The site of the nearly 1,500 billion VND dam project in Quang Ngai is deserted

VIÊN NGUYỄN |

Quang Ngai - The Tra Khuc River downstream dam project is expected to be completed in 2021, but is still unfinished, the construction site is deserted.

The Tra Khuc River Dam Dam project was started in July 2019 with a total investment of nearly VND 1,500 billion, expected to be completed in 2021, invested by the Project Management Board of Traffic works in Quang Ngai province. This is one of the key projects of Quang Ngai province, with the goal of defending the country, creating urban landscapes, developing riverside areas, raising the stature for Quang Ngai City ... However, the project encountered many problems, causing the completion progress to be extended from 2021 to 2023 and continue to expand to August, 2024. However, up to now, the project is still in a state of "covering the mat".

As noted by the reporter, at this time, Quang Ngai was sunny very convenient for the construction of the remaining items of the project, but on the project of a trillion dong project, there was no shadow of workers working. Many items have been completed but lying down in the rain and sun for many years, being seriously degraded.

One of the main reasons for the project's delay over the years is because the province has not yet completed the relocation and resettlement work for many households affected by the Tra Khuc River dam. Many areas of land of households have not been cleared.

Sharing with reporters at the first quarter press conference on 8.4.2024, the leader of Quang Ngai province said that the project of offering the downstream of Tra Khuc River continues to be implemented, but it is necessary to ensure synchronization with other projects to offer to promote the effect. In particular, the project of centralized wastewater collection and treatment system in Quang Ngai City is being designed and implemented by the province.

However, according to the reporter's research, the wastewater collection and treatment system project in Quang Ngai City, with a total investment of up to VND1,000 billion and expected to be implemented from 2024 to 2027, is still only on... paper.

On April 8, 2025, a reporter from Lao Dong Newspaper contacted the investor to learn about the project implementation situation in the coming time but has not yet received a response.

Du an lien tuc cham tien do, nhieu hang muc hoan thien dang nam phoi nang, mua. Anh: Vien Nguyen.
The project is continuously behind schedule, many completed items are exposed to the sun and rain. Photo: Vien Nguyen.

Nha dieu hanh du an xay dung dang do, bo hoang nhieu nam. Anh: Vien Nguyen
The project operator has been unfinished and abandoned for many years. Photo: Vien Nguyen
Nha o cua cac cong nhan thi cong du an chi lac dac vai nguoi ta tuc. Anh: Vien Nguyen.
The houses of the project construction workers are sparsely populated with only a few people. Photo: Vien Nguyen.
Nhieu khoi be tong da hoan thien nhung chua co mat bang de dua vao su dung, nam ngon ngang nhieu nam trong cong truong. Anh: Vien Nguyen
Many concrete blocks have been completed but there is no site for use, lying around for many years on the construction site. Photo: Vien Nguyen
Cong truong vang lang, khong mot bong nguoi. Anh: Vien Nguyen.
The construction site is quiet, with no one. Photo: Vien Nguyen.
May moc trong cong truong du an nam phoi nang, mua. Anh: Vien Nguyen.
Machinery in the project site are exposed to the sun and rain. Photo: Vien Nguyen.
May moc bi gi set. Anh: Vien Nguyen.
Machinery rusted. Photo: Vien Nguyen.

May moc, thiet bi tren cong truong nam ngon ngang giong nhu dong phe lieu. Anh: Vien Nguyen.
Machinery and equipment at the construction site are lying around like a pile of scrap. Photo: Vien Nguyen.
Nhieu ho dan o xa Tinh An, TP Quang Ngai chua dong thuan voi phuong an boi thuong nen chua ban giao mat bang de thi cong du an. Anh: Vien Nguyen.
Many households in Tinh An commune, Quang Ngai city have not agreed with the compensation plan, so they have not yet handed over the site for project construction. Photo: Vien Nguyen.
Ong Tran Van Hoa o xa Tinh An, TP Quang Ngai yeu cau cac co quan chuc nang bo tri dat tai dinh cu thi gia dinh ong moi dong y thao do nha cua de ban giao mat bang thi cong du an. Anh: Vien Nguyen.
Mr. Tran Van Hoa in Tinh An commune, Quang Ngai city requested the authorities to arrange resettlement land before his family agreed to demolish the house to hand over the project construction site. Photo: Vien Nguyen.
VIÊN NGUYỄN
TIN LIÊN QUAN

Confused when implementing, many key projects in Quang Ngai are sluggish

|

Many key projects in Quang Ngai province are behind schedule, causing difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.

900 billion VND project in Quang Ngai struggles despite no shortage of money

|

The implementation of the coastal road project in Quang Ngai is being delayed due to the low handover area...

The 3,500 billion VND project in Quang Ngai is facing difficulties due to lack of land

|

The construction of the Hoang Sa - Doc Soi road project in Quang Ngai is delayed due to the low and not seamless site clearance.

Close -up of T3 Tan Son Nhat station nearly 11,000 billion inaugurated on April 19

|

Ho Chi Minh City - T3 Terminal of Tan Son Nhat Airport has a total investment of nearly 11,000 billion VND, is the largest domestic station in the country, will officially inaugurated on April 19.

Reappointed Major General Hua Van Tuong as Deputy Commander of Military Region 5

|

The Prime Minister re -appointed Major General Hua Van Tuong as Deputy Commander of Military Region 5.

Gold price is peaked over 115 million VND/tael, people in Ho Chi Minh City still buy

|

Ho Chi Minh City - On April 16, the gold market in Ho Chi Minh City continued to witness the momentum, with SJC gold price reaching more than 115 million dong/tael.

Ho Chi Minh City will adjust the boundary of the ward overlapping with Binh Duong province

|

Ho Chi Minh City - Thu Duc City consider adjusting the boundary of the ward overlapping with Binh Duong province as the National University of Ho Chi Minh City.

The Department of Food Safety proposes Hikid Milk advertising to violate regulations

|

The Department of Food Safety - Ministry of Health has just sent a written request to inspect and handle organizations and individuals that commit acts of advertising Hikid dairy products that violate regulations.

Confused when implementing, many key projects in Quang Ngai are sluggish

Viên Nguyễn |

Many key projects in Quang Ngai province are behind schedule, causing difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.

900 billion VND project in Quang Ngai struggles despite no shortage of money

VIÊN NGUYỄN |

The implementation of the coastal road project in Quang Ngai is being delayed due to the low handover area...

The 3,500 billion VND project in Quang Ngai is facing difficulties due to lack of land

VIÊN NGUYỄN |

The construction of the Hoang Sa - Doc Soi road project in Quang Ngai is delayed due to the low and not seamless site clearance.