Deputy Prime Minister directs inspection and review of Long Thanh airport construction progress

PHẠM ĐÔNG |

The Deputy Prime Minister directed ministries, sectors, localities and relevant functional agencies to accelerate the implementation of the Long Thanh airport construction investment project.

The Government Office has just issued Document No. 912/VPCP-CN conveying the direction of Deputy Prime Minister Tran Hong Ha on accelerating the progress of the Long Thanh International Airport project (Long Thanh airport).

The Deputy Prime Minister requested the Ministries of Construction, Finance, Agriculture and Environment, Dong Nai Provincial People's Committee and relevant agencies to urgently implement the tasks as proposed by the Ministry of Construction and directed by the Prime Minister based on their assigned functions and tasks.

The Ministry of Construction continues to regularly inspect and direct investors and related managing agencies in project implementation to ensure the completion progress according to the plan; promptly report to the Prime Minister the implementation results, difficulties, obstacles and solutions to remove them.

Dong Nai Provincial People's Committee urgently completes the appraisal of the basic design of the fuel pipeline, works under component project 4 to soon deploy construction to ensure completion and synchronous exploitation in June 2026; if difficulties and obstacles arise, promptly report to the Ministry of Construction for support, guidance, and resolution.

Vietnam Airports Corporation must regularly organize inspections and reviews of construction progress, adjust and update progress weekly for each item and package under component project 3; promptly organize handling of difficulties and obstacles affecting construction progress.

Directing contractors to increase manpower and equipment, proactively gather sources of materials, materials, financial resources..., organize construction in 3 shifts, 4 teams, construction all day, holidays to complete according to the committed progress, especially packages with large remaining volume, with the risk of delays such as package No. 4.8 (Inland port traffic and technical infrastructure) and 5.10 (Passenger terminal).

Urgently organize the preparation of the feasibility study report for phase 2 and procedures for adjusting the function of 4 warehouses to deploy the next steps to ensure progress according to requirements.

Vietnam Airlines Corporation directs the investors of airline meal service projects, ground commercial technology, hangar No. 1 (aircraft hold) to accelerate the implementation progress to ensure completion and synchronous operation in June 2026.

Urgently organize research and deployment of investment in construction of hangar No. 2, cargo station No. 2, three express delivery cargo and 4 warehouses (from No. 5 to No. 8) to meet the progress according to the contract.

Ministries, branches, localities and agencies and units mobilize forces to implement specific tasks to accelerate the implementation progress and organize effective exploitation of the project. Research and build Long Thanh airport into a regional air transit center, along with a modern and synchronous air and non-air service ecosystem, towards forming the "Long Thanh Airport City".

According to Vietnam Airports Corporation, currently, joint venture contractors are mobilizing nearly 15,000 experts, engineers, workers and more than 3,000 equipment and machinery, deploying hundreds of construction teams on the construction site.

The project to build Long Thanh Airport Police Station has a total investment of more than 43 billion VND, started on December 25, 2024 with a construction time of 360 days. To date, the construction and equipment procurement package has been completed.

PHẠM ĐÔNG
RELATED NEWS

Deputy Prime Minister assigns deadline for completing the Aviation Security Committee

|

Deputy Prime Minister Tran Hong Ha requested the urgent completion of the consolidation of the Aviation Security Committee and the implementation of key tasks in the first quarter of 2026.

Long Thanh airport commercial operation in early 2026

|

The Long Thanh airport project will be put into technical flight operation on December 19, 2025 and commercial operation in early 2026.

The Government proposes to approve the feasibility study of phase 2 of Long Thanh airport

|

The Government proposed to organize the approval of the feasibility study report to invest in phase 2 of Long Thanh airport earlier than expected.

Gold confiscation without invoices" is misunderstood, people who spread false information may be fined

|

The confiscation is only set for gold bars that are exhibits of illegal trading and business. People who intentionally distort and spread false information may be penalized.

Son La requests dismantling of 6-year land lease expired registration center

|

Son La - Local authorities have just issued a document requesting the dismantling of the registration center that has expired land lease for nearly 6 years, as reflected by Lao Dong Newspaper.

Leaders of Malaysian Football Federation simultaneously resign

|

Members of the Executive Committee of the Malaysian Football Federation simultaneously resigned after the incident related to naturalized players.

Provinces and cities are forecast to have rain and severe cold due to a new cold air wave

|

It is forecasted that provinces and cities in the Northern region will turn cold, with mountainous areas experiencing severe cold from February 1 due to the impact of cold air.

Ministry of National Defense informs about military plane crash in Dak Lak

|

The Ministry of National Defense has officially announced the incident of a military plane crash in Dak Lak, which occurred on the morning of January 28.

Deputy Prime Minister assigns deadline for completing the Aviation Security Committee

PHẠM ĐÔNG |

Deputy Prime Minister Tran Hong Ha requested the urgent completion of the consolidation of the Aviation Security Committee and the implementation of key tasks in the first quarter of 2026.

Long Thanh airport commercial operation in early 2026

Phạm Đông |

The Long Thanh airport project will be put into technical flight operation on December 19, 2025 and commercial operation in early 2026.

The Government proposes to approve the feasibility study of phase 2 of Long Thanh airport

PHẠM ĐÔNG |

The Government proposed to organize the approval of the feasibility study report to invest in phase 2 of Long Thanh airport earlier than expected.