Sa Pa airport continues to be motionless after 4 years of groundbreaking

Đinh Đại |

Lao Cai - 4 years after the groundbreaking ceremony in March 2022, the progress of the Sa Pa airport project (Sa Pa Airport) has not changed much.

Recorded at the beginning of March 2026, the planned construction area of Sa Pa Airport in Bao Ha commune, Lao Cai province has only formed a resettlement area, and the main items of the airport have not yet been started.

Through research, the Sa Pa Airport project was approved for investment policy by the Prime Minister in 2021, with a total capital of nearly 7,000 billion VND in PPP form, of which state capital accounts for more than 49%. The scale of use is about 371ha of land.

On March 3, 2022, Lao Cai Provincial People's Committee held the groundbreaking ceremony of Sa Pa airport with the expectation of becoming a bright spot connecting traffic in the Northwest region with all regions of the country.

Khu vực xã Cam Cọn cũ (nay là Bảo Hà) được quy hoạch xây Cảng hàng không Sa Pa. Ảnh: Đinh Đại
Bao Ha commune area is planned to build Sa Pa airport. Photo: Dinh Dai

The project is divided into two phases. Phase 1 builds an airport meeting 4C standards and a grade II military airport, with a capacity of 1.5 million passengers per year. Phase 2 completes the items to increase the capacity to 3 million passengers/year.

The project implementation period is 50 years, including 4 years of construction and 46 years of exploitation and capital recovery. However, the biggest bottleneck still lies in the investor selection stage.

Khu tái định cư đã hiện hình với những ngôi nhà khang trang từ sự đồng thuận di dời để bàn giao mặt bằng của người dân. Ảnh: Đinh Đại
The resettlement area has taken shape with spacious houses from the consensus of relocation to hand over land by people. Photo: Dinh Dai

Mr. Nguyen Van Tan (resident of Bao Ha commune) said wearily: "Our people have heard about this Sa Pa airport project for many years. But for many years, after people agreed to hand over houses and land to serve construction, there has been no movement so far.

According to Mr. Tan, the smooth site clearance has shown the support of people in the commune. Therefore, people hope that the project needs to be accelerated in progress and the process of finding investors to create stability for economic development.

Từ trường học đến nhà dân đều đã giải phóng xong mặt bằng. Ảnh: Đinh Đại
From schools to people's houses, the ground has been cleared. Photo: Dinh Dai

Similarly, Ms. Bui Thi Diu (resident of Bao Ha commune) expressed: "People strongly support the airport construction project, which is reflected in the extremely favorable site clearance. When put into operation, the project helps attract tourists and investors to develop tourism and economy for the locality. However, many years have passed, the project is still only at the groundbreaking stage, so I don't know if the project can continue to be implemented or will be abandoned.

According to information from the Lao Cai Provincial Traffic Construction Investment Project Management Board, at the end of 2021, the province announced a survey of investor interest. At that time, two businesses expressed interest: Fansipan Sa Pa Cable Car Tourism Service Co., Ltd. (under Sun Group) and T&T Group Joint Stock Company.

2 lần mời thầu và 2 lần gia hạn nhưng dự án vẫn chưa tìm được nhà đầu tư. Ảnh: Đinh Đại
2 bidding invitations and 2 extensions, but the project has not yet found an investor. Photo: Dinh Dai

In May 2022, the bidding documents for Component Project 2 were approved and issued. Although the bid closing time was extended, no investors submitted documents. The second bidding invitation at the end of 2022 also fell into a similar situation, even after further extension.

Thus, after 2 bidding invitations and 2 extensions, finding investors is still difficult.

Mr. Nguyen Thanh Cong - Vice Chairman of Bao Ha Commune People's Committee - said that the locality is implementing site clearance phase 2 and arranging resettlement for affected households. As for the construction deployment time, the commune does not know because it is under the provincial authority.

Dự án Cảng hàng không Sa Pa được thực hiện cạnh cao tốc Nội Bài - Lào Cai. Ảnh: Đinh Đại
Sa Pa Airport Project is implemented next to the Noi Bai - Lao Cai expressway. Photo: Dinh Dai

Leaders of the Lao Cai Provincial Traffic Construction Investment Project Management Board further informed that site clearance work is still being maintained in parallel with the coordination of ministries and sectors to find investors.

In 2025, the project still cannot start because the investor has not been selected. Hopefully, in 2026, there will be a unit with sufficient capacity and determination to implement the project," this person said.

Đinh Đại
RELATED NEWS

Lao Cai Secretary inspects Sa Pa airport project worth 7,000 billion VND

|

Lao Cai - Through on-site inspection, the Provincial Party Secretary requested businesses to carefully study the land fund and route connecting from the airport to Sa Pa.

Sa Pa Airport continues to bid after 2 times of not finding an investor

|

Lao Cai - After 3 years of groundbreaking, Sa Pa airport has not yet found an investor and is preparing to invite bids for the third time.

After 3 years of construction, Sa Pa airport still has soldiers stationary

|

Lao Cai - After 3 years of construction, the progress of Sa Pa airport construction is still only at the completion stage of the resettlement area.

Bao Loc Temple: Printing seals in forbidden palaces, suggesting "offering more freely

|

The person who made the seal in the "forbidden palace" of Bao Loc Temple (Ninh Binh province) said "willingly offering more" after the reporter only gave 20,000 VND.

Sa Pa airport continues to be motionless after 4 years of groundbreaking

|

Lao Cai - 4 years after the groundbreaking ceremony in March 2022, the progress of the Sa Pa airport project (Sa Pa Airport) has not changed much.

Rose in the middle of summer" and the reason why short films force viewers to spend money

|

From a few-minute clip on social networks, many viewers are gradually drawn into the world of mini-dramas and short films like "Roses in the middle of summer".

Spain denies US cooperation claim

|

Spain denies US concession information after trade warning.

Trade union news: Appropriate pension increase for retirees before 1995

|

Trade union news bulletin includes: Increasing pensions for retirees before 1995; Requesting businesses not to work overtime on March 15 for workers to vote...

Lào Cai thúc tiến độ khởi công sân bay Sa Pa trong quý 4 năm 2025

Đinh Đại |

Lào Cai - Tỉnh đang đẩy nhanh lựa chọn nhà đầu tư, với mục tiêu khởi công sân bay Sa Pa trong quý 4 năm 2025.

Lao Cai Secretary inspects Sa Pa airport project worth 7,000 billion VND

Văn Đức - Đinh Đại |

Lao Cai - Through on-site inspection, the Provincial Party Secretary requested businesses to carefully study the land fund and route connecting from the airport to Sa Pa.

Sa Pa Airport continues to bid after 2 times of not finding an investor

Đinh Đại |

Lao Cai - After 3 years of groundbreaking, Sa Pa airport has not yet found an investor and is preparing to invite bids for the third time.

After 3 years of construction, Sa Pa airport still has soldiers stationary

Đinh Đại |

Lao Cai - After 3 years of construction, the progress of Sa Pa airport construction is still only at the completion stage of the resettlement area.