Many problems in land acquisition and clearance work in Hoa Vang district, Da Nang city

Nguyễn Linh |

Da Nang - Many projects in Hoa Vang are still stuck in the process of site clearance due to many reasons.

In 2024, the People's Committee of Hoa Vang district assigned the Site Clearance Board to carry out site clearance for 19 projects. To date, 9 projects have completed 100% of site clearance, 7 projects have completed over 90% of site clearance, and 3 projects have completed over 60% of site clearance.

One of the reasons for the slow site clearance is due to the slow and inadequate investment preparation work such as slow consultation on land use planning and land use purpose change. The Hoa Vang District Project Management Board provided plots in many batches and the recovered land plot dossiers had many shortcomings such as incorrect determination of the recovered area, incorrect land use ownership, and failure to find the land user.

The land plot records need to be adjusted and reassigned to many land users and the waiting time for reassignment is very long. The decision to approve land prices for compensation calculation is still very slow, the compensation land price has not kept up with the market price, so most households propose low prices.

Compensation prices for houses, structures, and trees according to regulations are still low and inadequate but have not been adjusted. For urban roads implementing the policy of the state and the people working together, the people have not reached a high consensus because the compensation prices are low.

Last October, the People's Committee of Da Nang City issued a decision on detailed regulations on compensation, support and resettlement when the State reclaims land in Da Nang City. However, a number of projects have completed the work of approving compensation values ​​and handing over the site for over 60% of the clearance records.

In the same project, it is impossible to apply two compensation policies, which will lead to unfairness and affect the petitions of households who have handed over land in the same project. Therefore, the Land Clearance Board has reported to the District People's Committee to submit to the City People's Committee for approval to apply compensation policies for unfinished projects. Currently, Hoa Vang District is waiting for the City's approval to apply compensation for the remaining files.

Nguyễn Linh
TIN LIÊN QUAN

District in Da Nang strives to complete criteria for type IV urban area

|

In 2024, Hoa Vang district (Da Nang city) continues to strive to complete the criteria to achieve type IV urban status. However, urban infrastructure still faces many difficulties.

Da Nang determined to successfully pilot free trade zone

|

Da Nang's spirit is very determined, after the pilot is finished, it must be completed and successful with the free trade zone.

Da Nang aims for economic growth of over 10% by 2025

|

At the press conference on the morning of December 20, the People's Committee of Da Nang City announced the socio-economic development plan for 2025 with a target of GRDP growth of over 10%.

Many violations in handling investment procedures outside the budget

|

HUE - Hue City Inspectorate pointed out violations in handling procedures for non-budget investment projects in the area.

Temperatures drop sharply, earthquake rescue in China faces difficulties

|

Rescue teams in the earthquake in Tibet (China) encountered many difficulties in searching for missing people because the temperature dropped below 0 degrees Celsius.

Kumquats hit the streets early, prices higher than every year due to scarcity

|

According to records, many streets in Hanoi have been selling ornamental plants such as peach, kumquat,... to serve the 2025 Lunar New Year.

Cao Bang provincial leaders ask to postpone inspection to prepare for Tet

|

Cao Bang provincial leaders requested the Government Inspectorate to postpone the direct inspection time to prepare for Lunar New Year.

Ho Chi Minh City residents take Metro Line 1 with "1-touch" operation

|

HCMC - After more than 2 weeks of Metro Line 1 being put into operation, the number of passengers has become more stable, and people have become familiar with using QR Codes to scan when entering and exiting the gate.

District in Da Nang strives to complete criteria for type IV urban area

Nguyễn Linh |

In 2024, Hoa Vang district (Da Nang city) continues to strive to complete the criteria to achieve type IV urban status. However, urban infrastructure still faces many difficulties.

Da Nang determined to successfully pilot free trade zone

Nguyễn Linh |

Da Nang's spirit is very determined, after the pilot is finished, it must be completed and successful with the free trade zone.

Da Nang aims for economic growth of over 10% by 2025

An Thượng |

At the press conference on the morning of December 20, the People's Committee of Da Nang City announced the socio-economic development plan for 2025 with a target of GRDP growth of over 10%.