Breaking the Da Lam dike in Quang Binh to proactively drain floodwaters for the dam

CÔNG SÁNG |

Quang Binh - Director of the Department of Agriculture and Environment's Construction Investment Project Management Board said that breaking the Da Lam dike is a proactive solution for the dam.

Regarding the Da Lam dam break that occurred on the morning of June 13 in Thai Thuy commune (Le Thuy district, Quang Binh province), Director of the Department of Agriculture and Environment Investment and Construction Project Management Board Dinh Khanh Hau said that this was not an unexpected incident but a proactive response measure in the context of prolonged extreme floods.

Mr. Hau informed that the Da Lam Reservoir Upgrade Project is invested by the Quang Binh Provincial Agricultural and Environmental Construction Investment Project Management Board, approved by the Provincial People's Committee in Decision No. 59/QD-UBND dated January 10, 2025, and started construction on February 26, 2025. At the time of the incident, the project was constructing important items such as reinforcing the downstream roof of the main dam, building a new spillway and a drainage culvert.

From the evening of June 11 to noon of June 13, Thai Thuy commune recorded 466mm of rain. Prolonged heavy rain caused a large amount of water to flow into the lake.

In that situation, from 4:00 a.m. on June 13, the construction unit proactively dug a flood drainage ditch on the right side of the dam.

However, the lake's water level rises too quickly, if the dike is not demolished to proactively drain the flood, the dike will break, greatly affecting the dam safety.

By 9:00 a.m. the same day, the Project Management Board had directed the demolition of the dike and items serving the construction of the water drainage culvert, to proactively release floodwater, lower the lake water level, and ensure safety for the main dam and the entire project.

The Project Management Board has reported to the People's Committee of Thai Thuy Commune and the People's Committee of Le Thuy District and requested to notify the people of the downstream villages about the situation to deploy appropriate response plans to minimize damage.

As reported by Lao Dong Newspaper, on the morning of June 13, the broken section in Da Lam dam was about 15m long, causing water from the reservoir to overflow strongly to lower communes. Da Lam Dam has a capacity of about 500,000m3.

CÔNG SÁNG
TIN LIÊN QUAN

Dam failure causes rice flooding, water floods into people's gardens

|

Ha Tinh - Heavy rain, Ha dam in Quy Hai village (Thach Ngoc commune, Thach Ha district) broke, causing flooding of many hectares of rice fields, water flooded into people's gardens.

People return to farming after the sludge dam burst in Bac Kan

|

Bac Kan - After 3 months since the sludge dam collapse in Ban Thi commune, hundreds of affected households have gradually stabilized their lives.

Completion of compensation payment after dam failure in Bac Kan

|

Bac Kan - The sludge dam collapse in Ban Thi commune (Cho Don district) has caused widespread impacts. Related units are still dealing with the incident and paying compensation.

Fined 150 million VND, a company asks to pay gradually due to difficulties

|

Thanh Hoa - Although there has been a decision to sanction administrative violations, Lang Chanh Forestry Company has not yet paid the fine, due to financial difficulties.

Strictly manage the short-term apartment rental model instead of absolutely banning

|

HCMC - According to experts, it is necessary to soon complete the legal framework to manage and develop short-term apartment rental activities instead of absolutely banning them.

Vietnam women's volleyball team promoted to 27th place in the world

|

The victory over Kazakhstan at the AVC Nations Cup 2025 helped the Vietnamese women's volleyball team rise to 27th place in the world.

Putting the provincial and commune-level apparatus after the merger into operation nationwide from July 1

|

The Politburo and the Secretariat request to ensure readiness to put the provincial and commune-level apparatus into operation from July 1, 2025.

Reasons for proposing to abolish the death penalty for the crimes of Embezzlement and Receiving Bribes

|

National Assembly delegate Nguyen Cong Long said that narrowing the death penalty does not mean that the law becomes weak.

Dam failure causes rice flooding, water floods into people's gardens

TRẦN TUẤN |

Ha Tinh - Heavy rain, Ha dam in Quy Hai village (Thach Ngoc commune, Thach Ha district) broke, causing flooding of many hectares of rice fields, water flooded into people's gardens.

People return to farming after the sludge dam burst in Bac Kan

Lam Thanh |

Bac Kan - After 3 months since the sludge dam collapse in Ban Thi commune, hundreds of affected households have gradually stabilized their lives.

Completion of compensation payment after dam failure in Bac Kan

Lam Thanh |

Bac Kan - The sludge dam collapse in Ban Thi commune (Cho Don district) has caused widespread impacts. Related units are still dealing with the incident and paying compensation.