The project to upgrade National Highway 14E in Quang Nam is in chaos

Hoàng Bin |

Quang Nam is asking to speed up the construction progress of the 1,850 billion VND National Highway 14E renovation and upgrade project. This project involves Thuan An Group, which has encountered many difficulties after the group's leader was arrested.

Slow progress

Quang Nam Provincial People's Committee said that after a period of focusing on removing bottlenecks in compensation, site clearance, and resettlement of the National Highway 14E renovation and upgrading project, the province has so far handed over 62.2/71.38km of land, reaching over 87%. The province is determined to hand over the entire land before December 31, 2024.

Mr. Le Van Dung - Chairman of Quang Nam Provincial People's Committee - assessed that the project's progress was too slow, because the construction speed had not kept up with the site clearance progress. This responsibility lies with the investor and the capacity of the project's contractors.

Quang Nam provincial leaders requested Project Management Board 4, Vietnam Road Administration (investor) to have drastic solutions to speed up construction progress, promptly terminate contracts, replace contractors who do not ensure capacity; have plans for overtime, and work with the spirit of "overcoming the sun, overcoming the rain" to ensure progress.

Working with the leaders of Quang Nam province to discuss solutions to speed up the progress of site clearance for the project to upgrade and expand National Highway 14E recently, the representative of Project Management Board 4, Vietnam Road Administration admitted that the project's construction progress is slow. The investor has taken measures to terminate the contract and replace some contractors who do not ensure progress.

Mr. Que Hai Trung - Deputy Director of Project Management Board 4, Vietnam Road Administration - said that during the design process, some project items still had many shortcomings such as the drainage system being much higher than the ground level of houses along National Highway 14E. The investor will coordinate with localities in the project area to make adjustments soon.

Du an nang cap, mo rong QL 14E tai Quang Nam dang thi cong i ach, do anh huong thoi tiet mua bao va nang luc han che cua nha thau. Anh: Nguyen Hoang
The project to upgrade and expand National Highway 14E in Quang Nam is being slowly constructed due to the impact of stormy weather and the limited capacity of the contractor. Photo: Nguyen Hoang

People suffer because of patchwork construction

According to Lao Dong, the recent heavy rains have caused many damaged sections of the road at the construction site of the project to upgrade and expand National Highway 14E through Quang Nam, causing obstacles and difficulties for people to travel.

Along the 30km stretch from Thang Binh district to Hiep Duc district, many sections of the road surface are peeling and riddled with potholes. The narrow, heavily damaged road, which is under construction, has caused many cars and trucks to be stuck and unable to avoid each other, posing a danger to road users, especially during rush hour when students leave school.

Ms. Nguyen Thi Hoa (a resident of Binh Quy commune, Thang Binh district) said that since the project was implemented in 2023, a traffic "black spot" of more than 50m long has appeared through Quy Xuan village, Binh Quy commune, causing many people to have accidents.

The construction unit has repaired many times, but could not improve completely. Currently, people have to live in the "dusty sun, muddy rain", worried because of the density of hundreds of trucks and containers circulating every day, the risk of safety is very high.

The representative of Project Management Board 4 (project investor) said that the continuous rain has affected the construction progress and the roadbed has deteriorated. Therefore, the investor has requested the construction units to review and inspect the entire project as well as repair unsafe points. However, the project is both under construction and for traffic exploitation, so it also hopes that people will share.

“For the construction of the project passing through residential areas, we have directed the construction units to purchase insurance and the insurance payment for cases of cracked houses will be carried out in several stages. We will request the insurance to coordinate with the locality to determine the current status of the affected houses before the construction time to have a basis to assess the extent of damage and then pay compensation to the affected households,” added Mr. Que Hai Trung - Deputy Director of Project Management Board 4, Vietnam Road Administration.

The project to renovate and upgrade National Highway 14E through Thang Binh, Hiep Duc, Phuoc Son districts, Quang Nam has a total investment of more than 1,848 billion VND, from the State budget. In March 2023, the project officially started construction, expected to be completed in 2025. The project is divided into 3 packages; the consortium of Tan Hoang Long Investment and Construction Trading Joint Stock Company - Thuan An Construction and Trade Development Joint Stock Company (later changed to Thuan An Group Joint Stock Company) - Tay An Investment and Construction Joint Stock Company won the XD02 package to construct the section from km40+00 to km71+500. The winning price of the XD02 package is more than 507 billion VND.

Hoàng Bin
TIN LIÊN QUAN

Investing 1,500 billion VND to expand the road connecting National Highway 51 in Dong Nai

|

Dong Nai - The project to upgrade Road 25B from the center of Nhon Trach district to National Highway 51 is speeding up the completion of procedures to start construction soon.

Multiple accidents on Highway 1, 9-seat car deformed

|

Ha Tinh - A series of traffic accidents occurred on National Highway 1 through Cam Quang commune (Cam Xuyen district) causing a 9-seat car to be deformed.

Clarifying responsibility for issuing wrong red books on prison land

|

Lam Dong - Provincial inspectors determined that 4.29 hectares of land of Dai Binh Prison had been illegally granted red books by local authorities to 7 households.

Inadequate treatment of officials and workers

|

National Assembly delegates said that the treatment of officials and employees working at drug rehabilitation facilities is not commensurate with the requirements and tasks of the job.

Nam Dinh has a new Provincial Party Secretary

|

Nam Dinh - Mr. Dang Khanh Toan was mobilized and appointed by the Politburo to hold the position of Secretary of Nam Dinh Provincial Party Committee.

Go Cong sea dike "fluctuates" before monsoon season

|

Tien Giang - Some sections of the Go Cong sea dike are degraded, local authorities in Go Cong Dong district have proposed investing in wave-reducing dikes.

Sad news

|

Mr. Ignatius Do Van Luan, born in 1956, father of comrade Do Thi Yen Phuong, father-in-law of comrade Nguyen Van Quang - reporter of Lao Dong Newspaper working at the Representative Office in the Mekong Delta, passed away at 2:00 p.m. on November 13, 2024, October 13, Giap Thin year. He was 68 years old.

Proposal to discipline former Minister of Transport Nguyen Van The

|

At the 50th Session, the Central Inspection Committee proposed that competent authorities consider and discipline Mr. Nguyen Van The.

Investing 1,500 billion VND to expand the road connecting National Highway 51 in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade Road 25B from the center of Nhon Trach district to National Highway 51 is speeding up the completion of procedures to start construction soon.

Multiple accidents on Highway 1, 9-seat car deformed

TRẦN TUẤN |

Ha Tinh - A series of traffic accidents occurred on National Highway 1 through Cam Quang commune (Cam Xuyen district) causing a 9-seat car to be deformed.

Sẽ khắc phục ngập ở Quốc lộ 14E trong quý I

Ngọc Thiện |

Bộ Giao thông vận tải cho biết, đã cân đối chấp thuận danh mục sửa chữa để thực hiện trong kế hoạch bảo trì quốc lộ với kinh phí 4,767 tỉ đồng.