Reason why the last 14 cases of the Ho Chi Minh City - Moc Bai expressway have not accepted 84.32 billion VND in compensation

HUỲNH DU |

Tay Ninh - Nearly 99% of the site clearance of the Ho Chi Minh City - Moc Bai expressway through Tay Ninh has been paid, the remaining 14 cases are the final "combination pieces" that need to be removed.

On August 20, the Tay Ninh Provincial Land Fund Development Center said that by the end of July 2026, the compensation, support, and resettlement work of component project 4 - Ho Chi Minh City - Moc Bai expressway, section passing through Tay Ninh province, had achieved significant results. However, there are still 14 cases that have not received compensation, with a total amount of 84.32 billion VND and an area of 1.34ha.

According to the Land Fund Development Center, the entire project has 2,274 affected cases, with a total recovered land area of 252.12ha and compensation amount of 3,154.96 billion VND. To date, 2,260 cases have been paid, reaching 99.38%; the amount spent is 3,070.64 billion VND, reaching 97.33%, while the area paid reached 250.76ha, equivalent to 99.47%.

Bản đồ hướng tuyến dự án đầu tư xây dựng đường cao tốc TP.Hồ Chí Minh - Mộc Bài. Ảnh Trung tâm quỹ đất Tây Ninh
Route map of the Ho Chi Minh City - Moc Bai expressway construction investment project. Photo: Tay Ninh Land Fund Center

In An Tinh and Go Dau wards, payment work has been completed for the entire number of cases, respectively 535 and 19 cases. In Phuoc Thanh commune, 556/558 cases have been paid, reaching 98.08% of the funding. Ben Cau commune has paid 128/133 cases, equivalent to 97.23% of the funding. Gia Loc ward alone has 7 cases that have not received money, with an area of 0.63ha and an amount of 48.95 billion VND.

Cases that have not received money are concentrated in problems related to area, compensation plan, land unit prices and disputes. In which, in Gia Loc, there are 3 households that do not agree with compensation area, 3 households that have not agreed on compensation and support plans and 1 household is in dispute. In Phuoc Thanh, there are cases that do not agree with land compensation unit prices and cases that are in dispute. Ben Cau has 5 cases of complaints about compensation prices for houses, architectural structures and site clearance boundaries of Xuyen A road.

Tây Ninh giải phóng mặt bằng cao tốc TPHCM - Mộc Bài đặt mục tiêu hoàn tất 100% trong tháng 9. Ảnh: Huỳnh Du
Tay Ninh clears the site for the HCMC - Moc Bai expressway, setting a target of completing 100% in September. Photo: Huynh Du

In parallel with compensation, resettlement work is also being implemented. There are 147 cases registered to receive resettlement land, while 124 cases have a need to receive compensation money to take care of their own accommodation. The resettlement areas are expected to be arranged in the 10.7ha area in Hung Thuan commune and the resettlement area at Dia Xu canal in Ben Cau commune.

The Land Fund Development Center aims to complete payment and hand over 100% of the site in September. To achieve this goal, the units continue to answer petitions, mobilize people to hand over the site; in case of disagreement, they will request to implement the steps according to regulations.

The Ho Chi Minh City - Moc Bai expressway project was approved by the Prime Minister in August 2024, with a total length of 51 km, of which the section through Ho Chi Minh City is 24.7 km long and the section through Tay Ninh province is 26.3 km long, with a scale of 4 expressway lanes.

The starting point connects to Ring Road 3 HCMC in Phu Hoa Dong commune, HCMC and the ending point intersects with National Highway 22 (Km 53+850) in Ben Cau commune, Tay Ninh province.

HUỲNH DU
RELATED NEWS

Ho Chi Minh City increases compensation of 1,330 billion VND for Ho Chi Minh City - Moc Bai expressway

|

Ho Chi Minh City adjusts to increase 1,330 billion VND for compensation, support, and resettlement for the Ho Chi Minh City - Moc Bai expressway project, raising the total budget to more than 6,382 billion VND.

Ho Chi Minh City - Moc Bai expressway project increases capital by more than 3,300 billion VND

|

Ho Chi Minh City - The Ho Chi Minh City - Moc Bai expressway project has been adjusted to increase the total investment to 22,975 billion VND, 3,358 billion VND higher than previously approved.

Ho Chi Minh City today: BOT project of Ho Chi Minh City - Moc Bai expressway to start soon

|

Ho Chi Minh City announces the 14th National Treasure, honoring thousand-year-old ancient pottery; Groundbreaking ceremony for the Ho Chi Minh City - Moc Bai expressway BOT project in April 2026...

Tornado in Bao Loc, a series of houses had their roofs blown off, and green trees fell

|

Lam Dong - Heavy rain accompanied by tornadoes swept through many wards in Bao Loc, causing dozens of houses to have their roofs blown off, green trees uprooted, and many roads obstructed.

Ho Chi Minh City achieves 98% of textbook demand, publishing houses continue to print additionally

|

Vietnam Education Publishing House said that it has supplied 98% of textbooks according to registered needs in Ho Chi Minh City and is continuing to print more to meet arising needs.

Tickets for the ASEAN Cup 2026 final for Vietnam national team are sold out, many fans could not buy tickets

|

VFF announced that tickets for the second leg of the ASEAN Cup 2026 final match between Vietnam and Thailand at My Dinh Stadium have been sold out online in just a few hours.

Proposal to reduce 30% tax for businesses with revenue under 10 billion VND

|

The Government proposes a 30% reduction in personal income tax and corporate income tax for business households and businesses with revenue below 10 billion VND.

Ho Chi Minh City increases compensation of 1,330 billion VND for Ho Chi Minh City - Moc Bai expressway

MINH QUÂN |

Ho Chi Minh City adjusts to increase 1,330 billion VND for compensation, support, and resettlement for the Ho Chi Minh City - Moc Bai expressway project, raising the total budget to more than 6,382 billion VND.

Ho Chi Minh City - Moc Bai expressway project increases capital by more than 3,300 billion VND

MINH QUÂN |

Ho Chi Minh City - The Ho Chi Minh City - Moc Bai expressway project has been adjusted to increase the total investment to 22,975 billion VND, 3,358 billion VND higher than previously approved.

Ho Chi Minh City today: BOT project of Ho Chi Minh City - Moc Bai expressway to start soon

Nguyên Chân |

Ho Chi Minh City announces the 14th National Treasure, honoring thousand-year-old ancient pottery; Groundbreaking ceremony for the Ho Chi Minh City - Moc Bai expressway BOT project in April 2026...