate less risk.

Trillion-VND coastal road through Thanh Hoa: Completed section, unfinished section

QUÁCH DU |

Thanh Hoa - After many years of implementing the coastal road project, many sections have been completed, but many sections are still "motionless".

Toll collection for coastal roads in Hung Yen province from 03.01.2026

Thu Hằng |

From 0:00 on January 3, 2026, cars traveling on the coastal road of Hung Yen province officially pay BOT tolls in the form of electronic non-stop toll collection ETC.

Lao Dong Newspaper warns of capital increase for coastal road project before inspection conclusion

HƯNG THƠ |

Quang Tri - Before the Government Inspectorate pointed out violations, Lao Dong Newspaper reported abnormalities in the proposal to adjust and increase capital in the coastal road project.