People regret land while waiting for VSIP project to be constructed

TRẦN TUẤN |

Ha Tinh - After nearly 1 year of construction, the VSIP Ha Tinh Project still has many hectares of unpaved and abandoned rice fields, making farmers regret their land.

Abandoned rice fields

On March 19, a reporter from Lao Dong Newspaper in Thach Lien Commune (Thach Ha District) recorded on the large field where the VSIP Ha Tinh Industrial Park Project (phase 1) has reclaimed people's rice fields, there are still many hectares of abandoned land that have not been cleared.

Mr. Bui Dinh Quoc (born in 1987, residing in Phu Quy village, Thach Lien commune), in the recent Winter - Spring crop, he sprayed herbicide on an area of 30,000m2 to prepare for the land and rice cultivation. However, this is the land of the VSIP Ha Tinh Project that has reclaimed the land from the people, so they do not allow him to cultivate anymore.

Con kenh phan chia phan dat cua du an VSIP Ha Tinh (ben trai) dang bo hoang va dat ruong cua dan canh tac lua xanh tot. Anh: Tran Tuan.
The canal dividing the land of the VSIP Ha Tinh project (left) is abandoned and the rice fields of the people of Thach Lien commune have not been reclaimed until now, and are being cultivated with green rice. Photo: Tran Tuan.

Knowing that I was planning to do the fields, VSIP stopped because they said they were about to do the construction. I said I was farming, if I were to construct, I would suffer the damage myself, but they still did not give me. However, they have not yet come to construct. If I had let them do it, I would definitely have had time to harvest more rice in this crop, Mr. Quoc pointed out the fields of Phu Quy village with regret.

According to Mr. Quoc, in the Summer - Autumn crop of 2024, when the VSIP Ha Tinh Project had started construction, he still managed to grow a rice crop on an area of 30,000m2, after deducting investment costs, he still made a profit of about 40 million VND.

According to the reporter's investigation, in the recent Winter - Spring crop, many farmers in Thach Lien commune regretted the abandoned VSIP project land, so they prepared the land for sowing. However, VSIP later requested that they not be allowed to cultivate anymore, so they had to stop. Up to now, those plots of land are still abandoned and unconstructed.

Hope the project speeds up progress

In June 2024, Vietnam Singapore Urban and Industrial Park Development Joint Stock Company (VSIP) held a groundbreaking ceremony for the VSIP Ha Tinh Industrial Park Project (phase 1) with a scale of 190.41 hectares, a total investment of more than 1,555 billion VND in Thach Lien and Viet Tien communes (Thach Ha district).

According to the schedule, the project will be completed after 3 years of construction. When completed, it is expected to attract domestic and foreign investors in fields such as: Electricity and electronics, semiconductors, precision mechanics, energy, electric vehicle batteries, metals, auto parts, food processing, logistics services, factories for rent... will create more than 30,000 jobs, creating momentum for the development and economic restructuring of Ha Tinh province.

Khu dat truoc day lam le khoi cong du an VSIP Ha Tinh. Anh: Tran Tuan.
The land was previously used for the groundbreaking ceremony of the VSIP Ha Tinh project. Photo: Tran Tuan.

However, after nearly 1 year of construction, in recent times, the project's construction has shown signs of being sluggish, with only a few excavators operating at the construction site. Currently, many hectares of rice fields have not been constructed and have been peeled off.

Mr. Tran Van Huong - Chairman of Thach Lien Commune People's Committee - said that currently, there are still dozens of hectares of agricultural land in the VSIP Ha Tinh project that have been reclaimed from the people but have not yet been constructed with embankment. Previously, in Thach Lien commune, the project had carried out the excavation of the phong phong in some locations, but after a while, it was no longer carried out.

Mot doan dat ruong da boc phong hoa dang tien hanh do dat san lap lam duong. Anh: Tran Tuan.
A section of peeled rice fields is being filled to make roads. Photo: Tran Tuan.

Mr. Nguyen Van Huong - Chairman of the People's Committee of Viet Tien commune - shared that the local government hopes that the VSIP Ha Tinh project will speed up the construction progress, ensuring the completion of the project on schedule. Thereby, attracting effective investment to create jobs for local people and promoting the development of service activities accordingly.

TRẦN TUẤN
TIN LIÊN QUAN

Many abandoned headquarters in the heart of Bac Lieu city

|

Bac Lieu - Newly formed headquarters, old headquarters abandoned, some places abandoned for more than 10 years without anyone looking.

Deputy Prime Minister shows how to remove obstacles for 4 abandoned projects in Nha Trang

|

Khanh Hoa - Deputy Prime Minister Ho Duc Phoc has suggested solutions to remove legal obstacles for 4 abandoned prime land projects in Nha Trang.

The fate of a dormitory worth over VND860 billion abandoned for 15 years

|

Ninh Binh - The concentrated student dormitory project started construction in 2009, and up to now, after 15 years, this project is still unfinished and abandoned.

Accelerating renovation, Cau Giay Park is airy after fencing

|

Hanoi - Cau Giay Park (Cau Giay District) is currently undergoing renovation and has completed the lowering of the surrounding fence to create open space.

Gasoline price today, March 20: All increase

|

Today's gasoline price, March 20: World gasoline price continues to increase today. Domestic gasoline prices are expected to increase sharply this afternoon.

Vingroup proposes to build metro line from District 7 to Can Gio

|

HCMC - Vingroup Corporation proposed to invest in a 48.7km long elevated metro line, a speed of 250km/h connecting District 7 to the Can Gio coastal urban tourism project.

Nam Nghiep ancient paint flower forest attracts visitors in the most beautiful season

|

Son La - Nam Nghiep village (or Nam Nghiep), Ngoc Chien commune is in the most beautiful mountainside flower season in recent years when flowers bloom evenly.

The billion-dollar hospital in Can Tho is stuck, who is responsible?

|

Can Tho - The Can Tho City Oncology Hospital project with a total capital of more than 1,700 billion VND has been stuck for many years and is still not completed, while the current Oncology Hospital is always crowded with patients.

Many abandoned headquarters in the heart of Bac Lieu city

NHẬT HỒ |

Bac Lieu - Newly formed headquarters, old headquarters abandoned, some places abandoned for more than 10 years without anyone looking.

Deputy Prime Minister shows how to remove obstacles for 4 abandoned projects in Nha Trang

Hữu Long |

Khanh Hoa - Deputy Prime Minister Ho Duc Phoc has suggested solutions to remove legal obstacles for 4 abandoned prime land projects in Nha Trang.

The fate of a dormitory worth over VND860 billion abandoned for 15 years

NGUYỄN TRƯỜNG |

Ninh Binh - The concentrated student dormitory project started construction in 2009, and up to now, after 15 years, this project is still unfinished and abandoned.