National Highway 13 expansion in Ho Chi Minh City is being accelerated on the days leading up to Tet

ĐÌNH TRỌNG |

Ho Chi Minh City - The National Highway 13 expansion project, the section passing through old Binh Duong, is being accelerated in the days leading up to the 2026 Lunar New Year.

On January 29, the construction site of the National Highway 13 expansion project, the section passing through old Binh Duong, became more bustling and bustling in the section from Vinh Binh Bridge to Ong Bo Bridge, about 5.5 km long.

According to records, this is the slowest site clearance section of the project. To date, the relocation of technical infrastructure has been basically completed. All old power poles along National Highway 13 have been moved deep inside. Houses and business production facilities of businesses are also about to complete 100% of the removal. Only a few houses are being removed for site handover.

Regarding construction, many machines, vehicles and manpower are concentrated in the section from Vinh Binh Bridge to Ong Bo Bridge. The construction unit is completing the installation of drainage culverts, carrying out road surface compaction, and at the same time spreading rocks and preparing asphalt pavement.

Quoc lo 13 doan qua phuong Binh Hoa, TPHCM. Anh: Dinh Trong
National Highway 13 section through Binh Hoa ward, Ho Chi Minh City. Photo: Dinh Trong

It is expected that this 5.5 km section will complete the construction and expansion at the beginning of the second quarter of 2026. This is the gateway to the center of Ho Chi Minh City, so there is a very large traffic volume. The completion of this section will contribute to reducing congestion at the gateway to Ho Chi Minh City.

Meanwhile, the 9.5 km section from Ong Bo bridge intersection to Le Hong Phong intersection is entering the completion phase. This section is near completion of asphalt paving to widen the surface of National Highway 13 from 6 to 8 lanes. Construction units are urgently constructing sidewalks, installing lighting and painting road markings. According to records, currently, vehicles can move in some sections, and the congestion situation has cooled down in sections that have been expanded to 8 lanes.

May moc va nhan luc dang duoc tap trung de thi cong. Anh: Dinh Trong
Machinery and manpower are being concentrated for construction. Photo: Dinh Trong
Cac doan da lu len nen duong dang duoc trai da. Anh: Dinh Trong
The sections that have been compacted with roadbed are being paved with stone. Photo: Dinh Trong
Tien do thi cong dang duoc day nhanh de giam thieu un u giao thong o khu vuc cua ngo vao trung tam TPHCM. Anh: Dinh Trong
The construction progress is being accelerated to reduce traffic congestion in the gateway area to the center of Ho Chi Minh City. Photo: Dinh Trong
Du kien trong quy 2.2025, doan 5km se hoan thanh viec mo rong tu 6 len 8 lan xe. Anh: Dinh Trong
It is expected that in the second quarter of 2025, the 5.5km section will complete the expansion from 6 to 8 lanes. Photo: Dinh Trong
Doan 8km da hoan thanh viec do nhua mo rong tu 6 len 8 lan xe. Anh: Dinh Trong
The 9.5km section has completed asphalt filling to expand from 6 to 8 lanes. Photo: Dinh Trong

The project to upgrade and expand National Highway 13 from 6 to 8 lanes, a nearly 15km long section through Binh Duong (formerly) was started in early 2022. The initial investment capital was 1,400 billion VND, currently, the total investment of the approved project to date is 6,255 billion VND. The project is being expanded from Ho Chi Minh City to Thu Dau Mot.

ĐÌNH TRỌNG
RELATED NEWS

Quang Tri recovers many golden land projects due to slow progress

|

Many projects using golden land in Quang Tri are revoked due to delays, violations of financial obligations, allowing land to be abandoned for a long time, causing waste of resources.

HCMC spends more than VND12,400 billion to clear 1,091 households, expand National Highway 13 to 10 lanes

|

Ho Chi Minh City spends more than VND12,400 billion to compensate, support, and resettle about 1,091 households in 2025, serving the National Highway 13 expansion project.

HCMC is about to expand National Highway 13 to 60m, build a 4-lane elevated road connecting Binh Duong

|

Ho Chi Minh City approved a plan to select a contractor to prepare to expand National Highway 13 to 60m, build a 4-lane elevated road, and help unblock the gateway connecting to Binh Duong province.

Lao Dong Newspaper delegation offers incense to commemorate leader Nguyen Duc Canh

|

Hung Yen - On the morning of January 29, the working delegation of Lao Dong Newspaper offered incense to commemorate leader Nguyen Duc Canh at the comrade memorial area in Thai Thuy commune, Hung Yen.

The case of a worker being electrocuted causing severe burns, functional agencies are involved to clarify

|

Thanh Hoa - After the incident of a worker being electrocuted, causing severe burns to both hands, functional agencies urgently intervened to clarify.

Russia targets 2 major attack directions, Ukraine's situation before the 2026 turning point

|

The situation of the Ukraine conflict is gradually revealing new directions of Russian aggression in 2026.

Vieng Phu Market in 2026 ready for the New Year's session

|

Ninh Binh - Localities have developed plans, ready for the meeting on the first day of the new year of Vieng Phu market in 2026.

Tet comes, ornamental kumquat prices increase sharply due to transportation costs

|

Dien Bien - With only more than 2 weeks left until Tet Nguyen Dan, the price of ornamental kumquats has increased sharply because transportation costs have also increased sharply.

Quang Tri recovers many golden land projects due to slow progress

CÔNG SÁNG |

Many projects using golden land in Quang Tri are revoked due to delays, violations of financial obligations, allowing land to be abandoned for a long time, causing waste of resources.

HCMC spends more than VND12,400 billion to clear 1,091 households, expand National Highway 13 to 10 lanes

MINH QUÂN |

Ho Chi Minh City spends more than VND12,400 billion to compensate, support, and resettle about 1,091 households in 2025, serving the National Highway 13 expansion project.

HCMC is about to expand National Highway 13 to 60m, build a 4-lane elevated road connecting Binh Duong

MINH QUÂN |

Ho Chi Minh City approved a plan to select a contractor to prepare to expand National Highway 13 to 60m, build a 4-lane elevated road, and help unblock the gateway connecting to Binh Duong province.