Reasons for 3-storey houses leaning when building Ho Chi Minh City Ring Road 3

ĐÌNH TRỌNG |

Binh Duong - The image of a "super thin" 3-storey house tilted attracted the attention of the people. This is a house affected during the construction of the Ho Chi Minh City Ring Road 3 project.

On March 25, the owner of a 3-storey house (on Hanoi Highway, in Binh Thang Ward, Di An City, Binh Duong Province) said that he was repairing the house. The house was tilted during the construction of the parallel road at Tan Van intersection under the Ho Chi Minh City Ring Road 3 project through Binh Duong province.

Previously, the house was about 100m2 wide, with 1 ground floor and 3 upper floors, and about 12m high. The house is in the area of land clearance to build Ho Chi Minh City Ring Road 3. The area of the houses to be recovered and cleared is about 2/3 of the houses.

Currently, the width of the remaining house is about 5m, the side of the house is about 1.5m long, the other side is about 4m long.

The owner of the house said that the house was affected during the construction of Ho Chi Minh City Ring Road 3. The remaining area of the house is currently due to the process of reducing the construction site of Ho Chi Minh City Ring Road 3.

Hay may muc phai chong do can nha. Anh: Dinh Trong
Two excavators had to support the house. Photo: Dinh Trong

Mr. Tran Hung Viet - Director of the Binh Duong Province Traffic Construction Investment Project Management Board (investor of the Ho Chi Minh City Ring Road 3 project through Binh Duong) - said that this 3-storey house has been compensated. However, the homeowner expanded it himself.

When the construction unit built a parallel road and dug deep, the house was tilted. The locality and the investor have handled it. The owner of the household no longer has to file a lawsuit and will handle it himself.

Currently, the investor and local authorities have advised people not to stay in the house to ensure safety.

Nhieu ho dan phai bac thang leo len nha. Anh: Nhu Quynh
Many households had to climb stairs to their houses. Photo: Nhu Quynh

It is known that in addition to the house above, many other households were also affected when constructing the roadbed to make drainage culverts for the project. People have to climb stairs 2-4m to get to their homes.

According to Mr. Tran Hung Viet - Director of the Traffic Construction Investment Project Management Board of Binh Duong province, the units are speeding up the construction progress here. Currently, sewers are being installed and the water pipes are being relocated. The units are trying to speed up the construction progress to restore the road surface. It is expected to be completed around April 10-15. After that, traffic was adjusted to move onto this parallel road to construct the overpass over National Highway 1.

Later, when the road surface is restored and sidewalks are built, the height difference between houses and the road surface will be reduced.

Nhieu ho dan phai dat thang de leo vao nha. Anh: Nhu Quynh
Many households had to set up ladders to climb into their houses. Photo: Nhu Quynh

Striving to ensure the progress of Ho Chi Minh City Ring Road 3 through Binh Duong

It is known that Tan Van intersection is part of the construction package 1 of the Ho Chi Minh City Ring Road 3 project. Tan Van intersection has a budget of more than 1,831 billion VND. The estimated construction period is 1,050 days. The project started construction in April 2024.

Up to now, the site clearance progress has reached 99%, the total construction output has reached nearly 20%, the construction unit continues to coordinate with local authorities and households to receive the site and is speeding up the construction progress, in April and early May 2025, the relocation of technical infrastructure will be completed.

According to the People's Committee of Binh Duong province, along with construction packages 1 and 3, other construction packages of the Ho Chi Minh City Ring Road 3 project in Binh Duong are also being accelerated, striving to ensure progress and put the project into operation in 2026.

ĐÌNH TRỌNG
RELATED NEWS

Lack of 6.3 million cubic meters of sand, Ho Chi Minh City Ring Road 3 is at risk of being behind schedule

|

The two sections of the Ho Chi Minh City Ring Road 3 project, over 21km long, are expected to open to traffic by the end of 2025, before the entire 76.34km route is completed on June 30, 2026. However, the construction progress is being hampered by a shortage of sand for embankment.

Image of the largest bridge on Ho Chi Minh City Ring Road 3 about to reach the finish line

|

Ho Chi Minh City - Nhon Trach Bridge, an important item on Ho Chi Minh City Ring Road 3, is about to close the final span on March 9 and is expected to open to traffic on April 30.

Ho Chi Minh City Ring Road 3 technical traffic opening through Long An in 2025

|

Long An - Strive to basically complete the expressway section of the Ho Chi Minh City Ring Road 3 project in October and will be completed and technically opened to traffic by December 31.

Disciplining former Chief of Office of Thua Thien Hue Provincial Party Committee related to the Provincial Party Committee Guesthouse Project

|

The Standing Committee of Hue City Party Committee disciplined Mr. Luu Duc Hoan with a reprimand for violations in leading and directing the implementation of the Provincial Party Committee Guest House Project.

Police inform about the case of a car driver not giving way to an ambulance in Tuyen Quang

|

Tuyen Quang - Functional agencies determined that the car driver had the act of not giving way to priority vehicles, with a fine of 6 - 8 million VND and 4 points off the driver's license.

Prolonging the term of Deputy Inspector General of the Government with Mr. Le Sy Bay

|

The Prime Minister decided to extend the term of office of Deputy Inspector General of the Government to the time of retirement according to regulations for Mr. Le Sy Bay.

Many people came to Le Thi Rieng Park to burn incense to commemorate heroic martyrs

|

Before the information that martyrs' remains are being gathered at Le Thi Rieng Park, Ho Chi Minh City, many people came to offer incense and express their respect to the spirits of the martyrs.

Proposal to support families with 2 daughters, young children may be subsidized up to 3 years old

|

The Ministry of Health proposed many new policies, including honoring families with 2 daughters, supporting tuition fees, health insurance for girls and allowances for children up to 3 years old.

Lack of 6.3 million cubic meters of sand, Ho Chi Minh City Ring Road 3 is at risk of being behind schedule

MINH QUÂN |

The two sections of the Ho Chi Minh City Ring Road 3 project, over 21km long, are expected to open to traffic by the end of 2025, before the entire 76.34km route is completed on June 30, 2026. However, the construction progress is being hampered by a shortage of sand for embankment.

Image of the largest bridge on Ho Chi Minh City Ring Road 3 about to reach the finish line

Anh Tú |

Ho Chi Minh City - Nhon Trach Bridge, an important item on Ho Chi Minh City Ring Road 3, is about to close the final span on March 9 and is expected to open to traffic on April 30.

Ho Chi Minh City Ring Road 3 technical traffic opening through Long An in 2025

Duy Minh |

Long An - Strive to basically complete the expressway section of the Ho Chi Minh City Ring Road 3 project in October and will be completed and technically opened to traffic by December 31.