After 3 years of construction, Sa Pa airport still has soldiers stationary

Đinh Đại |

Lao Cai - After 3 years of construction, the progress of Sa Pa airport construction is still only at the completion stage of the resettlement area.

Ngay 21.10.2021, Thu tuong ban hanh quyet dinh chu truong dau tu du an xay dung cang hang khong Sa Pa, Lao Cai voi tong muc dau tu hon 6.948 ti dong.
On October 21, 2021, the Prime Minister issued a decision on investment policy for the Sa Pa airport construction project, Lao Cai with a total investment of more than VND 6,948 billion.
Dia diem xay dung cang hang khong Sa Pa duoc xac dinh o mot so thon Con 2, Con 1, Cam Con... xa Cam Con, huyen Bao Yen. Dien tich su dung dat la 371 ha.
The construction location of Sa Pa airport is determined in some villages of Con 2, Con 1, Cam Con... Cam Con commune, Bao Yen district. The land use area is 371 hectares.
Thon Cam 2 thuoc dien giai phong mat bang de phuc vu xay dung. Du an duoc phan ky dau tu theo 2 giai doan, trong do giai doan 1 - xay dung cang hang khong Sa Pa dat tieu chuan cang hang khong cap 4C va san bay quan su cap II, dat cong suat 1,5 trieu hanh khach/nam; giai doan 2 se hoan thanh cac hang muc cua du an de dat cong suat 3 trieu hanh khach/nam.
Cam 2 Village is subject to site clearance for construction. The project is divided into 2 investment phases, in which phase 1 - construction of Sa Pa airport to meet the standards of a level 4C airport and a level II military airport, reaching a capacity of 1.5 million passengers/year; phase 2 will complete the project items to reach a capacity of 3 million passengers/year.
Mot goc khu tai dinh cu Cam Con. Thang 4.2020, khu tai dinh cu cang hang khong Sa Pa bat dau duoc trien khai xay dung. Cong trinh co tong muc dau tu 409,9 ti dong, trong do chi phi xay dung la 221,5 ti dong, chi phi giai phong mat bang la 139,5 ti dong, con lai la cac chi phi khac.
In the photo is a corner of Cam Con resettlement area. In April 2020, the Sa Pa airport resettlement area began construction. The project has a total investment of 409.9 billion VND, of which the construction cost is 221.5 billion VND, the site clearance cost is 139.5 billion VND, the rest is other costs. In the new place, spacious, large and modern houses have gradually sprung up right in the path.
San bay Sa Pa duoc xay dung canh cao toc Noi Bai - Lao Cai (ben phai) de tao thuan loi cho viec di chuyen.
Sa Pa airport was built next to the Noi Bai - Lao Cai expressway (opposite) to facilitate travel.
De thuc hien du an, hon 200 ho dan nam trong pham vi giai phong mat bang da duoc chuyen ve noi noi tai dinh cu moi. Nhieu nha o cu da bo khong hoac bi pha huy de phuc vu lam san bay.
On February 18, according to the reporter of Lao Dong Newspaper, to implement the project, more than 200 households within the clearance area have been moved to new resettlement areas. Many old houses have been abandoned or destroyed to serve as airports.
Mot dia diem tung duoc dung lam noi o de phuc vu cong tac giai phong mat bang nay da hoang vang. Xung quanh khu vuc, cua vao mo toang, la kho roi day san.
A location that was once used as a place to serve site clearance is now deserted. Around the area, the entrance is wide open, with dry leaves falling all over the yard.
Khong chi ngoi nha nho lup xup ma ca nhung ngoi nha gach kien co cung bi bo lai sau khi co du an lam san bay.
Not only the small, dilapidated house but also the solid brick houses were left behind after the airport project was built.
Cac diem truong hoc cung thuoc dien giai phong mat bang nen da khong con hoc sinh den hoc.
The schools are also subject to site clearance, so there are no more students coming to school.
Nguoi dan di lai tren duong san bay Sa Pa bi sat lo sau mua lu va hien chua the khac phuc.
Ahead is a part of the Sa Pa airport bypass road that was eroded after floods, but people still have to travel through it every day because it has not been repaired.
Nhung ke tu lan dong tho du an vao nam 2022, den nay da la dau nam 2025, sieu du an san bay gan 7.000 ti dong nay van nam im bat dong. Nguyen nhan duoc cho la chua tim duoc nha dau tu do doanh nghiep thay tien dau tu lon, kho co lai nen khong lam.
But since the groundbreaking ceremony in 2022, until the beginning of 2025, this nearly 7,000 billion VND airport super project has remained motionless. The reason is that investors have not been found because businesses see a large investment and it is difficult to make a profit, so they do not do it.
Lanh dao So Giao thong van tai Lao Cai thong tin: “Viec khoi cong xay dung trong nam 2024 va hoan thien vao giua nam sau la khong the. Chung toi dang phan dau thu hut duoc nha dau tu de dau nam 2025 co the khoi cong du an“.
The leader of Lao Cai Department of Transport informed: "It is impossible to start construction in 2024 and complete it in the middle of next year. We are striving to attract investors so that we can start the project in early 2025". Photo: Dinh Dai
Đinh Đại
TIN LIÊN QUAN

