Bottleneck at 2 expressway projects through Lang Son and Cao Bang

Khánh Linh |

Lang Son - The Huu Nghi - Chi Lang and Dong Dang - Tra Linh expressway projects are racing to make efforts to open the route in 2025.

In the picture of strategic infrastructure development in the Northeast region, the two expressway projects Dong Dang - Tra Linh and Huu Nghi - Chi Lang are considered new transportation "blood vessels", carrying the mission of connecting international border gates, expanding development space, strengthening regional linkages and promoting border trade.

However, on the field, both projects are facing many obstacles, especially in the stage of site clearance and relocation of technical infrastructure - "bottlenecks" that need to be removed.

According to the report, phase 1 of the Dong Dang - Tra Linh expressway project is over 93 km long, with a total investment of nearly VND14,114 billion.

Binh do tuyen cao toc Dong Dang - Tra Linh va 2 du an ket noi. Anh: Vu Khuyen
Chart of the Dong Dang - Tra Linh Expressway and 2 connecting projects. Photo: Vu Khuyen

Up to now, 70 construction teams have been deployed along the entire route, mobilizing more than 2,000 personnel and nearly 1,000 equipment and machinery. The output value reached about VND2,334 billion, equivalent to 22.3% of the contract value.

According to the reporter's research, although the construction speed has changed, the delay in handing over the site at many key locations is hindering the implementation pace.

In Lang Son province, only 387/458 hectares have been handed over, reaching 84.5%, with 87 households not yet relocated. Cao Bang province has reached a rate of 88%, but there are still 85 households that have not handed over their houses and residential land.

In particular, about 158 households in Thach An and Quang Hoa districts are lacking resettlement land, causing prolonged stagnation.

Tuyen cao toc Dong Dang - Tra Linh qua dia ban huyen Van Lang, tinh Lang Son. Anh: Khanh Linh
The Dong Dang - Tra Linh Expressway passes through Van Lang District, Lang Son Province. Photo: Khanh Linh

At the same time, with a length of 43 km and a total investment of more than VND 11,000 billion, the Huu Nghi - Chi Lang project is expected to complete the "last link" in the expressway corridor axis connecting Lang Son - Hanoi.

However, the construction progress to date has only reached 11.66% of the contract value.

Although contractors have increased 239 personnel and 226 equipment since March 2025 and added 5 construction teams, the construction site still does not have a seamless site.

The entire route has 497 households that had to be relocated, but only 81 households have handed over the site. Hundreds of technical infrastructure works such as high-voltage power poles, telecommunication lines, and railway signals have not been relocated.

Nhung ngoi nha giua duong tai tuyen cao toc Huu Nghi - Chi Lang. Anh: Khanh Linh
Houses in the middle of the road on the Huu Nghi - Chi Lang expressway. Photo: Khanh Linh

One of the major problems at present is the phenomenon of " sticky rice and bean" construction.

According to statistics, in the entire Lang Son area, there are up to 828 locations of power projects that have not been relocated, including the 110kV power pole.

Telecommunications infrastructure, water roads, railway signals... are also waiting to be resolved.

Mr. Vu Xuan Huy - Director of the Executive Board of DCT 559 Investment Joint Stock Company - a construction contractor shared: "We have mobilized over 140 vehicles, machinery, equipment of all kinds and over 400 engineers and construction workers on the construction site, taking advantage of favorable weather to construct on the route. However, the "sticky rice and bean" site has greatly affected the construction implementation".

Many sections of the route cannot implement bridge piles, bored piles, box culverts, and underpasses, causing the construction site to be cut off, reducing the effectiveness of synchronous construction.

Both of these projects are on the list of national key projects, of special interest to the Prime Minister, requesting the completion of site clearance in March 2025. However, in reality, the site clearance has not been completed.

Cac tuyen cao toc da, dang va se trien khai tai phia Bac. Anh: DVCC
Expressways have been, are and will be deployed in the North. Photo: DVCC

Mr. Do Minh Tuan - Vice Chairman of Van Lang District People's Committee said that currently, the entire political system is making efforts to participate day and night in site clearance work to hand over clean land to the project.

According to Mr. Tuan, authorities at all levels have mobilized people to temporarily stay in temporary houses to hand over the site. Investors also affirmed their readiness to increase construction teams, machinery, and human resources as soon as the site is clear.

However, to achieve the goal of opening the route, it is necessary to have a clear plan with specific handover milestones, avoiding the situation of waiting for the line and slow construction.

Khánh Linh
TIN LIÊN QUAN

New information about the Cho Moi - Bac Kan expressway project

|

The Ministry of Construction has just responded to voters about the Cho Moi - Bac Kan expressway project.

The Ring Road 3 intersection with Ho Chi Minh City - Long Thanh Expressway is revealed

|

The Ring Road 3 intersection with Ho Chi Minh City - Long Thanh - Dau Giay Expressway is being urgently completed to connect with Nhon Trach Bridge - expected to be technically open to traffic on April 30, 2025.

Cao Bang speeds up resettlement for people affected by highways

|

Cao Bang - After more than 1 year of implementation, the shape of the Dong Dang - Tra Linh expressway has gradually taken shape.

Special notice on the funeral of comrade Khamtay Siphandone

|

Vietnam will hold a funeral for comrade Khamtay Siphandone according to the National Funeral Rites for 2 days, from April 4 to 5, 2025.

HCMC installs 20 LED screens for people to watch the parade on the morning of April 30

|

Ho Chi Minh City has installed 20 LED screens on major roads in the central area for people and tourists to directly watch the parade and parade to celebrate the 50th anniversary of the country's reunification.

Restaurant fire in Hanoi

|

Hanoi - The fire that broke out at a restaurant in Nam Tu Liem district late in the afternoon of April 3, 2025 caused panic among people.

The death anniversary of Hung Vuong's great monk in Phu Tho is a grand festival

|

Phu Tho - The Hung Temple historical relic site is being decorated with many colors from the cultural funds of 13 districts, cities and towns in the area.

Lam Dong reforms to become an attractive destination for investors

|

Lam Dong - The locality is committed to strongly reforming administrative procedures, aiming to make the province an attractive destination for investors.

New information about the Cho Moi - Bac Kan expressway project

Xuyên Đông |

The Ministry of Construction has just responded to voters about the Cho Moi - Bac Kan expressway project.

The Ring Road 3 intersection with Ho Chi Minh City - Long Thanh Expressway is revealed

MINH QUÂN |

The Ring Road 3 intersection with Ho Chi Minh City - Long Thanh - Dau Giay Expressway is being urgently completed to connect with Nhon Trach Bridge - expected to be technically open to traffic on April 30, 2025.

Cao Bang speeds up resettlement for people affected by highways

Tân Văn |

Cao Bang - After more than 1 year of implementation, the shape of the Dong Dang - Tra Linh expressway has gradually taken shape.