Sticky rice" land holds back a series of traffic projects in the highlands of Lao Cai

Bảo Nguyên – Duy Dũng |

Lao Cai - A series of key transport projects in the highlands are falling into unfinished construction, lasting for many years due to site clearance problems.

In the last days of March, at many traffic construction sites in the highlands of Lao Cai, it is not difficult to encounter a messy scene: the road surface is dug unfinished, materials are scattered, and machinery is waiting. Many sections of the route are interrupted, some are completed, some are left empty, creating "smooth roads" that have lasted for many years.

The Quang Kim - Coc San connecting road project, more than 7km long, with a total investment of 50 billion VND, once expected to open an important traffic axis for rural areas, has not yet been completed after more than 3 years of implementation.

Nhiều vị trí thuộc Dự án đường kết nối Quang Kim - Cốc San vướng mặt bằng nên không thể thi công. Ảnh: Bảo Nguyên
Many locations belonging to the Quang Kim - Coc San connecting road project are entangled in site clearance, so construction cannot be carried out. Photo: Bao Nguyen

In Dong Quang village, just a light rain, the road under construction turns muddy and slippery. The roadbed sections that have been completed are "broken" in locations without clearance, making people's travel even more difficult.

According to Mr. Nguyen Sy Trong - Deputy Director of Minh Duc General Construction Co., Ltd. (the construction unit), the biggest reason for the project being prolonged is that the site handover is not continuous.

There are sections that have been cleared, interspersed with locations that have not been compensated for, and even hindered by unremoved power poles. The entire route is therefore divided, making it impossible to organize synchronous construction," Mr. Trong said.

Việc điều chuyển nắn tuyến cũng khiến dự án chậm tiến độ chung. Ảnh: Bảo Nguyên
The adjustment of the route also slows down the overall project progress. Photo: Bao Nguyen
Máy móc tập kết chờ mặt bằng để thi công. Ảnh: Bảo Nguyên
Machinery gathers waiting for site clearance for construction. Photo: Bao Nguyen

Also according to the contractor representative, the "tough" construction not only prolongs the progress but also affects the quality of the project, especially at the junctions between the part that has and does not have land. Currently, the project still has about 3km to "wait for land" to continue implementation.

A similar situation also occurred on the road to the center of Phin Ngan commune (now Bat Xat commune), with a total investment of 34 billion VND. After nearly 4 years of construction, the project has only completed about 3.5/6.8km.

Mr. Nguyen Anh Tuan - technical officer of Dong A Import-Export Production Joint Stock Company - said that in addition to site clearance issues, the project also lacks filling soil, making many sections unable to be implemented.

Nhiều vị trí thiếu đất đắp khiến dự án đường vào trung tâm xã Phìn Ngan cũ thi công cầm chừng. Ảnh: Bảo Nguyên
Many locations lack embankment soil, causing the road project to the center of the old Phin Ngan commune to be constructed halfway. Photo: Bao Nguyen

Machinery and manpower are ready but there is no land to build the foundation. We need about 20,000 cubic meters of soil but still have to wait for the investor to arrange resources. Some locations still have to adjust the design, so it is even longer," Mr. Tuan said.

On March 31, in an exchange with Lao Dong Newspaper, Mr. Vu Van Sinh - Director of the Bat Xat Area Project Management and Construction Investment Board (the investor of the 2 projects mentioned above) - said that the main reason for the slow progress of projects is that people have not agreed in site clearance work along with the high increase in material prices.

According to Mr. Sinh, prolonged construction is slowing down the project progress, wasting money for businesses, from labor maintenance costs to machinery and equipment.

In addition to promoting site clearance, the Board has worked and exchanged many times, requesting contractors to develop specific plans to accelerate progress.

Người dân mong muốn dự án sớm hoàn thành để thuận tiện giao thương, đi lại. Ảnh: Bảo Nguyên
People hope the project will be completed soon for convenient trade and travel. Photo: Bao Nguyen

Leaders of some highland communes also admitted - when the site has not been handed over synchronously, contractors can hardly deploy construction on a large scale. Having to "avoid" uncleared points makes the construction teams divided and unable to promote efficiency.

In the coming time, local authorities will focus on implementing many solutions, especially the work of inventorying and paying publicly and transparently to create high consensus among the people.

Only then can transportation projects be deployed smoothly, promote investment efficiency and truly become a driving force to promote socio-economic development.

Bảo Nguyên – Duy Dũng
RELATED NEWS

Removing the bottleneck of land, the key to relocating 20,000 houses along canals and ditches

|

The large project to relocate 20,000 houses along canals and ditches by 2030 of Ho Chi Minh City is facing a major challenge, which is solving the "bottleneck" of compensation for site clearance.

Lao Cai relocates a series of IPs, creating a clean ground to welcome investors

|

Lao Cai - From completing infrastructure, expanding land funds to digital transformation, the whole province is implementing many synchronous solutions to attract investment.

Removing site obstacles, promoting the progress of a 46 billion VND road in the highlands of Lao Cai

|

Lao Cai - The project to upgrade the road from Bao Nhai commune to Coc Ly is being focused on removing site obstacles to speed up construction progress.

Hanoi announces decision on personnel work

|

On the morning of March 31, Member of the Standing Committee of the City Party Committee, Standing Vice Chairman of Hanoi City People's Committee Duong Duc Tuan chaired a conference to announce decisions on personnel work.

Mr. Le Minh Ngan re-elected Chairman of Lai Chau Provincial People's Council

|

Lai Chau - Provincial Party Secretary Le Minh Ngan re-elected Chairman of the 16th Provincial People's Council, term 2026-2031.

Shops increase prices, sellers find it difficult to retain customers, buyers consider spending

|

Hanoi - Under pressure from input costs, many restaurants adjusted prices upwards, partly affecting the spending habits of diners.

Prime Minister appoints Director of Hanoi National University

|

The Prime Minister transferred and appointed Mr. Bui The Duy - Vice President of the Vietnam Academy of Science and Technology to hold the position of Director of Vietnam National University, Hanoi.

Sticky rice" land holds back a series of traffic projects in the highlands of Lao Cai

|

Lao Cai - A series of key transport projects in the highlands are falling into unfinished construction, lasting for many years due to site clearance problems.

Removing the bottleneck of land, the key to relocating 20,000 houses along canals and ditches

Lê Thanh Phong |

The large project to relocate 20,000 houses along canals and ditches by 2030 of Ho Chi Minh City is facing a major challenge, which is solving the "bottleneck" of compensation for site clearance.

Lao Cai relocates a series of IPs, creating a clean ground to welcome investors

Bảo Nguyên |

Lao Cai - From completing infrastructure, expanding land funds to digital transformation, the whole province is implementing many synchronous solutions to attract investment.

Removing site obstacles, promoting the progress of a 46 billion VND road in the highlands of Lao Cai

Đinh Đại |

Lao Cai - The project to upgrade the road from Bao Nhai commune to Coc Ly is being focused on removing site obstacles to speed up construction progress.