Projects in Can Tho are proposed to prioritize capital allocation

Tạ Quang |

Can Tho - The Western Ring Road Project, Provincial Road 917, 918, and National Highway 91 are being implemented very slowly, so it is being proposed to pay attention to prioritizing capital allocation.

On April 29, the People's Committee of Can Tho City issued an official dispatch on resolving voters' petitions before the 9th Session of the 15th National Assembly.

In the document, Chairman of Can Tho City People's Committee Truong Canh Tuyen requested the City Construction Investment Project Management Board to urgently complete the Tay Do Cultural Center project, pay attention to promptly implementing support, compensation and resettlement policies for the people, because this project has been delayed for too long, affecting the lives of local people.

Quoc lo 91 tai Km7 thuoc dia ban TP Can Tho. Anh: Ta Quang
National Highway 91 at Km7 in Can Tho City. Photo: Ta Quang

For the Western Ring Road Project, National Highway 91 (Km0 - Km7), Provincial Road 917, 918 with very slow implementation progress, the Chairman of the People's Committee of Can Tho City suggested paying attention to and finding solutions to overcome the causes, so that these projects can be completed to ensure the planned progress, contributing to creating more momentum to promote the socio-economic development of the city.

As for Nguyen Chi Thanh Street (connecting National Highway 91 to National Highway 91B), about 5km long, which has not been upgraded and expanded synchronously, the Chairman of the People's Committee of Can Tho City proposed to invest in implementing and installing a synchronous drainage system to ensure safety for people's travel on this route.

The Chairman of the People's Committee of Can Tho City said that the implementation progress of the Western Ring Road, Provincial Road 917, 918, National Highway 91 (Km0 - Km7) is very slow due to lack of capital, therefore, the Department of Finance is interested in prioritizing capital allocation.

Mot vi tri cua Duong tinh 918 thi cong dang do. Anh: Ta Quang
A location of Provincial Road 918 is under construction. Photo: Ta Quang

The Department of Home Affairs is interested in having specific and accurate orientations on vocational training in accordance with the requirements of businesses in newly opened industrial parks in Vinh Thanh district, so that voters who are laborers in Vinh Thanh district and neighboring localities have the opportunity to learn a trade and have jobs when the Vinh Thanh industrial parks in phase 1 and phase 2 come into operation.

The Department of Agriculture and Environment has continued to invest in the construction of road linkages at some locations that have not been implemented on the Cai San River (section belonging to Thanh My Commune, Vinh Thanh District), to ensure safety for people living along this river.

Tạ Quang
TIN LIÊN QUAN

Expressway and Can Tho's expectations

|

Can Tho - The completion and operation of expressway axes will give Can Tho City a great growth momentum, promoting all fields evenly.

Working headquarters of 32 communes and wards of Can Tho after the merger

|

Can Tho - The working headquarters of the commune and ward after the arrangement and merger has some changes. Readers can see the information below.

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

|

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.

Song Lam Nghe An invites police to investigate the referee

|

Song Lam Nghe An sent a document requesting the Criminal Police Department C02 - Ministry of Public Security to investigate unusual signs related to arbitration.

Canceling the first prize of the national science and technology competition accused of copying

|

The Ministry of Education and Training cancels and revokes the National Science and Technology Award for students after information reflecting " foreign product variety".

Airports and bus stations in Hanoi are crowded before the April 30 - May 1 holiday

|

On the afternoon of April 29, the number of passengers flocking to Hanoi bus stations increased sharply. The aviation, rail and passenger transport sectors have increased trips and service frequency.

Submitting to the Government the Bac Ninh - Bac Giang merger project before the prescribed time

|

Bac Giang - The project to merge Bac Ninh province and Bac Giang province to establish Bac Ninh province was submitted to the Government on April 28.

U80 veteran travels 1,300 km by motorbike to Ho Chi Minh City to watch a parade

|

HCMC - The 76-year-old veteran traveled 1,300 km by motorbike to HCMC to attend the parade to celebrate the 50th anniversary of the Liberation of the South and National Reunification.

Expressway and Can Tho's expectations

Tạ Quang |

Can Tho - The completion and operation of expressway axes will give Can Tho City a great growth momentum, promoting all fields evenly.

Working headquarters of 32 communes and wards of Can Tho after the merger

Phong Linh |

Can Tho - The working headquarters of the commune and ward after the arrangement and merger has some changes. Readers can see the information below.

Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30

Tạ Quang |

Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.