On March 25, the owner of a 3-storey house (on Hanoi Highway, in Binh Thang Ward, Di An City, Binh Duong Province) said that he was repairing the house. The house was tilted during the construction of the parallel road at Tan Van intersection under the Ho Chi Minh City Ring Road 3 project through Binh Duong province.
Previously, the house was about 100m2 wide, with 1 ground floor and 3 upper floors, and about 12m high. The house is in the area of land clearance to build Ho Chi Minh City Ring Road 3. The area of the houses to be recovered and cleared is about 2/3 of the houses.
Currently, the width of the remaining house is about 5m, the side of the house is about 1.5m long, the other side is about 4m long.
The owner of the house said that the house was affected during the construction of Ho Chi Minh City Ring Road 3. The remaining area of the house is currently due to the process of reducing the construction site of Ho Chi Minh City Ring Road 3.

Mr. Tran Hung Viet - Director of the Binh Duong Province Traffic Construction Investment Project Management Board (investor of the Ho Chi Minh City Ring Road 3 project through Binh Duong) - said that this 3-storey house has been compensated. However, the homeowner expanded it himself.
When the construction unit built a parallel road and dug deep, the house was tilted. The locality and the investor have handled it. The owner of the household no longer has to file a lawsuit and will handle it himself.
Currently, the investor and local authorities have advised people not to stay in the house to ensure safety.

It is known that in addition to the house above, many other households were also affected when constructing the roadbed to make drainage culverts for the project. People have to climb stairs 2-4m to get to their homes.
According to Mr. Tran Hung Viet - Director of the Traffic Construction Investment Project Management Board of Binh Duong province, the units are speeding up the construction progress here. Currently, sewers are being installed and the water pipes are being relocated. The units are trying to speed up the construction progress to restore the road surface. It is expected to be completed around April 10-15. After that, traffic was adjusted to move onto this parallel road to construct the overpass over National Highway 1.
Later, when the road surface is restored and sidewalks are built, the height difference between houses and the road surface will be reduced.
Striving to ensure the progress of Ho Chi Minh City Ring Road 3 through Binh Duong
It is known that Tan Van intersection is part of the construction package 1 of the Ho Chi Minh City Ring Road 3 project. Tan Van intersection has a budget of more than 1,831 billion VND. The estimated construction period is 1,050 days. The project started construction in April 2024.
Up to now, the site clearance progress has reached 99%, the total construction output has reached nearly 20%, the construction unit continues to coordinate with local authorities and households to receive the site and is speeding up the construction progress, in April and early May 2025, the relocation of technical infrastructure will be completed.
According to the People's Committee of Binh Duong province, along with construction packages 1 and 3, other construction packages of the Ho Chi Minh City Ring Road 3 project in Binh Duong are also being accelerated, striving to ensure progress and put the project into operation in 2026.