To have 7 metro lines in 10 years, HCMC must do it differently

MINH QUÂN |

Ho Chi Minh City aims to complete seven metro lines totaling 355km by 2035, but without innovation in the way it works, this plan will be difficult to achieve.

It took 17 years to build 20km Metro Line 1.

Metro Line No. 1 (Ben Thanh - Suoi Tien), nearly 20km long, has officially been put into commercial operation since December 22, 2024, 17 years after its approval.

Initially, the project had a total investment of more than 17,000 billion VND, started in 2012 with a plan to complete in 2018. However, a series of difficulties caused the progress to be continuously delayed.

In 2019, the total investment was adjusted to more than 43,700 billion VND and took another 5 years of construction.

Tinh tu luc duoc phe duyet, Metro so 1 mat 17 nam de di vao van hanh.  Anh: Anh Tu
From the time it was approved, Metro Line 1 took 17 years to come into operation. Photo: Anh Tu

Similarly, Metro Line 2 (Ben Thanh - Tham Luong) was approved in 2010 with an initial total investment of about VND 26,000 billion and adjusted to nearly VND 47,900 billion in 2019.

In the past, the project encountered difficulties due to slow site clearance and capital arrangement. Although Ho Chi Minh City later decided to use budget capital instead of ODA loans, to date, this metro line has not been able to start construction.

In reality, it takes 17 years to complete a 20km metro line (Metro Line 1), while Metro Line 2 has not yet started construction after more than a decade.

Without breakthrough changes, the goal of building 7 metro lines with a total length of 355km within 10 years is an extremely big challenge.

Complicated procedure with 52 steps

According to the Ho Chi Minh City Urban Railway Management Board (MAUR), to implement a metro project in Vietnam, the process must go through 52 steps in 4 phases.

If the investor proactively proposes a project, it takes 7 steps to prepare a pre-feasibility report, 6 steps to approve the investment policy, 7 steps to approve the project and 32 steps to select an investor.

In case the city proactively conducts pre-feasibility studies and calls for investment, the number of steps can be reduced to 48, but important steps such as approving investment policies, approving projects and selecting investors remain the same.

TPHCM dat muc tieu den nam 2035, he thong metro dam nhan 40-50% thi phan van tai hanh khach cong cong.  Anh: Anh Tu
Ho Chi Minh City aims to have the metro system take on 40-50% of the public passenger transport market share by 2035. Photo: Anh Tu

The complexity of procedures is one of the main reasons for the slow implementation of metro lines in Ho Chi Minh City. Without a specific mechanism, each metro line still has to "grope" according to the old process, easily falling into a vicious circle like previous projects.

Five big lessons from Metro Line 1

According to Mr. Nguyen Quoc Hien - Deputy Head of MAUR, from the implementation of Metro Line 1, the city has drawn 5 important lessons to apply to the next metro lines.

First, site preparation must be done carefully. The Metro Line 1 project took 12 years to complete, partly due to inaccurate site surveys, which led to increased costs and delays.

Second, the legal framework needs to be clear. Metro Line 1 was implemented in a context of a lack of detailed regulations, causing procedures to be submitted to multiple levels, causing delays. Therefore, the metro system needs a systematic legal framework to avoid a repeat of this situation.

Third, the contract preparation must be rigorous. Contracts for metro projects are often very valuable, over 100 million USD. International contractors have strong legal teams, while the Vietnamese side has not prepared thoroughly enough. This leads to many unclear terms, causing disputes between contractors and consultants.

Fourth, it is necessary to increase autonomy in the implementation process. Metro Line 1 takes a long time because it requires consultation from many ministries and sectors, prolonging the implementation time. Giving more autonomy to localities will help shorten the project implementation time.

Finally, metro construction must be based on operation. Unlike bridge construction, which only needs to connect two points, metro systems require synchronization from the beginning, including operation, maintenance, personnel training and connection with other types of transport. If not calculated carefully, exploitation will encounter many difficulties.

MINH QUÂN
RELATED NEWS

On the first Tet holiday, Metro Line 1 in Ho Chi Minh City earned more than 11.7 billion VND

|

HCMC - During the 10 peak days of Tet, Metro Line 1 (Ben Thanh - Suoi Tien) served more than 761,000 passengers, earning more than 11.7 billion VND.

Metro Line 1 officially operates, fulfilling a 17-year dream

|

HCMC - On the morning of December 22, Metro Line No. 1 (Ben Thanh - Suoi Tien) officially operated, marking a historical milestone after 17 years from the date of approval and 12 years of construction.

Metro Line 2 in Ho Chi Minh City unexpectedly switches from ODA capital to budget

|

Metro Line 2 (Ben Thanh - Tham Luong) was approved by the Party Committee of the Ho Chi Minh City People's Committee to be implemented using budget capital, instead of using ODA loans.

The salary that Bich Thuy can receive if competing in Japan

|

Many predict that Tran Thi Bich Thuy will go to Japan, however, she still participates in the second phase of the 2025 National Volleyball Championship.

Eliminate vehicle parking spots under bridges in 2 wards in Hanoi

|

Hanoi officially clears vehicle parking lots under Vinh Tuy bridge in Vinh Hung and Vinh Tuy wards.

Controversy over "Red Rain" and the hardship of historical war films

|

Controversies about some fictional details in "Red Rain" show difficulties in producing historical films, even in world cinema.

Mr. Nguyen Khac Toan was elected to hold the position of Chairman of Khanh Hoa Provincial People's Committee

|

Khanh Hoa - Mr. Nguyen Khac Toan - Standing Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council, was elected to hold the position of Chairman of the Khanh Hoa Provincial People's Committee for the 2021 - 2026 term.

On the first Tet holiday, Metro Line 1 in Ho Chi Minh City earned more than 11.7 billion VND

MINH QUÂN |

HCMC - During the 10 peak days of Tet, Metro Line 1 (Ben Thanh - Suoi Tien) served more than 761,000 passengers, earning more than 11.7 billion VND.

Metro Line 1 officially operates, fulfilling a 17-year dream

Nhóm PV |

HCMC - On the morning of December 22, Metro Line No. 1 (Ben Thanh - Suoi Tien) officially operated, marking a historical milestone after 17 years from the date of approval and 12 years of construction.

Metro Line 2 in Ho Chi Minh City unexpectedly switches from ODA capital to budget

MINH QUÂN |

Metro Line 2 (Ben Thanh - Tham Luong) was approved by the Party Committee of the Ho Chi Minh City People's Committee to be implemented using budget capital, instead of using ODA loans.