Quang Ngai focuses on solving difficulties for the VND 20,400 billion expressway project

VIÊN NGUYỄN |

Quang Ngai is making efforts to solve difficulties to speed up the progress of the Quang Ngai - Hoai Nhon expressway project, with a total investment of more than 20,400 billion VND.

The Quang Ngai - Hoai Nhon Expressway has a total investment of more than VND 20,400 billion; the total length is more than 88 km, of which the section through Quang Ngai is more than 60.3 km long. The project started on January 1, 2023; completion time is in 2025. Over the past 2 years, Quang Ngai has actively carried out tasks related to the implementation of the construction of the Quang Ngai - Hoai Nhon expressway. However, the project is still facing problems with site clearance, waste dumps, and material mines.

According to the investor's report, the problematic locations according to the main route construction contractor's recommendation have so far been resolved for 11/16 locations, the remaining 5 locations are not yet completed. The total area of adjusted and supplemented land clearance deposits that have been handed over to date is more than 24 hectares. The compensation plan for about 4 hectares has been approved; the remaining 20 hectares have not been approved because the additional area is not in accordance with the district-level land use planning and problems related to specific land prices.

Ham cao toc Quang Ngai - Hoai Nhon. Anh: Vien Nguyen.
Quang Ngai - Hoai Nhon Expressway tunnel. Photo: Vien Nguyen.

The total volume of land for filling materials according to the project's requirements is more than 10 million m3. Currently, the volume at the mines granted to contractors is more than 7.8 million m3, the expected volume to be purchased at commercial mines on the list of mines serving the expressway project is more than 1.1 million m3. The total volume of sand for common construction materials needed to serve the project is about 910,000 m3.

According to Mr. Tran Phuoc Hien - Vice Chairman of the People's Committee of Quang Ngai province, the provincial leaders have directed departments, branches, sectors and local authorities to coordinate with investors to urgently resolve problems, create the best conditions for construction units, and ensure the progress of the project. Compensation organizations must strictly and fully implement their responsibilities according to regulations, focus and prioritize resources to speed up the implementation progress to ensure the progress of completing the approval of compensation plans as soon as possible.

Project Management Board 2 directs contractors to proactively contact local authorities at the commune level to promptly coordinate in mobilizing and propagating households whose land is recovered to agree on handing over the site to organize construction implementation within the time limit for completing procedures for approving compensation plans.

VIÊN NGUYỄN
TIN LIÊN QUAN

Flexibility in construction of Quang Ngai - Hoai Nhon expressway

|

Quang Ngai - Hoai Nhon Expressway mobilizes maximum human resources and construction equipment even during the rainy season to ensure project progress and quality.

Football prediction PSG vs Chelsea in the FIFA Club World Cup 2025 final

|

In Sports Perspective No. 223, commentator Quang Tung commented on the FIFA Club World Cup final between PSG and Chelsea.

A plane carrying 300 people urgently landed on a strange island, stranded in the middle of the ocean

|

The US plane carrying nearly 300 people made an emergency landing in the middle of the ocean, stranded for more than 31 hours on a strange island.

The journey to turn Ponagar Tower into a special national monument

|

Khanh Hoa - The Government has recognized Ponagar Tower as a special national monument.

The plan to move "abandoned" aircraft in Noi Bai to Khanh Hoa will cost about 8.7 billion VND

|

The plane abandoned in Noi Bai is valued at more than 1.7 billion VND. If this aircraft is transferred to Khanh Hoa, Dong Nai will lose from 8.7 - 9.6 billion VND.

Research on Vietnamese people playing casino after the pilot period

|

The Deputy Prime Minister requested to study special policies for the development of Phu Quoc Special Zone, allowing Vietnamese people to play casino after the pilot period.

Thanh Hoa assigns tasks after Vice Chairman of the Provincial People's Committee Le Duc Giang was prosecuted

|

After the Ministry of Public Security prosecuted Vice Chairman of the Provincial People's Committee Le Duc Giang and many related officials, the Thanh Hoa Provincial People's Committee urgently re-assigned tasks.

Requesting 3 units to report the 208,000 VND bread case at Noi Bai airport before July 11

|

The Civil Aviation Authority of Vietnam has just requested units to report the 208,000 VND banh mi case at Noi Bai airport before July 11.

Flexibility in construction of Quang Ngai - Hoai Nhon expressway

VIÊN NGUYỄN |

Quang Ngai - Hoai Nhon Expressway mobilizes maximum human resources and construction equipment even during the rainy season to ensure project progress and quality.

Làm chủ công nghệ xây hầm cao tốc Quảng Ngãi – Hoài Nhơn

VIÊN NGUYỄN |

Đơn vị thi công cao tốc Quảng Ngãi – Hoài Nhơn đã cải tiến công nghệ thi công hầm nhằm rút ngắn tiến độ hoàn thành.

Cao tốc Quảng Ngãi - Hoài Nhơn tăng tốc ngay cả trong dịp lễ

VIÊN NGUYỄN |

Kỳ nghỉ lễ Quốc khánh 2.9 kéo dài 4 ngày. Tuy nhiên, hàng nghìn kỹ sư, công nhân vẫn miệt mài làm việc xuyên lễ trên cao tốc Quảng Ngãi - Hoài Nhơn.