Cao Bang speeds up resettlement for people affected by highways

Tân Văn |

Cao Bang - After more than 1 year of implementation, the shape of the Dong Dang - Tra Linh expressway has gradually taken shape.

According to the latest report of the Cao Bang Province Traffic Construction Investment Project Management Board, the total area of land to be recovered according to the technical design documents approved by the project enterprise is 813.48 hectares.

Of which, Cao Bang province needs to reclaim 260.76ha, has implemented 248.87ha, reaching 95.04%. Lang Son province needs to reclaim 361.13 hectares, implement 354.5 hectares, reaching 98.16%.

As of March 27, Cao Bang province has handed over the clean site according to the technical design documents of 323.66 hectares, reaching 88.07%.

Toan canh khu tai dinh cu tai thi tran Dong Khe (huyen Thach An). Anh: Tan Van.
Panorama of the resettlement area in Dong Khe town (Thach An district). Photo: Tan Van

Regarding site clearance according to technical design documents, Thach An district has completed the counting, prepared a compensation plan and estimate.

It is expected that the payment of compensation to the people will be completed in March 2025. The district has relocated 58/105 households.

Quang Hoa district has also completed the counting, appraised the compensation plan and is in the process of approving it. It is expected that the compensation payment will be completed in March 2025. The district has relocated 48/86 households.

Nhung lo dat lien ke da san sang xay dung. Anh: Tan Van.
Adjacent plots of land are ready for construction. Photo: Tan Van

A very important thing is the resettlement of households with affected houses that many people are interested in.

In Thach An district, the locality plans to arrange accommodation for 105 households, of which 63 households registered for concentrated resettlement and 42 households were scattered.

On April 1, according to the actual records of the reporter, the resettlement area in Dong Khe town has been basically completed, the connecting routes in the area, lighting and construction site are ready. In this resettlement area, 45 households have drawn lots to receive land.

Mot lo dat trong khu tai dinh cu da duoc ban giao. Anh: Tan Van.
A plot of land in the resettlement area has been handed over. Photo: Tan Van

In Quang Hoa district, resettlement area D in Hoa Thuan town has completed more than 90% of the work volume, the site is ready for handover. Households were introduced to the site, scale and technical infrastructure of the resettlement area.

Mr. Nong Van Hoat (Dong Khe town) shared: "This resettlement area was built last year, and now there are a few households building houses to live in. The government also had to do it quickly so that people could still live there, but the old houses had to be demolished to build a highway".

Cac doan tuyen cao toc dang dan hinh thanh. Anh: Tan Van.
The expressway sections are gradually taking shape. Photo: Tan Van

Recently, in the project inspection on March 28, Chairman of Cao Bang Provincial People's Committee Hoang Xuan Anh requested departments, branches, and sectors, especially Thach An and Quang Hoa districts, to flexibly, creatively and synchronously apply many solutions to soon hand over the site to project enterprises.

The Provincial Traffic Construction Investment Project Management Board and the construction unit will coordinate with the districts to measure and count, speeding up the relocation of technical infrastructure for the power line to be completed before April 30.

Close-up of the resettlement area.
Tân Văn
TIN LIÊN QUAN

Dong Dang - Tra Linh Expressway affects 31 hectares of forest

|

Cao Bang - The Provincial People's Council has just approved a proposal to convert the purpose of using 31 hectares of forest for the Dong Dang - Tra Linh Expressway.

Difficulties at the Dong Dang - Tra Linh Expressway project

|

Cao Bang - The construction of the Dong Dang - Tra Linh expressway is facing some difficulties in site clearance.

Latest progress of the Dong Dang - Tra Linh expressway project

|

Cao Bang - The Chairman of the Provincial People's Committee set a time frame for completing the site clearance of the first expressway through the area.

Squeezing billions to build resettlement areas, people are still not interested

|

Lang Son - People are still not interested in the resettlement areas of the Dong Dang - Tra Linh expressway project despite spending tens of billions of VND to invest.

Requirements for export restructuring before the new US tax rate

|

In the context of the global economy continuing to have many potential uncertainties, restructuring export activities is no longer an option, but has become an urgent requirement.

The hardship after the salary of 10-15 million VND/month of workers

|

Behind the high salary of over 10 million - 15 million VND/month, many workers have to trade it for a lot of time and health.

Proposal to consider early retirement policies for officials in disadvantaged areas

|

Lam Dong - Officials who have worked for more than 15 years in disadvantaged areas will be allowed to retire earlier but will not receive benefits commensurate with those in other areas.

A resident's house in Da Lat caught fire fiercely at night

|

Lam Dong - The fire broke out and burst fiercely at a house in Da Lat city. Those present tried to put out the fire, but failed.

Dong Dang - Tra Linh Expressway affects 31 hectares of forest

Tân Văn |

Cao Bang - The Provincial People's Council has just approved a proposal to convert the purpose of using 31 hectares of forest for the Dong Dang - Tra Linh Expressway.

Difficulties at the Dong Dang - Tra Linh Expressway project

Tân Văn |

Cao Bang - The construction of the Dong Dang - Tra Linh expressway is facing some difficulties in site clearance.

Latest progress of the Dong Dang - Tra Linh expressway project

Tân Văn |

Cao Bang - The Chairman of the Provincial People's Committee set a time frame for completing the site clearance of the first expressway through the area.