Nearly 68% of the 1,500 billion VND road in Dong Nai has just been handed over

HÀ ANH CHIẾN |

Dong Nai - The Bien Hoa City Central Axis Road Construction Project has a total investment of more than VND1,500 billion, and only 68% of the site has been handed over since 2023.

On March 11, the Dong Nai Province Traffic Construction Investment Project Management Board said that the Bien Hoa City Central Axis Road Construction Project, from Vo Thi Sau Street to Dang Van Tron Street (Thong Nhat Bridge and the road connecting the two ends of the bridge) has only been handed over the construction site to 154 households with an area of over 22 hectares, reaching nearly 68% of the area.

However, the site is not continuous, leading to the lack of synchronous construction of construction items (currently, there are still 92 households that have received compensation, there are no resettlement plots so the site has not been handed over).

The Management Board of the Dong Nai Province Traffic Construction Investment Project recommends that the People's Committee of Bien Hoa City promptly complete compensation and site clearance and hand over construction sites for priority locations that meet construction conditions such as Thong Nhat Bridge, Vam Ong An Bridge and traffic routes of branches 1, branches 2, Thong Nhat Bridge intersection, Dang Van Tron intersection...

Regarding the implementation progress, up to now, contractors have implemented the construction of 5 main construction packages, the value of the packages is nearly 444 billion VND, reaching about 40%.

The project to build the central axis road of Bien Hoa city, the section from Vo Thi Sau street to Dang Van Tron street is a key traffic project of Dong Nai province with a total length of nearly 5.5 km.

The total area reclaimed is about 33.38 hectares with 380 households. Of which, Thong Nhat ward has about 50 households, Hiep Hoa ward has about 330 households.

The total investment is about 1,506 billion VND, of which the construction cost is 1,273 billion VND from the provincial budget.

The project implementation period is from 2021 to 2026.

The Bien Hoa City Central Axis Road Project with Thong Nhat Bridge and the road connecting the two ends of the bridge were started on January 31, 2023 and is expected to be completed after nearly 3 years of construction.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Auction of Hoa An quarry land with an area of nearly 37 hectares in Dong Nai

|

Dong Nai - The land of the Hoa An quarry in Bien Hoa city has an area of nearly 37 hectares (value according to the land price list of over 500 billion VND) and is planned to be auctioned in September 2025.

In 2026, construction of a social housing project with nearly 1,250 apartments in Dong Nai will begin

|

Dong Nai - Social housing in Long Binh ward, Bien Hoa city will be built with 12 floors, including 1,248 apartments, completing procedures in 2025 and starting construction in 2026.

Opening a 1,000 billion VND arterial road in Dong Nai

|

Dong Nai - The Trang Dai - Tan Hiep - Tan Phong inter-ward road construction project (Bien Hoa city) has a total investment (in 2019) of about 1,000 billion VND.

Son Tung M-TP loves a popular specialty in Quang Ninh

|

Quang Ninh - When announcing the upcoming performance in Ha Long City, singer Son Tung M-TP took the opportunity to show off a specialty dish to fans.

Hour 9: The lonely woman - Part 1

|

Hour 9 - A woman was forced to get married, then left empty-handed. Although she rose strongly, in the end, will she find happiness?

Vietnam team is missing 4 players at the first training session in Binh Duong

|

4 players Tien Linh, Quang Hai, Thanh Binh and Bui Hoang Viet Anh were not present in the first training session of the Vietnam team in Binh Duong.

The money-based waste weighing pilot in Ho Chi Minh City is still inadequate

|

HCMC - Currently, Hoc Mon and Binh Chanh districts are applying the pilot of weighing garbage to calculate money. This caused many collectors to react because of inadequacies.

Service land price of a district in Hanoi exceeds 200 million VND/m2

|

Hanoi - Many service land plots in Ha Dong district are being advertised by owners at prices exceeding 200 million VND/m2.

Auction of Hoa An quarry land with an area of nearly 37 hectares in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - The land of the Hoa An quarry in Bien Hoa city has an area of nearly 37 hectares (value according to the land price list of over 500 billion VND) and is planned to be auctioned in September 2025.

In 2026, construction of a social housing project with nearly 1,250 apartments in Dong Nai will begin

HÀ ANH CHIẾN |

Dong Nai - Social housing in Long Binh ward, Bien Hoa city will be built with 12 floors, including 1,248 apartments, completing procedures in 2025 and starting construction in 2026.

Opening a 1,000 billion VND arterial road in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - The Trang Dai - Tan Hiep - Tan Phong inter-ward road construction project (Bien Hoa city) has a total investment (in 2019) of about 1,000 billion VND.