Hot weather does not hinder the progress of the Can Tho - Ca Mau expressway

Tạ Quang |

Overcoming the heat, engineers and workers constructing the Can Tho - Ca Mau expressway are making continuous efforts to complete the key project on schedule.

Amidst the fiery summer sunshine of the Western region, the construction site of the Can Tho - Ca Mau expressway is still bustling with the sound of machinery and the footsteps of hundreds of workers.

According to Lao Dong Newspaper, at the IC5 intersection, more than 150 people and equipment are focusing on high-altitude construction for many different stages.

Nut giao IC5 thuoc cao toc Can Tho - Ca Mau. Anh: Ta Quang
IC5 intersection on Can Tho - Ca Mau Expressway. Photo: Ta Quang

Mr. Nguyen Bang (born in 1997, Bac Lieu province) shared that harsh weather really affects his health. However, he and his colleagues always encouraged each other and were determined to complete the assigned work.

Sharing the same spirit, Mr. Nguyen Van Ngu (born in 1976, Dak Lak province) confided that the hot weather makes outdoor work more tiring. But thinking that the completed road will bring convenience to people, making it easier for goods to circulate, he has more motivation to try.

Anh Nguyen Van Ngu ke ve cai nang nong gay gat tren cong truong. Anh: Ta Quang
Mr. Nguyen Van Ngu talked about the fierce heat at the construction site. Photo: Ta Quang

Mr. Nguyen Thanh Vinh - Deputy Executive Director of Truong Son Nam Board - said that the unit is constructing 21km of road with 20 bridges and has reached about 50% of the workload. Currently, there are about 150 engineers and workers working in the spirit of "3 shifts", taking advantage of the whole night to speed up the progress.

Mr. Nguyen Thanh Vinh added that with hot weather combined with a large amount of work, the unit also did not forget to remind workers to pay attention to their health, drink enough water and rest properly to ensure endurance in harsh weather conditions.

Mac du nang nong nhung cong nhan va may moc van hoat dong lien tuc. Anh: Ta Quang
Despite the hot weather, workers and machinery are still operating continuously. Photo: Ta Quang

Overcoming many difficulties, the workers at the Can Tho - Ca Mau expressway construction site have always maintained a sense of responsibility and enthusiasm. They understand that every drop of sweat that falls on them contributes to the development of their homeland.

My Thuan Project Management Board informed that the construction progress has reached 66/70% of the plan. Basic material problems have been resolved. It is expected that all bridges on the route will be completed before April 30 and 100% of the work of reloading the entire route will also be completed at the same time.

Den nay, tien do thi cong cao toc Can Tho - Ca Mau da dat 66/70% ke hoach. Anh: Ta Quang
To date, the construction progress of the Can Tho - Ca Mau expressway has reached 66/70% of the plan. Photo: Ta Quang

According to the Ministry of Construction, contractors have mobilized 183 construction teams, 971 machines and equipment, 3,000 human resources, and organized overtime construction. To date, the route has been relocated for 74.9km (nearly 90%), the bridge section has deployed 95/95% of bridges on the main route, meeting the schedule.

Previously, at the inspection of the Can Tho - Ca Mau expressway in Ca Mau province, Prime Minister Pham Minh Chinh proposed that it must be inaugurated on December 19, 2025. To achieve this, it is necessary to construct more quickly, be more determined, and focus all resources to complete the entire route.

The Can Tho - Ca Mau expressway project has a main route length of 110.85km (through Can Tho city is 0.6km, Hau Giang province is 63.65km, Bac Lieu province is 7.7km, Kien Giang province is 17km, Ca Mau province is 21.9km) and 25.85km connecting route. The project is divided into 2 component projects including the Can Tho - Hau Giang section and the Hau Giang - Ca Mau section invested by the My Thuan Project Management Board, with a scale of 4 lanes, a total investment of VND 27,523 billion. The project started on January 1, 2023, and is scheduled to be completed by the end of 2025.

Tạ Quang
RELATED NEWS

Can Tho - Ca Mau Expressway accelerates asphalt paving without holidays

|

Hau Giang - Taking advantage of good weather, the contractor constructed the Can Tho - Ca Mau expressway with asphalt in each segment.

Investors inform about compensation for people in the dead rice crop next to the highway

|

My Thuan Project Management Board has coordinated with Hau Giang provincial authorities to help people affected by dead rice next to the Can Tho - Ca Mau expressway

Day and night construction of Can Tho - Ca Mau expressway after the Prime Minister's direction

|

In order for the Can Tho - Ca Mau expressway to be completed by December 19 at the latest, the contractor has proactively developed a detailed plan, with the goal of completing the asphalt paving by the end of November.

Man falls into spillway dead, motorbike stuck on dam bank

|

Dak Lak - Functional agencies are investigating the cause of the incident at the Krong Buk Ha reservoir area that killed a man.

Hundred-billion-dong actor Quang Tuan talks about the nickname princess given by Tran Thanh

|

Actor Quang Tuan shared with Lao Dong Newspaper about his balance between acting and participating in reality television.

King" Drone may launch thousands of UAVs to appear soon

|

The "king" drone (drone or UAV) that can carry thousands of UAVs will soon appear.

Cuba widespread power outage, Internet distribution by time frame

|

Many areas in Cuba can now only access the Internet or make phone calls for a few short hours each day due to widespread power outages.

Leaving crowded roads and traffic jams, people in Hanoi take the tram home

|

Hanoi - After rush hour, many people have chosen electric trains to travel quickly, reduce congestion, and contribute to promoting green traffic.

Can Tho - Ca Mau Expressway accelerates asphalt paving without holidays

Tạ Quang |

Hau Giang - Taking advantage of good weather, the contractor constructed the Can Tho - Ca Mau expressway with asphalt in each segment.

Investors inform about compensation for people in the dead rice crop next to the highway

Tạ Quang |

My Thuan Project Management Board has coordinated with Hau Giang provincial authorities to help people affected by dead rice next to the Can Tho - Ca Mau expressway

Day and night construction of Can Tho - Ca Mau expressway after the Prime Minister's direction

Tạ Quang |

In order for the Can Tho - Ca Mau expressway to be completed by December 19 at the latest, the contractor has proactively developed a detailed plan, with the goal of completing the asphalt paving by the end of November.