The main artery intersection at the gateway to Ho Chi Minh City urgently races towards the finish line

Tâm Tú |

Tay Ninh - My Yen intersection connecting 3 key expressways is focusing on construction, sprinting to open the technical traffic on December 19.

At the My Yen intersection construction site, the intersection of 3 key traffic axes including Ho Chi Minh City Ring Road 3, Ben Luc - Long Thanh Expressway and Ho Chi Minh City - Trung Luong, a series of construction teams are focusing all their efforts to work "all night". The goal is to bring the project to technical traffic on time on December 19.

  Khu vuc nut giao My Yen da hoan thanh phan cau, duong va tham nhua tuyen chinh, dat tien do hon 87%. Ảnh: Anh Tu
The My Yen intersection has completed the bridge, road and asphalt section of the main route, reaching a progress of more than 87%. Photo: Anh Tu

Currently, the shape of this large-scale intersection has been clearly revealed. According to the Project Management Board, the workload of the entire intersection has reached about 87%. To meet the December 19 progress milestone, contractors are making the most of favorable weather, mobilizing total human resources and machinery to complete the final meters of asphalt pavement.

In the area of the arch-shaped bridge branch connecting Ring Road 3 to Ben Luc - Long Thanh Expressway, the rough part such as the bridge piers and concrete surface has been completed. The working groups are taking turns continuously to install railing and lighting systems and complete auxiliary items.

Hang loat phuong tien may moc cung tat bat thi cong. Ảnh: Anh Tu
A series of machines and vehicles are busy constructing. Photo: Anh Tu
Cac nhanh duong dan quay dau va nhap ve cao toc TPHCM - Trung Luong dang duoc nha thau thi cong tham nhua chieu 13/12.
The branches of the approach roads turning around and merging into the Ho Chi Minh City - Trung Luong Expressway are being paved by the contractor. Photo: Anh Tu
Cau vuot quay dau tren tuyen Vanh dai 3 TP.HCM da hoan thanh phan lan can, he thong chieu sang va dang duoc tham nhua.
The overpass on Ho Chi Minh City Ring Road 3 has completed the railing, lighting system and is being paved with asphalt. Photo: Anh Tu
He thong bien bao cung dang duoc tien hanh lap dat tai doan giao voi cao toc TPHCM - Trung Luong. Ảnh: Anh Tu
The sign system is also being installed at the intersection with the Ho Chi Minh City - Trung Luong Expressway. Photo: Anh Tu

Right below the overpass of the Ho Chi Minh City - Trung Luong Expressway, the main section of Ring Road 3 hundreds of meters long is being paved continuously by wheelchairs and road users.

About 500 m from the central intersection, the bridge and Ring Road 3 parallel road system is also gradually reaching the finish line. Tan Buu overpass and the parallel bridge branch across Cho Dem river have completed the concrete bridge surface. Traffic safety items such as directional signs and road markings are being urgently installed at intersections.

Cau vuot Tan Buu va nhanh song hanh qua song Cho Dem da hoan thien phan tho, xong lop betong mat cau. Ảnh: Anh Tu
Tan Buu overpass and the parallel branch across Cho Dem river have completed the rough construction and completed the concrete layer on the bridge surface. Photo: Anh Tu

According to the plan, on December 19, My Yen intersection will be technically open to traffic. The traffic organization plan is expected to allow cars from the Ho Chi Minh City - Trung Luong Expressway to move down to the My Yen intersection to connect to Nguyen Huu Tri Street and vice versa.

At the same time, the section connecting Ring Road 3 and Ben Luc - Long Thanh Expressway (the section passing through the toll station at the end of the route) is also ready for vehicles to run.

O diem cuoi cao toc Ben Luc - Long Thanh giao voi Vanh dai 3 TPHCM la khu vuc dat tram thu phi, doan nay da cho xe chay. Ảnh: Anh Tu
At the end of the Ben Luc - Long Thanh Expressway intersecting with Ho Chi Minh City Ring Road 3, there is a toll station, this section has been opened to traffic. Photo: Anh Tu

The Ho Chi Minh City Ring Road 3 project has a total length of more than 76 km, passing through Ho Chi Minh City, Dong Nai, Tay Ninh with a total investment of more than VND 75,300 billion. Meanwhile, the Ben Luc - Long Thanh Expressway is over 57 km long, with an investment capital of over VND31,000 billion.

The completion and operation of the My Yen intersection not only has significance in terms of progress but also creates strategic regional linkages. When put into synchronous operation, this "super intersection" will close the traffic axis surrounding Ho Chi Minh City, reduce the pressure of vehicles running through the inner city, shorten travel time and logistics costs between the West and Southeast, creating momentum for a breakthrough for the Southern Key Economic Zone.

Tâm Tú
RELATED NEWS

Workers are busy constructing Tan Van intersection, speeding up the progress of Ring Road 3

|

HCMC - The largest scale of the Tan Van intersection of the Ho Chi Minh City Ring Road 3 project is under urgent construction, striving to complete by 2026.

HCMC today: Duyet of the 3,000 billion VND intersection project in the South

|

Ho Chi Minh City approves the intersection project worth nearly VND3,000 billion, the largest in the South; Inauguration of a park worth over VND1,000 billion in Vung Tau on December 19...

HCMC approves the intersection project worth nearly VND3,000 billion, the largest in the South

|

Ho Chi Minh City spends nearly VND3,000 billion to build an intersection connecting Ben Luc - Long Thanh Expressway with Rung Sac Road, opening more connecting directions for Can Gio.

Nguyen Thi Oanh equalizes a record of 15 gold medals in SEA Games athletics

|

The victory in the 3,000m final overcoming obstacles helped Nguyen Thi Oanh equal the record of 15 gold medals in the SEA Games athletics.

Updated gold price at the end of the session on December 16: Deep decrease of 1.6 million VND/tael

|

Updated gold price at the end of the session on December 16: Domestic and world gold both decreased in today's trading session.

Police exposed the tricks of drivers to avoid AI cameras

|

Hanoi - Many drivers use all kinds of methods to cover and blur their license plates to bypass the AI camera.

Accelerating site clearance, Ring Road 1 gradually emerges

|

Hanoi - The site clearance of Ring Road 1 from Hoang Cau to Voi Phuc is in the acceleration phase, with continuous machinery and openings.

Explaineration of the principal for the case of " blocking" A80 money before being arrested

|

Before being arrested for allegedly having violations related to paying money to students on the occasion of A80, the Principal of Hanoi College of Tourism affirmed that this was just a " misunderstanding".

Workers are busy constructing Tan Van intersection, speeding up the progress of Ring Road 3

NHƯ QUỲNH - ANH TÚ |

HCMC - The largest scale of the Tan Van intersection of the Ho Chi Minh City Ring Road 3 project is under urgent construction, striving to complete by 2026.

HCMC today: Duyet of the 3,000 billion VND intersection project in the South

Nguyên Chân |

Ho Chi Minh City approves the intersection project worth nearly VND3,000 billion, the largest in the South; Inauguration of a park worth over VND1,000 billion in Vung Tau on December 19...

HCMC approves the intersection project worth nearly VND3,000 billion, the largest in the South

MINH QUÂN |

Ho Chi Minh City spends nearly VND3,000 billion to build an intersection connecting Ben Luc - Long Thanh Expressway with Rung Sac Road, opening more connecting directions for Can Gio.