Quang Ninh determined to complete site clearance for 22 key projects

Nguyễn Hùng |

Quang Ninh sets a target to complete site clearance (GPMB) for 22 key projects before September 2026.

Site clearance (GPMB) for the Hanoi - Quang Ninh high-speed railway project in Yen Tu ward is being quickly implemented, with working groups actively propagating and mobilizing people to hand over land. Up to now, 155/243 households have been counted, Yen Tu ward is determined to complete GPMB work ahead of schedule.

Mr. Bui Duc Anh - Vice Chairman of Yen Tu Ward People's Committee said that site clearance work began before the groundbreaking ceremony (April 12, 2026), and the entire political system has been mobilized. Yen Tu Ward sets a target to complete 100% of inventory work in May, approve the residential land compensation plan in June, and hand over the site to investors in July or August.

In addition to Yen Tu, other wards such as Mao Khe, Hoang Que, Uong Bi, Dong Mai, Ha An and Tuan Chau are also accelerating site clearance. Quang Ninh province has established a site clearance working group led by the Chairman of the Provincial People's Committee to remove difficulties for localities.

The project requires the recovery of about 273.13ha of land, affecting 1,825 households and 16 organizations. Quang Ninh province plans to allocate about 2,760 billion VND for site clearance work in the period 2026 - 2028, with 2,000 billion VND for 2026.

The high-speed railway project is one of the 22 key projects of Quang Ninh, striving to complete site clearance before September 2026. Other important projects include Song Khoai Industrial Park, Quang Ninh LNG Power Plant, Ha Long Xanh Urban Area, Tuan Chau Public Park and coastal connecting transport projects, industrial parks, and seaports.

The total area to be cleared for 22 projects is nearly 8,900ha, affecting nearly 16,000 organizations, households and individuals.

For the remaining workload, Quang Ninh province sets a target to basically complete site clearance for all key projects by September 2026.

Nguyễn Hùng
RELATED NEWS

Lao Cai accelerates site clearance for nearly 2,200 billion VND industrial park

|

Lao Cai - When put into operation, Tran Yen Industrial Park will create jobs for tens of thousands of workers, contributing 1,500 billion VND to the budget each year.

Paying more than 143 billion VND for site clearance of VSIP Thai Binh phase 2 project

|

Hung Yen pays more than 143 billion VND in compensation and site clearance support for 153 households, serving the VSIP Thai Binh industrial park phase 2 project.

Hanoi minimizes the application of coercive measures when site clearance

|

Hanoi - In the process of site clearance for projects, the Chairman of the City People's Committee requested to strengthen mobilization and persuasion of people, and minimize the application of coercive measures.

Trade unions only complete their tasks when they are a reliable support for workers

|

According to delegate Le Van Dai, trade unions can only complete their political tasks when workers find this place a reliable support.

Innovating trade union financial work to ensure sustainability and promote resource efficiency

|

This is the presentation of Mr. Nguyen Anh Tuan - Member of the Presidium of the Vietnam General Confederation of Labor, Chairman of the Hai Phong City Labor Federation at the XIV Vietnam Trade Union Congress, on the afternoon of June 4, 2026.

The most solid "remote defense line" to protect workers

|

The Vietnam Electricity Trade Union determines that close participation in law-making and supervision is the most solid "distant defense line" to protect workers.

Trade unions must become pioneers in promoting science and technology

|

Faced with the wave of artificial intelligence, the Vietnam Trade Union needs to help workers access new knowledge, improve skills and adapt to development requirements.

Deeper understanding of the role of grassroots trade union officials

|

Thanh Hoa - Attending and following the opening session of the 14th Vietnam Trade Union Congress, union members and trade union officials are more deeply aware of the role of the grassroots level.

Lao Cai accelerates site clearance for nearly 2,200 billion VND industrial park

Duy Dũng |

Lao Cai - When put into operation, Tran Yen Industrial Park will create jobs for tens of thousands of workers, contributing 1,500 billion VND to the budget each year.

Paying more than 143 billion VND for site clearance of VSIP Thai Binh phase 2 project

Hà Vi |

Hung Yen pays more than 143 billion VND in compensation and site clearance support for 153 households, serving the VSIP Thai Binh industrial park phase 2 project.

Hanoi minimizes the application of coercive measures when site clearance

HOÀI ANH |

Hanoi - In the process of site clearance for projects, the Chairman of the City People's Committee requested to strengthen mobilization and persuasion of people, and minimize the application of coercive measures.