Northwest end of day: Sa Pa airport bypass landslide

|

Landslide on Sa Pa airport bypass; Termination of billion-dollar steel project; Queuing in cold rain to buy tickets for Vietnam - Indonesia match are some of the highlights.

Sa Pa Airport construction schedule delayed by another year

|

Lao Cai - Since breaking ground in 2022, the 7,000 billion VND Sa Pa airport construction project has continued to miss its scheduled start date.

10 police officers in Hanoi ask to hold lower positions

|

Hanoi - 10 Department Heads and District Police Heads voluntarily applied to hold positions lower than the positions they are holding after streamlining the apparatus.

Where each household has a railway crossing in Hanoi

|

Hanoi - On Ngoc Hoi Street (Thanh Tri District), there is a residential area where each household has its own access to the railway.

Pi digital money is priced, Pi players still find it difficult to sell

|

Pi Digital currency has been officially listed, however, many "Pi players" despite owning thousands of Pi digital currency have not been able to participate in buying and selling.

Investigation of signs of violations of a residential area project in Thanh Hoa

|

Thanh Hoa province has just directed the relevant authorities to urgently provide full documents related to the Dong Tho residential area project, Thanh Hoa city.

Mr. Nguyen Van Duoc becomes Chairman of the Ho Chi Minh City People's Committee

|

HCMC - With the majority of votes, Mr. Nguyen Van Duoc - Deputy Secretary of the HCMC Party Committee was elected to hold the position of Chairman of the HCMC People's Committee for the 2021 - 2026 term.

Districts and communes subject to merger in the 2026 - 2030 period

|

District and commune-level administrative units that do not meet the standards of corresponding administrative units will be subject to arrangement and merger in the period of 2026 - 2030.

Northwest end of day: Sa Pa airport bypass landslide

NHÓM PV |

Landslide on Sa Pa airport bypass; Termination of billion-dollar steel project; Queuing in cold rain to buy tickets for Vietnam - Indonesia match are some of the highlights.

Sa Pa Airport construction schedule delayed by another year

Đinh Đại |

Lao Cai - Since breaking ground in 2022, the 7,000 billion VND Sa Pa airport construction project has continued to miss its scheduled start date.

2 lần mời thầu vẫn "ế", sân bay Sa Pa lại lỗi hẹn khởi công

Đinh Đại |

Lào Cai - Sau ba năm kể từ khi được phê duyệt chủ trương đầu tư, dự án xây dựng sân bay Sa Pa 7.000 tỉ đồng vẫn khó thể khởi công trong năm 2024 như mong muốn.