Trillions of Dong in projects in Quang Ngai waiting for disbursement

VIÊN NGUYỄN |

The implementation of many large projects in Quang Ngai is facing difficulties due to land acquisition problems, leading to stagnant progress, with more than a thousand billion VND waiting for disbursement.

The Hoang Sa - Doc Soi Road Project with a total investment of 3,500 billion VND, of which 1,300 billion VND is from the central budget, the rest is from the provincial budget; invested by the Quang Ngai Provincial Traffic Project Management Board, started construction in December 2023. The total capital plan for 2024 allocated for the project is over 792.5 billion VND, of which the capital plan assigned at the beginning of the year is over 192.5 billion VND. The additional capital plan from the increased central budget revenue source in 2022 is 600 billion VND. The money is available, but so far only over 47.1 billion VND has been disbursed, reaching 24.5% of the capital plan assigned at the beginning of the year. Not a single dong has been disbursed from the increased central budget revenue source in 2022.

Tien do du an duong ven bien Dung Quat – Sa Huynh, giai doan IIB dang tri tre vi vuong mat bang, du kien se khong phe duyet duoc bat ky phuong an boi thuong nao trong nam 2024. Anh: Vien Nguyen
The progress of the Dung Quat – Sa Huynh coastal road project, phase IIB, is stagnant due to land acquisition issues, and it is expected that no compensation plan will be approved in 2024. Photo: Vien Nguyen

The main difficulty of the project is that the progress of site clearance on the main route of Hoang Sa - Doc Soi is very slow, to date only 29.32/164.51 hectares have been handed over, reaching 17.8%. The handed over site is not continuous, so it is not possible to ensure the simultaneous implementation of construction projects according to the plan, leading to slow construction progress and failure to ensure the disbursement of the capital plan for 2024.

There are still many major unresolved problems in site clearance, such as the specific land price for compensation calculation in 2024 has not been approved or has been approved but is no longer suitable. The Provincial People's Committee's regulations on compensation, support, and resettlement according to the 2024 Land Law and guiding Decrees have not been issued... so it is expected that the project's progress in the rest of 2024 will continue to be delayed.

Similarly, the Dung Quat – Sa Huynh coastal road project, phase IIB, is also sluggish due to land clearance problems. Accordingly, the total capital plan for 2024 allocated for the project is 290 billion VND. However, so far, only 8.079/290 billion VND has been disbursed, reaching 2.8% of the capital plan. Currently, the project is stuck with land clearance work, the section through Binh Son district, Quang Ngai city and Mo Duc district.

From now until the end of the year, the estimated value of approved compensation and support plans for the section through Quang Ngai City, Binh Son, and a part through Mo Duc District will not ensure progress according to the plan. It is expected that no compensation plan will be approved in 2024, thus only ensuring the ability to disburse in 2024 of about 68 billion VND.

The same situation is the project of embankment to prevent landslides and beautify the landscape of the southern bank of Tra Khuc River (Tra Khuc 1 bridge - Ben Tam Thuong), the central budget capital plan for 2024 is 100 billion VND, but so far only 2.4 billion VND has been disbursed, reaching 2.4% of the capital plan. Currently, due to difficulties in implementing the project's site clearance, especially difficulties related to the area overlapping the boundary of the Tra Khuc River downstream dam (the project started in 2010), the site clearance progress and construction output in 2024 are not guaranteed according to plan. After review, it is expected that the disbursement of the central budget capital plan in 2024 will be about 44.3 billion VND.

VIÊN NGUYỄN
RELATED NEWS

Flood center of Hoa Thinh commune devastated, trying to get up after severe floods

|

Dak Lak - On November 24, floodwaters in Hoa Thinh commune have receded. The authorities are deploying to help people overcome the consequences of natural disasters.

Gold price today 11/24: Domestic tensions, world decline

|

Gold price today 11/24: Domestic gold market struggles in opposite directions. Meanwhile, world gold is being adjusted down.

Gia Lai flooded again after heavy rain, many neighborhoods submerged in water

|

Gia Lai - Heavy rain at night caused many areas in the eastern part of the province to be flooded again, especially the downstream of the Ha Thanh River and residential areas of Quy Nhon Bac Ward.

Probability to welcome storm No. 15 in the East Sea, forecast time and area at risk of heavy rain

|

Initial forecast for around November 28-30, the area from Da Nang to Lam Dong is likely to experience widespread heavy rain due to storm No. 15.

15 national highway and railway congestion points were severely damaged by heavy rain and floods

|

Traffic in many Central and Central Highlands provinces was severely affected by a particularly heavy flood, a series of landslides and flooding caused traffic congestion.

Banning motorbikes using gasoline in Ring Road 1: Support levels

|

owners of gasoline motorbikes who switch to electric motorbikes worth VND10 million or more will be supported with a maximum of VND5 million.

HCMC dispatches hundreds of soldiers to support 18 communes and wards in flooded areas, Dak Lak province

|

HCMC - HCMC Police mobilized 200 officers, soldiers and many specialized vehicles to promptly support Dak Lak province in the recent natural disaster.

Vì sao Quảng Ngãi giải ngân vốn đầu tư công thấp?

VIÊN NGUYỄN |

Tại kỳ họp thứ 25, Hội đồng nhân dân tỉnh khoá XIII, lãnh đạo tỉnh Quảng Ngãi cho hay, kết quả giải ngân vốn đầu tư công trong 6 tháng đầu năm 2024 vẫn còn thấp.

Bộ NN&PTNT đốc thúc Quảng Ngãi giải ngân vốn được bố trí

VIÊN NGUYỄN |

Bộ NN&PTNT bố trí vốn cho Quảng Ngãi để nâng cấp và mở rộng cảng cá Tịnh Hòa, TP Quảng Ngãi. Tuy nhiên, đến nay việc giải ngân vốn đang rất trì trệ do vướng mặt bằng.

Quảng Ngãi khó giải ngân gần 660 tỉ đồng cho người nghèo

Viên Nguyễn |

Hàng nghìn tỉ đồng được phân bổ cho Chương trình mục tiêu quốc gia phát triển kinh tế - xã hội vùng đồng bào dân tộc thiểu số và miền núi ở tỉnh Quảng Ngãi - giúp đời sống của người dân vùng cao ngày vơi bớt khó khăn, tuy nhiên việc giải ngân nguồn vốn này giai đoạn 2021-2025 đạt tỉ lệ rất thấp so với kế hoạch.