Revealing more than 14km of elevated roads through the urban area in Ho Chi Minh City

Tâm Tú |

Ho Chi Minh City - The elevated route belongs to the Ring 3 of Ho Chi Minh City through the urban area in Thu Duc City gradually formed, expected to be completed by the end of this year.

The 3rd Ring Project through Ho Chi Minh City has a length of more than 47km, of which more than 14km through Thu Duc City is designed as an elevated road, 4 lanes in phase 1.

This route starts from Ho Chi Minh City - Long Thanh - Dau Giay highway passing Thu Duc City and ends at Tan Van intersection.

Tuyen duong tren cao thuoc du an Vanh dai 3 chay xuyen qua khu do thi Vinhomes Grand Park, TP Thu Duc nhin tu tren cao. Anh: Anh Tu
The elevated route belongs to the Ring 3 project through Vinhomes Grand Park, Thu Duc City (Ho Chi Minh City) from above. Photo: Anh Tu

Records of Labor on 10.2, at the XL3 package (longer than 3km) - one of 5 bidding packages through Thu Duc City, many engineers and workers are urgently constructing to accelerate the progress.

After more than a year of construction, the section of Ring Road 3 overhead through Vinhomes Grand Park urban area, Thu Duc City has installed the viaduct, is getting up a number of sections to complete. The XL3 package has reached more than 40% of the work volume, while the remaining 4 packages reached 15-20%.

Tuyen duong sau khi hoan thanh se co 4 lan xe, rong 21,5m o doan co lan dung khan cap va 19,5 o lan duong thong thuong. Anh: Anh Tu
The route after completion will have 4 lanes, 21.5m wide in an emergency stop lane and 19.5m in the regular lane. Photo: Anh Tu

Representative of the construction unit of XL3 package said that after guarding the beams, the unit will pour concrete, plastic carpets as the bridge, install the lighting system, railing, expected to be completed by the end of this year .

Cac cong nhan, ky su dang tap trung gac thanh dam. Theo ky su o cong truong de gac mot thanh dam tren xa mu phai mat 2-5 gio. Anh: Anh Tu
The workers and engineers are focusing on the bar. According to engineers at the construction site, it takes 2-5 hours on the hat bar. Photo: Anh Tu
O moi thanh dam co mot khoang ho de do be tong gia cuong truoc khi tham nhua duong, hoan thien mat duong. Anh: Anh Tu
In each beam, there is a gap to pour reinforced concrete before asphalt carpet, complete the road surface. Photo: Anh Tu
Mat cau can xuyen qua khu do thi Vinhomes Grand Park, TP Thu Duc sau khi da lap dam xong con chua nhieu cot thep hinh tron de do be tong, tham nhua lam lan duong hoan chinh. Anh: Anh Tu
The viaduct throughout the Vinhomes Grand Park urban area, Thu Duc City, after installing the beam, left a lot of reinforcement to pour concrete and plastic mats as a complete lane. Photo: Anh Tu
Doan duong tren cao qua TP Thu Duc se hoan thanh thong xe ky thuat vao ngay 31.12.2025. Anh: Anh Tu
The elevated road through Thu Duc City will complete the technical traffic on December 31, 2025. Photo: Anh Tu

Belt 3 of Ho Chi Minh City has a total length of 76km, passing through Ho Chi Minh City, Binh Duong, Dong Nai and Long An, with a total investment of more than 75,378 billion dong.

Particularly, the section through Ho Chi Minh City has a total investment of 41,387 billion dong, of which the cost of site clearance accounts for 18,975 billion dong.

In addition to the section through Thu Duc City, the completion milestones of other sections in the project have also been determined.

On April 30, 2025, the section from Nhon Trach Bridge to Ho Chi Minh City - Long Thanh - Dau Giay highway will be completed and put into operation.

In December 2025, the highway to Long An, from the doctor's bridge to the Ben Luc intersection will open.

On April 30, 2026, the sections of Ring 3 through Binh Chanh, Hoc Mon and Cu Chi (Ho Chi Minh City) will be connected with the section through Dong Nai and Binh Duong.

In December 2026, the entire Ho Chi Minh City Ring Highway 3 will officially be completed and clear.

Tâm Tú
TIN LIÊN QUAN

The longest canal improvement project in Ho Chi Minh City has 25 ground

|

The project to renovate Tham Luong - Ben Cat - Rach water canal, the longest canal in Ho Chi Minh City is facing difficulties when 25 ground has not been handed over or re -encroached.

Tang Long Bridge in Ho Chi Minh City is about to open after many years of "covering the mat"

|

Ho Chi Minh City - Immediately after the Lunar New Year, Tang Long Bridge Project has conducted construction again, speeding up the progress to clear the car at the end of February.

Ho Chi Minh City accelerated rescuing the tide project of VND 10,000 billion

|

Ho Chi Minh City People's Committee Chairman Phan Van Mai has just directed a series of solutions to remove obstacles of the Super Project to prevent the tidal nearly VND 10,000 billion.

311 teachers unexpectedly have their insurance money collected VND4.6 billion

|

Nghe An - 311 teachers were charged VND4.6 billion in insurance, including more than VND2.6 billion in fines for late payment.

People's Artist Cong Ly ceases to hold the position of Deputy Director of the Hanoi Drama Theater

|

People's Artist Cong Ly will leave the position of Deputy Director of the Hanoi Drama Theater after March 2025.

Proposal of the Vietnam Fatherland Front of Ho Chi Minh City to supervise personnel planning

|

HCMC - The delegate of the Vietnam Fatherland Front of HCMC proposed to supervise the planning of cadres, enhancing proactiveness and transparency.

Prime Minister: Institutions must promote and liberate all resources

|

The Prime Minister noted that it is necessary to pay attention to the major characteristic of the rapidly changing world situation, with many new and unpredictable problems appearing.

Binh Dinh sets growth target of 8% or more

|

Binh Dinh - On March 13, National Assembly Chairman Tran Thanh Man - Head of the Investigation Team No. 1910 of the Politburo worked with the Standing Committee of the Binh Dinh Provincial Party Committee.

The longest canal improvement project in Ho Chi Minh City has 25 ground

MINH QUÂN |

The project to renovate Tham Luong - Ben Cat - Rach water canal, the longest canal in Ho Chi Minh City is facing difficulties when 25 ground has not been handed over or re -encroached.

Tang Long Bridge in Ho Chi Minh City is about to open after many years of "covering the mat"

Tâm Tú |

Ho Chi Minh City - Immediately after the Lunar New Year, Tang Long Bridge Project has conducted construction again, speeding up the progress to clear the car at the end of February.

Ho Chi Minh City accelerated rescuing the tide project of VND 10,000 billion

MINH QUÂN |

Ho Chi Minh City People's Committee Chairman Phan Van Mai has just directed a series of solutions to remove obstacles of the Super Project to prevent the tidal nearly VND 10,000 billion.