Increasing the capacity of quarries, ensuring the progress of the expressway in Da Nang

Nguyễn Linh |

The Hoa Lien - Tuy Loan Expressway Project in Da Nang is facing difficulties in filling materials and a shortage of fill soil. Da Nang City has upgraded Truong Ban quarry and accelerated site clearance to complete the project in August.

The Hoa Lien - Tuy Loan Expressway Project, a section passing through Da Nang City with a length of 11.5km, stretching across the three communes of Hoa Nhon, Hoa Son and Hoa Lien, is facing challenges in balancing filling materials.

According to the report of the Ho Chi Minh Road Project Management Board, although the balance of excavated and filled soil within the project is still being controlled, the quality of exploited soil and rock does not meet the technical requirements for filling activities.

To solve this problem, the Department of Natural Resources and Environment of Da Nang City has proposed and approved by the City People's Committee a plan to handle excess soil and rock. Fortified soil and soil of poor quality will be transported to four closed mines for site clearance. This solution not only helps save processing costs but also contributes to improving the environment and restoring old mining areas.

However, in addition to handling excess soil and rock, the project is also facing a shortage of fill soil.

After careful consideration of quality, reserves and economic and technical factors, the solution was to upgrade the Truong Ban stone quarry. Truong Ban Stone Quarry has completed the proposal to increase the exploitation capacity to 100% and is waiting for approval from the City People's Committee.

The raising of Truong Ban quarry capacity needs the consent of the relevant units, including the Ho Chi Minh Road Project Management Board and the local government. All the production of the mine will be given priority for the Hoa Lien - Tuy Loan highway project, ensuring a stable supply of materials. The plan of upgrading Truong Ban quarry is expected to help accelerate the construction progress and complete the project on time.

The Hoa Lien - Tuy Loan Expressway project started construction in September 2023 and is expected to be completed in November 2025. However, the Government aims to shorten the completion progress in August with a total investment of VND 2,112.985 billion.

According to Mr. Phan Van Ton - Chairman of Hoa Vang District People's Committee, the nearly 11.5km long main expressway has been completely handed over. However, the 20km parallel service road has only been handed over 19.43km, and more than 20 dossiers are still stuck.

In that situation, the Ho Chi Minh Road Project Management Board has proposed that Da Nang City direct Hoa Vang District to urgently complete procedures for compensation payment, support, and resettlement arrangement for the remaining households, and at the same time request the locality to take stronger and more drastic measures to require people to hand over more than 500m of remaining land.

The Ho Chi Minh Road Project Management Board said that it has completed the contractor selection procedures and is ready to start construction of resettlement area No. 1 in March. For the remaining 2 resettlement areas, procedures are being urgently implemented, ensuring completion in 2025.

Nguyễn Linh
TIN LIÊN QUAN

Day and night construction of Can Tho - Ca Mau expressway after the Prime Minister's direction

|

In order for the Can Tho - Ca Mau expressway to be completed by December 19 at the latest, the contractor has proactively developed a detailed plan, with the goal of completing the asphalt paving by the end of November.

Urgently compensate people with dead rice next to the Can Tho - Ca Mau Expressway

|

The Deputy Prime Minister requested an urgent review, statistics and compensation for damages to people with dead rice next to the Can Tho - Ca Mau Expressway.

Nearly 7,000 households will give up land to build highways and open national highways

|

Ho Chi Minh City is urgently completing land acquisition procedures for nearly 7,000 households to implement a series of key transport projects including the Ho Chi Minh City - Moc Bai Expressway and 4 projects to upgrade and expand National Highways 1, 13, 22 and the North - South axis road.

Voters propose preserving Hoi An after administrative unit arrangement

|

Hoi An commune-level administrative unit is still facing many conflicting opinions after the reorganization project of Quang Nam.

Another third case of falling from a building and dying at Van Hanh Mall in Ho Chi Minh City

|

HCMC - On April 26, a third case of falling from a building was recorded and died at Van Hanh Mall (District 10). The authorities are still investigating the incident.

Song Lam Nghe An recommends refereeing work at V.League

|

Song Lam Nghe An Club sent a document recommending the refereeing after the match against The Cong Viettel in round 20 of V.League 2024-2025.

Garbage truck collides with 2 motorbikes on the road, 4 people injured and dead

|

Long An - A garbage truck collided with 2 motorbikes on National Highway N2, killing 2 people on the motorbike and seriously injuring 2 others.

Agree to reduce land rent payable in 2025

|

The Government asks for the opinion of the National Assembly Standing Committee on reducing 30% of land rent payable in 2025 to support people and businesses.

Day and night construction of Can Tho - Ca Mau expressway after the Prime Minister's direction

Tạ Quang |

In order for the Can Tho - Ca Mau expressway to be completed by December 19 at the latest, the contractor has proactively developed a detailed plan, with the goal of completing the asphalt paving by the end of November.

Urgently compensate people with dead rice next to the Can Tho - Ca Mau Expressway

PHẠM ĐÔNG |

The Deputy Prime Minister requested an urgent review, statistics and compensation for damages to people with dead rice next to the Can Tho - Ca Mau Expressway.

Nearly 7,000 households will give up land to build highways and open national highways

MINH QUÂN |

Ho Chi Minh City is urgently completing land acquisition procedures for nearly 7,000 households to implement a series of key transport projects including the Ho Chi Minh City - Moc Bai Expressway and 4 projects to upgrade and expand National Highways 1, 13, 22 and the North - South axis road.