Land clearance problems affect project progress
On October 2, Mr. Nguyen Viet Hung - Deputy Minister of Construction had a working session with the People's Committee of Quang Ngai province and related units to direct the removal of existing problems and obstacles on the main route of the Quang Ngai - Hoai Nhon expressway project.

Reporting at the meeting, Mr. Ngo Truong Nam - General Director of Deo Ca Group Joint Stock Company said that the unit strives to complete the 50km section of the project by October 30, 2025 and complete the entire route by the end of 2025 (except tunnel No. 3).
However, according to Mr. Nam, the current big obstacle is the situation that people hinder the construction and establishment of a camp for guarding people all day and night. At the point of Km41 Deo Eo Gio (Nguyen Nghiem commune), the situation of serious disorder and disorder should be almost "rule" in recent years.
Mr. Nam said that resolving people's petitions is legitimate and necessary, but on the basis of the law. To ensure legality and avoid further obstruction of people, it is recommended that the locality support the organization of dialogues with the people.
According to Mr. Le Thang - Director of Project Management Board 2, if the site is not cleared before October 15, 2025, it will be very difficult to ensure progress because the rainy season cannot be paved with asphalt concrete simultaneously.
It is known that out of 9 commune-level localities where the project passes through, there are currently 5 localities that have not completed site clearance, including the communes of Dinh Cuong, Lan Phong, Nguyen Nghiem, Khanh Cuong and Duc Pho ward with 14 locations, including some locations with long-term problems, but slow to resolve, affecting the overall progress of the project.
Mr. Nguyen Ngoc Sam - Vice Chairman of the People's Committee of Quang Ngai province suggested that investors and contractors coordinate with localities to organize dialogues with people and make clear commitments on the time frame for each specific case to both persuade on the basis of law and propagate so that people can understand clearly. Thereby, the problem of land clearance is completely eliminated.
The province will continue to direct relevant units to focus and completely resolve the problems and difficulties to hand over the remaining site of the project.
Must ensure people's consensus
Mr. Nguyen Viet Hung emphasized: "The parties must focus highly, completely resolve the site, ensuring that the site problems must be completely resolved by October 15, 2025 at the latest so that the contractor can complete the project by the end of December 2025 as directed by the Prime Minister.

Mr. Nguyen Viet Hung suggested that, to ensure the consensus of the people and ensure legal regulations during the appraisal and payment of support and compensation, investors and contractors need to develop a feasible plan, the date and time of appraisal, the date and time of payment, commit to progress, and commit to payment time points.
"Meeting to mobilize and propagate for people to hand over the site, without obstructing the construction, we must ensure the timeline, this week assess which houses and localities are specific and coordinate with local authorities to implement. Say it once, not repeat it, you must make a specific commitment based on your ability" - Mr. Hung expressed.
Regarding construction work, Deputy Minister Nguyen Viet Hung requested contractors and investors to speed up construction progress, especially in sections that are not entangled but the progress has not been met. Focus on completing each item on the construction site and disbursing and finalizing.
Closely coordinate with localities in appraisal and compensation payment on the basis of legal regulations.