Quang Ngai focuses on solving difficulties for the VND 20,400 billion expressway project

VIÊN NGUYỄN |

Quang Ngai is making efforts to solve difficulties to speed up the progress of the Quang Ngai - Hoai Nhon expressway project, with a total investment of more than 20,400 billion VND.

The Quang Ngai - Hoai Nhon Expressway has a total investment of more than VND 20,400 billion; the total length is more than 88 km, of which the section through Quang Ngai is more than 60.3 km long. The project started on January 1, 2023; completion time is in 2025. Over the past 2 years, Quang Ngai has actively carried out tasks related to the implementation of the construction of the Quang Ngai - Hoai Nhon expressway. However, the project is still facing problems with site clearance, waste dumps, and material mines.

According to the investor's report, the problematic locations according to the main route construction contractor's recommendation have so far been resolved for 11/16 locations, the remaining 5 locations are not yet completed. The total area of adjusted and supplemented land clearance deposits that have been handed over to date is more than 24 hectares. The compensation plan for about 4 hectares has been approved; the remaining 20 hectares have not been approved because the additional area is not in accordance with the district-level land use planning and problems related to specific land prices.

Ham cao toc Quang Ngai - Hoai Nhon. Anh: Vien Nguyen.
Quang Ngai - Hoai Nhon Expressway tunnel. Photo: Vien Nguyen.

The total volume of land for filling materials according to the project's requirements is more than 10 million m3. Currently, the volume at the mines granted to contractors is more than 7.8 million m3, the expected volume to be purchased at commercial mines on the list of mines serving the expressway project is more than 1.1 million m3. The total volume of sand for common construction materials needed to serve the project is about 910,000 m3.

According to Mr. Tran Phuoc Hien - Vice Chairman of the People's Committee of Quang Ngai province, the provincial leaders have directed departments, branches, sectors and local authorities to coordinate with investors to urgently resolve problems, create the best conditions for construction units, and ensure the progress of the project. Compensation organizations must strictly and fully implement their responsibilities according to regulations, focus and prioritize resources to speed up the implementation progress to ensure the progress of completing the approval of compensation plans as soon as possible.

Project Management Board 2 directs contractors to proactively contact local authorities at the commune level to promptly coordinate in mobilizing and propagating households whose land is recovered to agree on handing over the site to organize construction implementation within the time limit for completing procedures for approving compensation plans.

VIÊN NGUYỄN
RELATED NEWS

Flexibility in construction of Quang Ngai - Hoai Nhon expressway

|

Quang Ngai - Hoai Nhon Expressway mobilizes maximum human resources and construction equipment even during the rainy season to ensure project progress and quality.

Hanoi and Ho Chi Minh City are special provincial-level administrative units

|

The Government has just issued Decree 307/2025/ND-CP regulating the classification of administrative units.

Updated gold price at the end of the session on November 28: Domestic gold increased sharply

|

Updated gold price at the end of the session on November 28: SJC gold bars and plain round gold rings increased in price simultaneously.

Visit to Egypt to expand cooperation between Vietnam - Egypt Trade Union

|

At the invitation of the Egyptian Union of Trade Unions (ETUF), the Vietnam Trade Union Delegation visited and worked in Egypt from November 23 to 26.

HCMC sprints to build a new land price list to be applied from 2026

|

HCMC - Leaders of departments, branches and localities are responsible if there is a delay in developing and announcing the first land price list to be applied from January 1, 2026.

Surprisingly, Vietnamese people were elected as members of the US National Academy of Creative Arts

|

Good news and pride from the United States, when a Vietnamese professor becomes a member of the US National Academy of Inventors ( NAI).

The Executive Committee of the Trade Union of Lao Dong Newspaper for the 2025-2030 term consists of 9 members

|

On November 28, the Trade Union Congress of Lao Dong Newspaper for the 2025-2030 term took place at the headquarters of Lao Dong Newspaper.

Live football U17 Vietnam vs U17 Macau (China)

|

Live football U17 Vietnam and U17 Macau (China) in the U17 Asian qualifiers, taking place at 19:00 today (November 28).

Flexibility in construction of Quang Ngai - Hoai Nhon expressway

VIÊN NGUYỄN |

Quang Ngai - Hoai Nhon Expressway mobilizes maximum human resources and construction equipment even during the rainy season to ensure project progress and quality.

Làm chủ công nghệ xây hầm cao tốc Quảng Ngãi – Hoài Nhơn

VIÊN NGUYỄN |

Đơn vị thi công cao tốc Quảng Ngãi – Hoài Nhơn đã cải tiến công nghệ thi công hầm nhằm rút ngắn tiến độ hoàn thành.

Cao tốc Quảng Ngãi - Hoài Nhơn tăng tốc ngay cả trong dịp lễ

VIÊN NGUYỄN |

Kỳ nghỉ lễ Quốc khánh 2.9 kéo dài 4 ngày. Tuy nhiên, hàng nghìn kỹ sư, công nhân vẫn miệt mài làm việc xuyên lễ trên cao tốc Quảng Ngãi - Hoài Nhơn.