Slow handover of land hinders progress of National Highway 6 expansion project

Hữu Chánh |

After more than 2 years of construction, Chuong My district has handed over a part of the cleared land for the construction of National Highway 6 expansion. Meanwhile, the section through Ha Dong district, Hanoi City has not yet been implemented due to lack of site clearance.

Only 51% of the land area has been reclaimed

In December 2022, the Hanoi People's Committee started the renovation of 21.7km of National Highway 6 through Ha Dong and Chuong My districts. The starting point of the project is located at km14 in Ba La, Ha Dong district; the end point is km38, Xuan Mai town, Chuong My district.

The project has a total investment of 8,100 billion VND from the city budget. Of which, about VND 5,100 billion is for site clearance (GPMB), VND 2,900 billion is for construction and equipment procurement costs. According to the design, the expanded rear section has a cross-section of 50-60m, with a design speed of 80km/h.

The route has a box culvert, seven bridges and four main intersections, including intersections of different levels (where two or more roads intersect at different elevations) with National Highway 21A, the North-South axis road and Ring Road 4. The project to expand National Highway 6 through Chuong My district is 15.87km long. The area of recovered is about 85.36ha, 3,379 plots of land are affected, passing through 7 communes and 2 towns.

On March 11, 2024, the Hanoi People's Committee approved component project 1.2: Compensation, support and resettlement for site clearance in Chuong My district under the project to expand National Highway 6, Ba La - Xuan Mai section.

By December 2024, the People's Committee of Chuong My district had handed over the site to the Hanoi Traffic Construction Investment Project Management Board (investor) and the contractor to construct the project with an area of about 57.58 hectares (public land and agricultural land).

The project to expand National Highway 6 through Ha Dong district, nearly 6km long, has not yet been implemented due to the site not being handed over.

According to the People's Committee of Ha Dong district, the total land area to be recovered to implement the project is about 26.46ha (public land 6.96ha; residential land, commercial services 8.36ha; agency land 0.16ha; rice and aquaculture land 10.95ha; cemetery land 0.026ha) related to 1,266 households and individuals.

The number of households expected to be resettled is about 317 households. The City People's Committee has approved the principle of a resettlement housing fund for the project in 2023, including 50 apartments, of which 19 apartments are at H's house in Trung Van ward, Nam Tu Liem district and 31 apartments are at A2 Kim Giang housing fund, Thanh Xuan district.

On December 16, 2024, the People's Committee of Ha Dong District worked with the City Traffic Construction Investment Project Management Board to review documents related to the survey consultancy package. After reviewing, the content of contract No. 139/2022/HDTV-BQLCTGT dated November 2, 2022 has only completed part of the work and there is still time to implement the contract.

May moc lam viec tren cong truong du an mo rong Quoc lo 6.  Anh: Huu Chanh
Machinery working at the construction site of the National Highway 6 expansion project. Photo: Huu Chanh

Focus on removing obstacles

The Chuong My District Government said that this project in the area currently has problems with land origin confirmation, the application of the site clearance policy mechanism is transitioning from the 2013 Land Law to the 2024 Land Law, from Decision No. 10/2017/QD-UBND dated March 29, 2017 of the City People's Committee to Decision No. 56/2024/QD-UBND dated September 6, 2024 of the City People's Committee regulating a number of contents on compensation, support, and resettlement when the State reclaims land in Hanoi.

In addition, within the scope of the project's site clearance, there are floating infrastructure works that must be moved, national defense land is reclaimed, and the purpose of use is changed to serve the purpose of socio-economic development, grave relocation, etc.

Currently, the People's Committee of Chuong My district has reported to the City People's Committee, departments and branches for instructions on removing obstacles and trying to hand over the site clearance to the construction unit for the entire project in the first quarter of 2026.

According to Vice Chairman of Ha Dong District People's Committee Bui Xuan Ha, to speed up the progress and ensure the exploitation of the site clearance documents that have been carried out to avoid duplication of funding, Ha Dong District People's Committee has proposed that the City People's Committee consider and approve the policy to allow the district to receive the results of the work performed and sign the contract appendix on the basis of contract No. 139, to complete the remaining work to speed up the project implementation progress.

Hữu Chánh
TIN LIÊN QUAN

Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

|

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.

Accelerating site clearance for the VND86,000 billion project through Bac Ninh

|

Bac Ninh province aims to complete site clearance for the Ring Road 4 - Hanoi Capital Region project in the first quarter of 2025.

4,200 billion VND hospital project in Quang Ninh is stuck in land acquisition

|

Quang Ninh General Hospital, Facility 2, has a total investment of about 4,200 billion VND. After 6 months of construction, the project has not been able to be implemented due to land clearance problems.

Strong earthquake in Tonga just a few days after Myanmar earthquake

|

A 7.1-magnitude earthquake near Tonga prompted an initial Tsunami warning but was later lifted.

The Cong Viettel beat Hoang Anh Gia Lai to advance to the semi-finals of the National Cup

|

On the evening of March 30, The Cong Viettel defeated Hoang Anh Gia Lai with a score of 2-0 to win a ticket to the semi-finals of the 2024-2025 National Cup.

Updated gold price at the end of session 30.3: Profit despite surfing

|

Updated gold price at the end of the session on March 30: The difference between buying and selling is at a high level, investors still make a profit even if investing in the short term.

The army and police set out to support overcoming the consequences of the earthquake

|

The delegation of officers and soldiers of the Ministry of National Defense and the Ministry of Public Security have set out to support Myanmar in overcoming the consequences of the earthquake.

Waiting for the end of living with wastewater in industrial parks

|

Quang Tri - The lives of people living next to industrial parks have been disrupted by wastewater. Meanwhile, the wastewater treatment plant has not yet come into operation

Land clearance problems slow down the progress of Van Thanh bridge in Phan Thiet

Duy Tuấn |

Binh Thuan - After more than 2 years of construction, the progress of the Van Thanh bridge project has only reached about 51% of the contract volume due to land clearance problems.

Accelerating site clearance for the VND86,000 billion project through Bac Ninh

Vân Trường |

Bac Ninh province aims to complete site clearance for the Ring Road 4 - Hanoi Capital Region project in the first quarter of 2025.

4,200 billion VND hospital project in Quang Ninh is stuck in land acquisition

Đoàn Hưng |

Quang Ninh General Hospital, Facility 2, has a total investment of about 4,200 billion VND. After 6 months of construction, the project has not been able to be implemented due to land clearance problems.